HomeMy WebLinkAbout06/18/2013 Stormwater Improvements Construction Engineering Services 2013Mount Prospect Public Works Department
t INTEROFFICE MEMORANDUM
TO: VILLAGE MANAGER MICHAEL E. JANONIS
FROM: DIRECTOR OF PUBLIC WORKS
DATE: JUNE 13, 2013
SUBJ: ACCEPT PROPOSAL FOR 2013 STORMWATER IMPROVEMENTS
CONSTRUCTION ENGINEERING SERVICES ($136,000)
Background
On August 16, 2011, the Village Board commissioned Burns & McDonnell Consulting Engineers of
Downers Grove, Illinois, to analyze the causes of flooding associated with a severe weather event
that occurred on July 23, 2011. Burns & McDonnell was also asked to identify cost - effective
recommendations to mitigate defined and recurrent flooding problems.
Burns & McDonnell's report was presented to the Village Board at the March 13, 2012 Committee of
the Whole meeting. Their findings and recommendations were subsequently discussed at several
public meetings throughout 2012.
On December 4, 2012, the Village Board authorized issuance of $2.5 million in general obligation
debt to facilitate the design and construction of specified Village -owned sewer system improvements
recommended in the Burns & McDonnell flood study report.
On December 18, 2012, the Village Board awarded a design engineering contract to Burns &
McDonnell for the preparation of plans, specifications, and bid documents necessary to construct
the Hatlen Heights Stormwater Improvements, Hatlen Heights Sanitary Improvements, Lonnquist
Stormwater Improvements, Lonnquist Combined Sewer Improvements, and the Lawrence Lane
Stormwater Improvements. These projects are presently scheduled for construction during summer
2013.
Staff has asked Burns & McDonnell to submit a proposal to provide construction engineering and
inspection services for the aforementioned projects.
Proposal
Burns & McDonnell has submitted a proposal to provide specified full -time construction engineering
and contract administration services for a not -to- exceed fee of $136,000. Attachment A details the
services included in the scope of work rendered for this fee.
Page 2 of 2
Accept Proposal for 2013 Stormwater Improvements Construction Engineering Services ($136,000)
June 13, 2013
Discussion
The fee requested by Burns & McDonnell represents approximately 7 -1/2% of the projected
construction costs ($1,804,518.37). It has been our experience that costs for full -time construction
engineering work typically range between 8 % -12% of construction costs. By comparison, Burns &
McDonnell's fee request seems reasonable and competitive.
Additionally, staff asked Burns & McDonnell to assign a senior level construction representative
(inspector) and a senior level construction engineer. Due to the high public profile of the
construction work, and the fact much of the work is sited in residential neighborhood near private
homes, staff feels that ample construction engineering experience and expertise is necessary to
successfully complete the project.
Finally, it is the opinion of staff that Burns & McDonnell is uniquely qualified to supervise the
construction of this project. As noted previously, Burns & McDonnell was extensively and intimately
involved in the public meetings, flooding study, and design work associated with this project. As a
consequence, we believe that they have a greater vested interest in the success of the project than
perhaps any other engineering firm.
Recommendation
I recommend accepting the proposal from Burns & McDonnell Consulting Engineers of Downers
Grove, Illinois for specified construction engineering services associated with the 2013 Stormwater
Improvements Project in an amount not to exceed $136,000. Sufficient funds for this proposed
expenditure exist in the current budget.
P. Dorsey
ATTACHMENT "A"
CONSTRUCTION ADMINISTRATION
AND
CONSTRUCTION ENGINEERING ACTIVITIES
A. CONSTRUCTION ADMINISTRATION
General The Construction Administrator will serve as the Village of Mount Prospect's
representative for the entire construction project as assigned by the Village. As such he
will function as an extension of the Village's staff and be responsible for overall
implementation and management of the project. The Construction Administrator will
provide all Level 1 management services. These services are defined as all management
functions and requirements over and above the daily routine project requirements. They
will include implementation of Village policies, program administration, coordination
and monitoring of consultants and contractors providing overall management control
and direction to insure completion of the construction project in accordance with the
Village's objectives of cost, time and quality. The Construction Administrator will
work closely with and report to the Director of Public Works or his designee.
2. Specific Duties and Responsibilities
a. Project Control
Establish and maintain lines of communication, authority, and procedures for
coordination among the Village, Director, Design Engineer, Contractors, and
Construction Engineer as needed to carry out the project construction
requirements.
b. Additional Services
When required, identifies the need for, and assists the Village in selecting and
retaining professional services of a surveyor, testing laboratories and other special
consultants, and coordinates these services during their performance.
c. Contract Requirements
Administrates and monitors for the Director, contractors and other project
consultants, the contractual requirements for items such as insurance, bonds, and
general conformance with governmental regulations, including minority
compliance.
d. Construction Monitoring
Monitors the work of contractors and construction engineer to insure adequate
quality control of the construction work and compliance with the design drawings,
specifications and other required regulations.
Page 1 of 6
e. Scheduling
Works with the contractor and Construction Engineer to insure that a workable
construction schedule is developed and agreed to by all parties. Provide for
continuous monitoring of the schedule as construction progresses. Identify potential
variances between scheduled and probable completion dates. Review schedule for
work not started or incomplete and recommend to the Director, Construction
Engineer and contractors, adjustments in the schedule to meet the probable
competition date. Provide summary reports of each monitoring and document all
changes in schedule.
Together with the Construction Engineer determine the adequacy of the contractor's
personnel and equipment and the availability of materials and supplies to meet the
schedule. Recommend courses of action to the Director when requirements of a
contract are not being met.
f. Administration
Handle all project administrative correspondence including preparation of all
written documents and correspondence requiring the Village's and Director's
signature and authorization. Maintain a file on all project correspondence and
records to include daily construction reports prepared by the Design Engineer's
field Construction Engineer.
g. Contractor's Payment
Review and process for payment, through the Director, all applications by
contractors and design consultants for progress and final payments.
i. Change Orders
Recommend necessary or desirable changes to the Director and the Design
Engineer, review requests for changes, and handle all administrative aspects to
include contractor negotiations, formal preparation and submission with
recommendation to the Director.
j. Cost Control
Monitors all project costs and revises and refines the initially approved changes as
they occur, and develop cash flow reports and forecasts as needed.
k. Job Meetings
Conduct periodic (biweekly in general) progress meetings with all associated
parties to review construction progress, procedures, scheduling, design
interpretation, problem areas and overall coordination.
Page 2 of 6
1. Reports
Provide a timely weekly status reporting system to keep the Village abreast of all
aspects of the project which will: a) emphasize problem areas to the Director on a
by- exception basis; and b) present solutions for the problems which will enable
management to make decisions on a go- or -no -go basis.
m. Public Information
Provides advance and current information to the public as necessary and
appropriate. Works with citizens directly impacted by contractor to protect
citizen's interests.
n. Final Completion
Together with the Design Engineer and Construction Engineer conduct and
develop a pre -final inspection and develop a pre -final punchlist for the contractor.
Upon competition of the pre -final punchlist notify the Director that a final
inspection is in order. Attend the final inspection with the Village and contractors.
Advise the Director when all punchlist work resulting from the final inspection
has been completed. Recommend, prepare, and process all final pay estimates
through the Director.
o. As -built Drawings
Review as -built drawings prepared by the Design Engineer to insure adequate
information has been given to facilitate on -going maintenance work by the
Village.
B. CONSTRUCTION ENGINEER
General The Design Engineer may serve as the Village's on -site construction
representative for the construction project as the Construction Engineer. He will be
responsible for the general control and field inspection of the construction project and
will provide all Level 2 management services. These services are defined as all
management functions required for day to day control of the project. They will include
field inspection, design interpretation, contract administration and general coordination
and control of the day to day construction activities of the contractor to insure timely
completion and quality construction in strict compliance with contract drawings and
specifications. The Construction Engineer will work closely with and report to the
Construction Administrator.
Page 3 of 6
2. Specific Duties and Responsibilities
a. Liaison and Contract Control:
Assist the contractors in understanding the intent of the contract documents. Serve
as the Village's representative with the contractors working principally through
the contractor's project engineer and on -site superintendent. Serve as the Village's
liaison with other local agencies, utility companies, state agencies, businesses, etc.
keeping them advised of day to day activities.
b. Review of Work, Rejection of Defective Work, Inspection and Testing
1) Conduct on -site observations of the work in progress to determine that the
project is proceeding in accordance with the contract documents and that
completed work will conform to the requirements of the contract documents.
2) Instruct contractor to correct any work believed to be unsatisfactory, faulty or
defective or does not conform to the requirements of the contract documents, or
does not meet the requirements of any inspections, tests or approval required to be
made; and advise Construction Administrator of action taken and if any special
testing or inspection will be required.
3) Verify that tests are conducted as required by the contract documents and in
presence of the required personnel, and that contractors maintain adequate record
thereof; observe, record and report to Construction Administrator appropriate
details relative to the test procedures.
4) Perform or cause to have performed as applicable, all required field tests such as
concrete tests, soil compaction tests and insure such tests are made by as may be
specified. Analyze the results of all field and laboratory tests to determine the
suitability of materials tested.
5) Accompany visiting inspectors representing public or other agencies having
jurisdiction over the project, record the outcome of these inspections and report to
Construction Administrator.
Contractors Suggestions and Requests
Consider and evaluate suggestions and requests for modifications in drawings
and specifications which may be submitted by the contractor and make
recommendations to the Construction Administrator with any time and cost
implications for final decision.
Page 4 of 6
d. Schedules
Review construction schedule and schedule of values prepared by the contractor.
Be alert to the construction schedule and to the conditions which may cause
delay in completion and report same to the contractor and the Construction
Administrator in sufficient time to make adjustments.
e. Conferences
1) Attend periodic progress meetings scheduled by the Construction Administrator
with all associated parties to review the overall project status and problems.
f. Contract Administration and Records
1) Handle all day to day contract administration and associated correspondence in
accordance with the established procedures.
2) Maintain at the job site orderly files for correspondence, reports of job
conferences, reproductions of original contract documents including all addenda,
change orders, field orders, additional drawings issued subsequent to the
execution of the contract documents, progress reports, and other project related
documents.
3) Keep a diary or log book, recording contractor's hours on the job site, weather
conditions, data relative to questions of extras or deductions, list of visiting
officials, daily activities, decisions, observations in general and specific
observations in more detail as in the case of observing test procedures.
4) Record names, addresses and telephone numbers of all contractors, sub-
contractors and major suppliers of equipment and materials.
g. Reports
Furnish Construction Administrator written reports as required of progress of the
work and contractor's compliance with the approved progress schedule.
Contractors Payment Requisition
Review applications for payment with contractor for compliance with the
established procedure for their submission and forward them with
recommendations to Construction Administrator, noting particularly their relation
to the schedule of values, work completed and materials and equipment delivered
to the site.
Page 5 of 6
j. Governmental Policies
Review contractor EEO policies and other governmental mandated programs to
insure contractor compliance with the governing regulations.
k. Change Orders
Perform initial evaluation of change orders and submit same to Construction
Administrator with recommendation and cost estimate breakdown for final
approval and processing.
As -built Drawings
Maintain an accurate record of all field conditions and upon completion of the
project insure that the design drawings are revised to show the true as -built
condition.
m. Final - Completion
1) Together with the Construction Administrator conduct and prepare a pre -final
inspection and give to the contractor a pre -final punchlist. Thereafter insure that
the contractor completes same in an expeditious fashion. Notify the Construction
Administrator in writing when all work is completed and ready for final payment.
2) Together with the Construction Administrator conduct a final inspection with
the Village and the general contractor. Prepare a final punchlist and thereafter
insure that the contractor completes same in an expeditious fashion. Notify the
Construction Administrator in writing when all work is completed and ready for
final payment.
Page 6 of 6