HomeMy WebLinkAbout6. Village Manager's Report 09/04/2012Mount Prospect Public Works Department
?/ INTEROFFICE MEMORANDUM
t
TO: VILLAGE MANAGER MICHAEL E. JANONIS
FROM: WATER & SEWER SUPERINTENDENT
DATE: AUGUST 29, 2012
SUBJECT: BID RESULTS FOR GEORGE STREET NORTH SANITARY RELIEF
STATION PROJECT (CIP) - ($156,544)
Background
In the current budget, funds have been requested to rehabilitate the George Street
North Sanitary Relief Pumping Station.
This pumping facility is used to provide relief to the Village -owned sanitary sewer
system in the event that the Metropolitan Water Reclamation District of Greater Chicago
(MWRDGC) interceptor sewer becomes surcharged. The MWRDGC interceptor sewer
system accepts wastewater from Mount Prospect sewers and transports it to treatment
plants in Skokie or Des Plaines. During wet weather, interceptor sewers can become
full thereby limiting the rate at which they can accept gravity flow from local Mount
Prospect sewers. To mitigate the resultant surcharge conditions in our local sewers,
pumping stations were installed in some neighborhoods. These stations help prevent
the MWRDGC interceptors from backing -up into local sewers. They also help reduce
basement back -ups by pumping wastewater from our local sewers into the interceptors
under pressure.
The George Street North Relief Station is located in the George Street right -of -way just
north of Weller Creek. It was built in 1971 and has been repaired over the years as
needed. In 2010, a standby emergency generator with automatic transfer switch was
installed and is operational. This station provides sanitary sewer relief for the area from
Prospect Avenue to Weller creek, bounded by Edward Street to the west and Albert
Street on the east.
Staff created detailed bid specifications and bidding materials necessary to procure the
needed retrofits, services and equipment. The improvements include the installation of a
complete replacement pump station with new pumps, guide rails and controllers, along
with all associated wiring and other electrical control equipment. The stand -by
Page 2 of 3
Bid Results for George Street North Sanitary Relief Project (CIP) ($156,544)
August 29, 2012
generator and automatic transfer switch installed in 2010 are in excellent condition and
will not be replaced as part of this project.
Since these stations are permitted by the MWRDGC, staff worked closely with a
consulting engineer to ensure that the rehabilitation effort meets all permitting
requirements. This effort required that staff maintain the same horsepower rating for all
new pumps to match the existing permit. Staff also recommended standardizing pumps
and other equipment between the various stations. Staff feels that this is an important
aspect of the overall rehabilitation effort. This standardization effort allows staff to stock
fewer spare parts as the pumps and their fittings now will be interchangeable between
stations. In the past, pumps could not be interchanged in emergencies or required an
extensive amount of effort to accommodate different flanges or other fittings to make
them work for more than one station.
The Village owns and maintains eight (8) sanitary relief stations and two (2) sewage lift
stations. All of the sanitary relief stations operate in a manner similar to the George
Street North station. Lift stations serve a different purpose. Lift stations pump
wastewater from a lower elevation to a higher elevation so that it can be discharged to
an interceptor sewer. In future years, staff intends to rehabilitate all of the sanitary relief
and lift stations in the Village -owned wastewater collection system.
Bid Results
On Monday, August 27, 2012 at 1:00 P.M., sealed bids for the project were opened and
read aloud. Six (6) invitational bids were distributed and public notice was placed in a
local newspaper as required by law. Eight (8) additional bids were acquired by
unsolicited vendors. Four (4) bids were received. The bid result was as follows:
Discussion
The consultant and staff reviewed the bid submittals and find that the bidders meet the
intent of the specification, are qualified and are proposing similar equipment. Martam
Construction of Elgin, Illinois has worked with the Village in the past on numerous
projects. Martam's work for the Village has been timely and on budget. Staff finds that
Martam Construction of Elgin, Illinois is the lowest responsible bidder.
Bidder
Total
1
Martam Construction
Elgin, Illinois
$ 142,313.00
2
Marc Kresmery
Elgin, Illinois
$ 145,250.00
3
DiMeo Brothers
Elk Grove, Illinois
$ 199,500.00
4
Kovilic Construction
Franklin Park, Illinois
$ 247,200.00
Discussion
The consultant and staff reviewed the bid submittals and find that the bidders meet the
intent of the specification, are qualified and are proposing similar equipment. Martam
Construction of Elgin, Illinois has worked with the Village in the past on numerous
projects. Martam's work for the Village has been timely and on budget. Staff finds that
Martam Construction of Elgin, Illinois is the lowest responsible bidder.
Page 3 of 3
Bid Results for George Street North Sanitary Relief Project (CIP) ($156,544)
August 29, 2012
The project is scheduled to be completed and fully operational by late November. All
landscaping and any asphalt or concrete work will also be completed before the end of
the year.
Since the existing station will be replaced under this contract, there is always the
possibility of unforeseen issues arising during construction so staff is recommending the
inclusion of a 10% contingency ($14,231.00). This would make the total award for this
project $156,544 (base bid of $142,313 plus the 10% contingency of $14,231). The
engineer's estimate for the replacement project was $175,000.
Bid Recommendation
I recommend accepting the lowest qualified bid for the George Street North Sanitary
Relief Station Project as submitted by Martam Construction of Elgin, Illinois at a cost not
to exceed $156,544.00. Sufficient funds for this project are available in the current
budget.
�
Matt Overeem
Water & Sewer Superintendent
I Concur.
Se6n P. Dorsey
Director of Public Works
MEO/ meo
H:\ Water \projects\2012 \george \george street north.docx
Mminr
L 11
INTEROFFICE MEMORANDUM
TO: VILLAGE MANAGER, MICHAEL E. JANONIS
FROM: WATER/ SEWER SUPERINTENDENT
DATE: AUGUST 29, 2012
SUBJECT: REJECTION OF BID FOR ELEVATED TANK PIPING MODIFICATIONS
BACKGROUND
In 2008, Public Works retained the professional engineering firm, Burns & McDonnell of Downers
Grove, Illinois, to develop a computerized hydraulic model of the Village -owned potable water
distribution system and provide recommendations for improvements. The goal of the project was to
address system deficiencies, such as areas with low pressure or inadequate fire flows, and facilitate more
efficient operation of the facilities to better serve current and future demands.
Based on the study, staff recommended a phased program of water system improvements that would be
incorporated into the water and sewer enterprise fund capital improvements program as time and budget
allowed. The first recommendation from the study is for modifications to improve the inflow and outflow
piping of the existing elevated storage tank.
The elevated tank serves as the principal gauge for the Village's potable water supply system. The rising
and falling elevation of water within the elevated tank is the mechanism which turns on or off the various
pumps and reservoir fill valves located in the system. Hydraulic modeling found that the intake and
outflow piping of the elevated tank was undersized. In short, the existing piping forms a restriction that
retards the water system's reaction to changes in pressures and flows.
The improvement recommended to correct this deficiency includes the abandonment of the existing 12"
diameter inflow /outflow piping and replacement with a larger 24" diameter inflow /outflow pipe. The
increased pipe diameter (24 ") was determined utilizing computerized hydraulic modeling.
This improvement is the first in a series of scheduled improvements involving the elevated tank.
In 2013, the tank itself is slated for complete rehabilitation including interior and exterior recoating as
well as mechanical and safety improvements.
Mount Prospect Public Works Department
In 2014, the water mains at the base of the tank; including water mains on Evergreen Avenue, Maple
Street, and Northwest Highway, are scheduled for replacement with larger diameter pipes. Similar to
inflow /outflow pipe over - sizing, this work is also intended to improve the flow of water into and out of
the elevated tank.
Page 2 of 2
REJECTION OF BID FOR ELEVATED TANK PIPING MODIFICATIONS ($358,888)
AUGUST 14, 2012
Staff intended to effect these improvements in sequential order starting with the inflow /outflow pipe,
followed by the tank rehabilitation, and concluding with the water main work.
BID RESULTS
Bid documents were sent out in July 2012 to tank repair firms, piping and mechanical contractors who
perform large scale piping work. Fifteen firms were solicited for this work. The bid was advertised and
publicly opened on August 13, 2012.
The following sole bidder responded:
Contractor
Total Bid
Dahme Mechanical Industries Inc., Arlington Heights $358,888
FIT 7.YNikL4 re7►1
The only bid received was from Dahme Mechanical Industries, Inc. of Arlington Heights, Illinois
( Dahme) in the amount of $358,888. The engineer's estimate for this work was $158,500. Sufficient
funds do not exist in the current budget to facilitate this work at Dahme's price. Burns & McDonnell
reviewed Dahme's bid and found their prices are significantly higher than what is currently being seen in
the market.
Post -bid discussion with planholders revealed that the proposed work was viewed as a niche project
because it involved an unusual combination of mechanical piping work and underground construction
work. In addition, we believe that the small overall scope of the work had a limiting affect on bidder
interest.
Staff believes that more competitive pricing can be garnered by restructuring the work and incorporating
it into the planned 2013 elevated tank rehabilitation or the 2014 water main improvements.
RECOMMENDATION
I recommend that the Village Board reject the bid from Dahme Mechanical Industries, Inc. of Arlington
Heights, Illinois for the Elevated Tank Piping Modifications Project because it substantially exceeds the
engineer's estimate of probable cost and it substantially exceeds available funding.
*�
Matt Overeem
Superintendent
MEO /meo
C:\ Users \sdorsey \Documents \Water \Elevated Tank Infrastructure Rehab \VB Recommendatin to Reject Bids.docx