HomeMy WebLinkAbout08/20/2013 Repair & Preventative Maintenance of Village Hall Parking GarageMount A ?/ Mount Prospect Public Works Department INTEROFFICE MEMORANDUM TO: VILLAGE MANAGER MICHAEL E. JANONIS FROM: SUPERINTENDENT OF STREETS & BUILDINGS DATE: AUGUST 13, 2013 SUBJECT: SEALED BID RESULTS FOR THE REPAIR AND PREVENTATIVE MAINTENANCE OF THE VILLAGE HALL PARKING GARAGE (NOT TO EXCEED $46,000) BACKGROUND In the current budget, staff has requested funds for repair and preventative maintenance of the Village Hall parking garage. The work will include, but not be limited to: • rout, clean, caulk double tee joints and floor cracks • repair floor spalls and delaminating • vertical and overhead concrete repairs including soffit and parapet wall spalls • replacement of cove joint along the Village Hall building east side wall • perform any and all other additional work, as required by the Director of Public Works, for the unit costs indicated on the bid sheet • pressure wash and paint the interior walls, ceiling and floor sealing, one level or about 100 spaces The Village hired Desman Associates of Chicago, Illinois to design and prepare the bid documents, oversee the bid opening and supervise construction of the project. Desman is an architectural engineering firm that specializes in parking structures and performed the original design and construction management services for the Village Hall Parking Deck project in 2003. The contract is for 2013 and also includes an optional second year (2014) for the same prices if both parties agree. BID RESULTS Sealed bids were opened at 1:00 P.M. on August 5, 2013 for the proposed work. A bid notice was placed in the local paper and five concrete /restoration firms were invited to participate. Page 2 of 2 Repair and Preventative Maintenance of the Village Hall Parking Garage August 15, 2013 Bids were received. The results are as follows: Bidder Harry S. Peterson, Chicago, IL Takao Nagai Concrete Restoration, Chicago, IL *Golf Acquisitions Group, Hammond, IND. William Hach, Wood Dale, IL *No bid bond — bid not accepted per bid instructions DISCUSSION Bid Price $46,000 $47,850 $55,000 $57,273 The low bidder Harry S. Peterson has previously worked for the village in 2011 sealing the parking deck at the Police & Fire Headquarters and performed satisfactorily. All references were contacted and said that Harry S. Peterson completed their contracts satisfactorily and that they would hire them again. RECOMMENDATION Staff recommends the Village Board award a contract for repair to the Village Hall Parking Deck in 2013 with an option for a second year to the lowest cost proposal as submitted by Harry S. Peterson, Chicago, Illinois. The first year would be in the amount not to exceed $46,000. Sufficient funds for this proposed expenditure exist in the current budget. Subsequent awards would be in amounts appropriated in the 2014 budget. Paul Bures Superintendent of Streets & Buildings I concur: Sean P. Dor ey Director of Public Wor s c: Director of Public Works Sean P. Dorsey Deputy Director of Public Works Jason Leib File