HomeMy WebLinkAbout06/29/1993 COW agenda COMMITTEE OF THE WHOLE
PLEASE NOTE EARLY START TIME
AGENDA
Meeting Location: Meeting Date and Time:
Mount Prospect Senior Center Tuesday, June 29, 1993
50 South Emerson Street 7:00 P.M.
I. CALL TO ORDER - ROLL CALL
II. ACCEPTANCE OF MINUTES OF MAY 25, 1993
III. CITIZENS TO BE HEARD
Items IV and V were originally scheduled for discussion at the June 8 Committee of
the Whole meeting. Due to a storm-related power failure, that meeting was cancelled
and the items were deferred to this meeting.
IV. ST. EMILY'S STOPLIGHT DISCUSSION
Approximately 60 days ago, the Village was formally approached by representatives
from St. Emily's Elementary School requesting that the Village install a stoplight at
the intersection of Central Road and Horner Lane for the purpose of assisting with
the crossing of school children in the mornings and afternoons during the school
year. Based upon Police Department surveys and a recent study performed by the
Engineering Division, a total of eight (8) children cross from the south side of Central
Road in order to reach St. Emily's School. To the best of our knowledge all but one
of those children live in Des Plaines.
The request was based on the belief that traffic volumes and automobile speeds
made the crossing of Central Road a somewhat dangerous proposition. Currently,
the Village provides a Crossing Guard to assist school children in making their way
to the School. A study conducted by the Mount Prospect Police Department during
calendar year 1992 indicated that there was a justifiable safety concern. The
question of safety involves not only the school children but also extends to the
Crossing Guard. The initial Police Department conclusion was that these safety
concerns warranted the discontinuation of a Crossing Guard and implementation of
alternate modes of transporting the children to school.
While the safety of these school children is without question a vital concern, it is also
appropriate to look at the cost of providing the required measure of safety; how that
cost should be distributed and identify less costly alternatives that would provide at
least the same level of safety as the proposed stoplight.
The estimated cost of the stoplight is $120,000. Monthly maintenance would run
$100. Even with the stoplight, a Crossing Guard would still be required to monitor
the intersection at an annual cost of approximately $2,700.
Village Board members directed staff to study the situation further and present a
range of options. The information attached hereto will help to facilitate that
discussion. In addition to appropriate Village staff, Sister Danielle, Principal of St.
Emily's School, has been invited to attend along with the City Manager of Des
Plaines Walter Douthwaite.
V. POLICE AND FIRE HEADQUARTERS UPDATE
Since June 8, Police and Fire operations have moved to the new building. Staff is
busy settling in and becoming acclimated to the facility. Cut-over to the new Village
phone system was completed on June 22 with fine tuning continuing as needed.
Presented here for your review and approval is a Change Order in a not-to-exceed
amount of $34,265. The vast majority of the items address safety concerns. Over
half of the cost is attributable to three areas: The elevator, uninterrupted power
supply (UPS) and an attic smoke and fire detection system. All of the changes are
essential to the efficient long-term maintenance and operation of the building.
Your information package also contains final reconciliation costs associated with
previously approved Change Orders. Final costs were approximately $3,800 less
than the established "not-to-exceed" amounts. The attached Project Budget recap
continues to show the entire project to be substantially under the original
Referendum estimate.
Appropriate staff will be in attendance to answer your questions.
VI. PHASE III FLOOD CONTROL PROJECT UPDATE
This fiscal year, four major flood control projects were scheduled for construction:
(1) Des Plaines River Backwater Valves, (2) Prospect Manor/North Main sanitary,
(3) Hatlen Heights sanitary and (4) Fairview Gardens sanitary. All projects have
been under way since late March.
The Des Plaines River and Fairview Gardens projects have been substantially
completed. It appears that the Fairview Gardens Project will come in under budget
while the Des Plaines River project will be completed at a cost slightly above the
original estimate. A final Change Order on this latter project will be presented to the
Village Board at an upcoming meeting. Design errors on the Hatlen Heights project
have been previously reviewed by the Village Board and staff is currently working on
remedial plans per Board direction.
The Prospect ManodNorth Main Project had been progressing smoothly until the
recent discovery of a 1,350 foot section of extremely deteriorated existing combined
sewer pipe in the 400 and 500 blocks of North Emerson Street. This line currently
serves the neighborhood and was not scheduled for replacement or abandonment
as part of the Prospect Manor project. Due to its location relative to excavation for
the new relief line, serious concern exists that this pipe will collapse during
construction. Regardless, the pipe is in such bad condition that it would be prudent
to replace it now while the street is open. The estimated cost for said repairs is
approximately $115,000 plus engineering fees. Staff is researching whether the
costs will be eligible under the IEPA Loan Program.
The information package contains a detailed description of the problem along with
staff recommendations. Herb Weeks and appropriate staff will be in attendance to
facilitate discussion.
VII. DISCUSSION REGARDING POOL CAR FLEET MAINTENANCE
During the 1993-1994 Budget Hearings, the Board expressed an interest in
reviewing the Village's current Fleet Maintenance and Replacement Program. Staff
has conducted a preliminary review and several hours of discussion have taken
place. At this time, my conclusion is that the Program is adequately serving the
needs of the Village.
However, I feel that discussion at the Board level will be helpful in creating a better
understanding of the Program including its design, review criteria and subjective
components. The discussion will also allow Board members to pursue specific
areas of interest.
Discussion is limited to that portion of the Program covering automobiles; i.e.,
squads, staff cars and pool cars. Future discussion regarding specialized vehicles
and equipment will be discussed as part of individual Department reviews. Your
information package should provide a broad overview of the Program and
appropriate staff will be in attendance to facilitate discussion.
VIII. MANAGER'S REPORT
IX. ANY OTHER BUSINESS
X. ADJOURNMENT