HomeMy WebLinkAbout6. Village Manager's Report 06/05/2012Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
�M?/
TO: VILLAGE MANAGER MICHAEL E. JANONIS
FROM: DIRECTOR OF PUBLIC WORKS
DATE: MAY 29, 2012
SUBJ: BID RESULTS FOR 2012 SEWER LINE SPOT RELAYS
BACKGROUND
On Monday, May 7, 2012, sealed bids for the 2012 Sewer Line Spot Relay Project were opened
and read aloud. This bid package was assembled to procure the services of a sewer
excavation contractor capable of replacing structurally failed pipe and installing or repairing
manholes. In many instances, once this work is completed, the remaining sections of affected
pipe are further rehabilitated utilizing the cured -in- place -pipe (CIPP) process.
Four (4) bids were received. The bid results were as follows:
Bidder
Base Bid
Martam Construction, Elgin, IL
$284,500.00
Swallow Construction, Downers Grove, IL
$312,115.00
Bolder Construction, Deerfield, IL
$386,000.00
Suburban General Construction, LaGrange Park, IL
$434,500.00
Staff identified Martam Construction of Elgin, Illinois (Martam) as the apparent lowest cost
bidder and presented a recommendation to award a contract accordingly at the May 15, 2012
Village Board meeting. However, Martam had failed to attend a mandatory pre -bid meeting
thereby raising concerns about the responsiveness of their bid. Subsequently, the Village
Board declined a motion to accept staff's award recommendation.
DISCUSSION
The estimate of probable construction cost for this project was $277,000 - $295,000. With the
exception of Martam's bid, all of the bids exceeded this estimate.
To gain a better understanding of this anomaly, staff contacted bidders and learned that all had
associated monetary risk with a bid document requirement assigning responsibility for the
disposal of hazardous soil to the successful contractor. This requirement is a legacy provision
utilized in most previous excavation contracts. However, recent changes in Illinois
Page 2 of 2
BID RESULTS FOR SEWER LINE SPOT RELAYS
MAY 29, 2012
Environmental Protection Agency regulations pertaining to the disposal of construction and
demolition debris have formalized the compliance process and increased costs.
Staff has no knowledge that any of the excavation sites included in the scope of work for this
project contain soils requiring disposal as hazardous material. In fact, our experience
excavating in and about these areas for water main breaks and other sewer repairs suggests
that all of the soil can be disposed of as clean construction debris. Consequently, staff has
concluded that a blanket assignment of responsibility for the disposal of all excavated soils to
the contractor, regardless of composition, only serves to add unnecessary cost to the project.
Therefore, staff proposes to re -bid the work with clear instructions directing bidders to assume
that all excavated soils can be disposed as clean construction debris. If hazardous soils are
encountered, the material will be sequestered, analyzed, and disposed by the Village pursuant
to existing protocols. No hazardous soil disposal costs will be assigned to the contractor.
Furthermore, staff has determined that re- bidding will not adversely affect the progress of the
cured -in- place -pipe lining project. As noted previously, much of the work included in the spot
relay project is prelude to CIPP work. Staff has contacted Visu -Sewer Clean & Seal, the
successful CIPP contractor, and learned that the materials necessary for our contract will not be
delivered until the end of July. Consequently, there is sufficient time to re -bid and start
construction on the spot relay work.
RECOMMENDATION
Staff recommends rejecting all bids as non - responsive because they exceeded construction
cost estimates.
Staff also recommends re- bidding the work with modified instructions pertaining to the disposal
of excavated soils. Bid results and an award recommendation will be presented for
consideration at a future Village Board meeting.
,
Sean P. Dorsey
CC: Village Clerk Lisa Angell
Deputy Director of Public Works Jason Leib
Water /Sewer Superintendent Matt Overeem
Mount Prospect Public Works Department
1 INTEROFFICE MEMORANDUM
TO: VILLAGE MANAGER MICHAEL E. JANONIS
FROM: DIRECTOR OF PUBLIC WORKS
DATE: MAY 30, 2012
SUBJ: LED STREETLIGHT FIXTURES FOR KENSINGTON BUSINESS CENTER
Background
On November 16, 2010, the Village Board awarded a contract to Precision Products Plus, Inc.
(Precision Products) of Montclair, California for the purchase of 54 light emitting diode (LED)
streetlight fixtures. These fixtures were to be installed on Village -owned streetlight poles in the
Kensington Business Center. The attached map denotes the project area.
The purchase was facilitated by two (2) energy efficiency grants: an Energy Efficiency
Community Block Grant (EECBG) and an Illinois Department of Commerce and Economic
Opportunity (DCEO) grant. In tandem, these two grants funded the entire purchase; no
expenditure of Village funds was necessary.
The Village Board approved the purchase following a motion to waive bidding procedures. This
motion was necessary due to a dearth of acceptable retrofit LED streetlight products in the
marketplace.
Subsequent to Village Board approval, staff placed an order with Precision Products in January
2011. Since then, Precision Products has shipped product on four (4) separate occasions. All
shipments have been rejected due to numerous product quality and design issues.
The most recent shipment was received on May 18, 2012. It was preceded by a letter from staff
to Precision Products that recapitulated their poor performance to date and established a date
certain (May 14, 2012) by which an acceptable product must be delivered. As indicated, the
shipment did not arrive on time and, upon examination, was found to still have several
craftsmanship and design defects.
Problem Statement
It is the opinion of staff that Precision Products is incapable of designing, manufacturing, and
delivering an acceptable LED retrofit streetlight fixture suitable for installation as a roadway light
in the Kensington Business Center.
Page 2 of 4
LED STREETLIGHT FIXTURES FOR KENSINGTON BUSINESS CENTER
MAY 30, 2012
Discussion
Since 2010, the LED lighting industry has made significant advances in technology and product
offerings. In fact, most traditional streetlight manufacturers now offer LED retrofit products.
Such was not the case in 2010. In fact, the Precision Products fixture selected in 2010 was
actually a prototype device intended to position the firm as an early adopter of LED technology
in the streetlighting industry.
Consequently, our recent search for a fixture to replace the Precision Product streetlight head
has yielded several products conventionally manufactured by established streetlight producers:
Manufacturer
s Hadco
Model
Cobra
Unit Cost
$725.00
Cree LED Lighting
Cobra
$790.00
General Electric
Cobra
$901.10
General Electric
Shoebox
$1,208.70
All of the lights listed above satisfy the American Resource Recovery Act (ARRA) "Buy
American" purchasing provisions stipulated in the EECBG and DCEO grants. Additionally, all of
the above listed products can be delivered within four (4) weeks after an order is placed.
The lowest cost alternative, the Phillips Hadco "cobra" fixture, exceeds the cost of the original
Precision Products fixture by $150 per unit. The Phillips Hadco light costs $725 per unit. The
Precision Products light cost $575 per unit.
However, recent developments in LED streetlighting technology have also been commensurate
with developments in the application of streetlighting standards to LED lights. As a
consequence, all of the above lights have been specifically designed to illuminate a roadway of
the width found in the Kensington Business Center when installed on poles and arms of the
height and length currently in place. Conversely, the Precision Products fixture was designed
as simplistic approximation of the output from a 400 -watt high pressure sodium light; its design
did not include important environmental factors such as roadway width, pole height, and arm
length.
Staff obtained and installed samples of the Phillips Hadco "cobra" light, the Cree LED Lighting
"cobra" light, and the GE "shoebox" light. It is the opinion of staff that the Phillips Hadco light
performed best during field testing in the Kensington Business Center. It provided better
illumination than the other products and cast it as desired on the roadway. Staff also found the
Phillips Hadco light adequately designed and crafted featuring good access to routine
maintenance components such as the LED driver and the LED bulbs. Additionally, the
mounting hardware for the Phillips Hadco light was extremely flexible allowing the light to be
adjusted on all axes so that the light can be mounted parallel to the roadway regardless of pole
or arm angle.
Page 3 of 4
LED STREETLIGHT FIXTURES FOR KENSINGTON BUSINESS CENTER
MAY 30, 2012
The Phillips Hadco light "cobra" design is a markedly different
aesthetic when compared to the existing "shoebox" style light
installed in the Kensington Business Center. The photograph at
right depicts the Phillips Hadco light. Although different, it is the
opinion of staff that the installed light presents an acceptable
appearance. The light depicted features a flat black finish. If
ordered, the light would have a bronze /brown finish to match the
existing poles and arms.
It is the opinion of staff that a direct investment of Village funds in the amount of $14,615.35 is
worthwhile.
To begin with, it is relevant to note that the streetlight heads in the Kensington Business Center
have reached the end of their useful life and are due for replacement irrespective of grant
funding opportunities. Replacing the existing lights with an in -kind high pressure sodium fixture
would cost approximately $1,300 per unit for a total project material cost of $70,200. There
would be no meaningful future reduction in energy consumption to mitigate this expense. There
is no grant money available to offset such an expenditure; it would be fully borne by the Village.
Conversely, a $14,615.35 direct investment in this LED retrofit project provides a reasonable
payback period. Assuming that the replacement of 54 streetlight fixtures garners electrical
energy savings worth $3,618 in the first year and this savings increases at a rate of 1.5%
(inflationary cost of electricity) in subsequent years, the investment will be returned in 3.9 years.
Finally, it is important to note that the EECBG grant contains provisions requiring the project to
be fully completed no later than August 20, 2012. This performance requirement provides
insufficient time to let public bids for streetlight fixtures.
Recommendation
Staff requests the Village Board to consider the following motions:
Page 4 of 4
LED STREETLIGHT FIXTURES FOR KENSINGTON BUSINESS CENTER
MAY 30, 2012
Motion 1: Rescind award to Precision Products Plus, Inc. of Montclair, California in the amount
of $31,050 for 54 "shoebox" style LED streetlight fixtures.
Motion 2: Waive rules for public bidding and award a contract for the purchase of 54 Phillips
Hadco LED streetlight fixtures to Graybar Electric of Glendale Heights, Illinois in an
amount not to exceed $39,150.
Sean P. Dorsey
Cc: Village Clerk Lisa Angell
Deputy Director of Public Works Jason Leib
Water /Sewer Superintendent Matt Overeem
Project Engineer Donna Brown
Administrative Analyst Mike Dallas
N
N +F KENSINGTON BUSINESS CENTER
Map Info S as of May 2012 PROJECT AREA Street Light LED Retrofit VOMP LIGHTS (54)
IRONWOOD-DR
z El
Z
w
0 [ 011 LLJ
Z/ z
- 4 �E4 jq
.. ... . ......... 0>� —
�� i � 1 � � "01 ❑ 1 1 il EE El El A 0 D w Kil [j 4 El Ej]
2i F. 4. 0 - -
D LJ ❑ El w
TO z i 0 ❑ ❑ ............................................
en
. . . ................................. . . ......
E KENSINGTON RD z
....................... . ........................................................................................... .................................................................................. ...........................................................................................................
...........
705
Lu
m 000 R7O —0
............................
o
....................
LLY CT . . . ........
H r [701]
7
t Ir R75
:z ............................ z ............. .......... .
FQ
Z
(n
El
W ,
I L
10 L" -AV
.................. . ....................
...... .....
........605 ................................ (_n
(n
INN
147
,.. 0 585
0 o A Ir
.............................. ................... ............. LL
570 ' ABA
................................ ............
51
................. .................
Ew:!!09 550
150
.... .............................. I ..............................
W, . ................................................................... 555 852 ... ... . .......
U . ... . ........... . ......... . . . . . . ... . ...... . .......
�Z520
........................................................... ..................
...........
HILL ST
..................................... ................................................................. 0 0
S IN . .....
ILI
0
. ........... .
........... 431
412
431
410
411
600 ............................................................................ F
..........................
.............................. V . V . I . L .. Q . V . V . C . ) .. C .. D . - .. L . N .....................
6 0 13H EE�l ',I-GRE
0 .......... �� [4- "^ ��0 � 320
1003 !i 31 ..... F3 1�
0
,% w - — �L i I ...............
K Lu ............. ......... TT�
�. z E�
I'z 1[]:P U[T a F-1-i ..............
EA EP�* -�JT J� E Tt6j
3, - L:O DENIN'
W
1
Z 7� 31 0
z . ...........
z RVEST I N m 30