HomeMy WebLinkAbout5.2 Community Investment Plan - Fiscal Year 2025 to 2029M+,wn �'xyt�lts�=e Item Cover Page Subject Community Investment Plan - Fiscal Year 2025 to 2029 Meeting August 13, 2024 - MEETING OF THE MOUNT PROSPECT COMMITTEE OF THE WHOLE Fiscal Impact Dollar Amount Budget Source Category DISCUSSION ITEMS Type Budget Item Information The Village primarily has two major budget types: Operating Budget and Capital Budget. The Operating Budget provides an appropriation for the day-to-day expenditures, including personnel costs, supplies, contractual services, and other recurring items. The Capital Budget provides for major capital expenditures, including construction, building improvements, infrastructure improvements, vehicles, major technological purchases, and other expenditures providing the benefit beyond a single year. The Capital Budget is also known as the Community Investment Plan. The presented plan is a preliminary plan, and it will be finalized later in the year along with the Operating Budget. The presented plan provides a summary of capital spending over the next five-year period from 2025 to 2029. Though it is a five-year plan, major focus is given to the immediate 2025 fiscal year. Ilio-iiccinn The proposed five-year CIP plan from 2025 to 2029 totals $177.8 million. The proposed capital spending for 2025 is $31.5 million. Department FY 2025 20 Villllage Manager's Office 436,500 30 Finance 75,,,GGG 40 C ommuniity & Econo miic E1evellopmenet 850, Cd ) 50 Burman Services 1,197,500 60 IPolllice 399,000 70 IFire 9446,703, 3Cr IPubLic Works 28,,773,1,144 iGrand Total 31,41 ,322 FY 2026 FY 2027 FY 2029 FY 2029 Total 216,500 1811,500 1811,500 131,500 1,197,500 - - - - 75,000 25%,%&0 250,000 250,000 25.0,000 1,85.0,000 - 44,500,000 - - 4,500N000 300,000 500,000 300,000 300,000 1,799,000 1,82,500 - - 6 0,000 1,785,203 44,331,202 244,443,7,41441, 35,,212,253 30,7440,709 166,,54114,719 45,290,202 29,918,941 38,943,753 32,132,209 177,755,4121 Based on the above data, the Department of Public Works will have $166.5 million in capital projects over the next five years. The amount represents 93.6 percent of the overall capital spending. The plan for the year 2025 proposes $28.8 million in public works projects and the same accounts for 91.4 percent of the overall 2025 capital spending. Ci a pa rtme nt FY 2025 FY 2026 FY 2727 ....,8,3.60,000 FY 2029 FY 2029 Total ....440,3.417, 7Cd)Water System 8,160,000 6,825,OCd) 1,7844,306, 8,,405,000 8,597,0&0 Cn.... 701 Sanitary System 2,270,000 2,270,000 2,270,000 2,270,oG0 1,800,000 10,8.80,0oO 702 Control) and RRellated I 630,000 4480,000 30,0,000 3„625,,000 4475,,000 3,4490,000 703 Storm Sewer 325,000 325,,0Ci0 - - - 65.0,00n0 7044 Street Construction and Reconstruction 3,510,000 1.1„828,600 100,000 2,653,100 100,000 3.8,3.91,700 705 Resurfacing, Curbs & Gutters, Siidewallks 9,908, 8,02 19,679,956 171,203,075- 144,4478,,993 1.5,44244,4460 70,69,5,31.6 706 Improvement to IPu6Rlic BulRlldlings 79%075 Il„1,30,395 5,177,060 5,,853,,710 1,28.8„ 510 144,2448,750 707 Computer Hardware/Software 511,,500 51,6,5010 4481,,500 4181,5010 4481,500 2,4472,500 708 Vehlidles/Auttoumottli've Equiip€mentt 3,085,000 1„4486,000 1,4468,000 2,61.2,000 2,736,000 11,369,000 799 1 on-Automottiive Equipment 1,,151,708 1.82,,.500 200,000 227,000 660,000 2,,1'944,208 710 Miscellllaneous 1,1449,237 5544,2271 559,306 5641,4450 . 569,739 3,396,9,53 G ra nd Total 31., ,322. 45,290,202 29.,918,941 38,943.,753 32,132,2"09 177.,755,427.. As seen in the table above, the plan includes various street resurfacing and sidewalk projects totaling $70.7 million, 39.8 percent of the overall five-year CIP. The plan also includes $18.2 million in street construction projects, totaling 10.2 percent of the overall five-year CIP. 50 percent of the total proposed CIP items consists of various street and street related projects. The other major project categories are for the water system, totaling $40.1 million or 22.6 percent of the overall five-year CIP and sanitary system, totaling $10.9 million or 6.1 percent of the overall CIP. The category of improvement to public building is proposed, totaling $14.2 million or 8.0 percent of the overall five-year CIP. The five-year CIP plan also includes various vehicle replacements totaling $11.4 million or 6.4 percent of the overall CIP. The year 2025 plan includes $9.9 million in street resurfacing and sidewalk projects, $3.5 in street reconstruction projects, $8.2 million in water infrastructure improvements, $2.3 million in sanitary system improvements, $3.1 million in vehicle replacements and $4.5 million in other planned projects and improvements. Funding Sources: The Village funds its capital improvement plan using various sources of funds as described below: Fu nad i ng Sou rc F"Y 2025 F"Y 2026 F'Y 2327 F'Y 2029 F'Y 20219 Tota l 001 -General Fund 11566"237 1,518,221 1,7844,306, 2,737,4450 1,821,739 9,4127,953 020-Capilt4l (improvement Fund 44,9844,26,3 1.2,701,4427 2,71.1„836f 9,169,3744 6,196,308, 35,763,208 023 -Street Consttructilon Fund 5,752,,322 16,44244,,0544 5,4430,,299 8,816,4429 7,,3.241,,6^6,2 413,597,,766, 0244-Plood Control) Construction Fund 835,000 705,000 200,000 1,525,000 375,010101 3,6440,,000 037 -SI” IP TIIIF 8,00,000 50,000 50,000 50,000 508,000 1,o0CR,o0o �041-Mottor IFuell Taal (Fund 2,,500,,G00 2,,500,,1000 2,,.500,,000 2,,500,1000 2,,.500,,000 12,500,,1000 0443 -Asset Seli ure (Fund 644,,000 - - - - 644,,000 045 -Prospect & (Malin TIIF 1,775,000 350,,000 350,000 350,000 350,000 3,175,000 050 -water & Sewer Fund 9,560,000 9,195,000 3.0,530,000 10,775,000 3.0,4197,000 50,857,000 053.-IParkung System Revenue (Fund 1.1.1„000 3.32,,'00 3.63,,000 227,000 300,,000 933,,000 061-Vehlidle Replacement Fund 3,,023.,,000 3.,,418,8,000 3.,,4168,,000 2,,63.2,000 2,,736,000 3.3.,325,000 062-Cornputer RRepllacernent (Fund 23.3.,,500 216,500 3.83.,,500 181,500 3.83.,,500 972,,500 TBD -To be determined - 41,500,000 - 41,500,000 Grand Total 31,480,322 45,28O,,202 29,918,9441 38P941,753 32,132,2 177P 755.1427 The Street Construction Fund will fund $43.6 million or 24.5 percent of the total CIP over the next five years. Additionally, $12.5 million in street projects are funded from the Motor Fuel Tax revenues. This fund is also going to receive certain major grants totaling $18.5 million over the next five years for certain federally funded projects. The Water and Sewer Fund will provide funding for various utility infrastructure projects totaling $50.9 million. Of this amount, $22.0 million will be funded from the bond proceeds. Per the water rate study conducted in 2023, the Village will be required to issue bonds for the water and sewer projects in 2027 and 2032. The remaining amount of water and sewer projects are funded from the collected service charges. The Capital Improvement Fund will provide funding for $35.8 million or 20.1 percent of the overall CIP amount and the Vehicle Replacement Fund will fund $11.3 million or 6.4 percent of the overall CIP. The 2025 plan includes funding of $9.9 million from the Water and Sewer Fund for various watermain replacement and sanitary sewer rehab projects. The Street Construction Fund will provide funding of $5.8 million for the street resurfacing projects. There are various small capital projects and technological advancements proposed using the Capital Improvement Fund totaling $5.0 million in 2025. The Village will be conducting scheduled vehicle replacement totaling $3.0 million in 2025 using funds from the Vehicle Replacement Fund. There are projects totaling $2.6 million proposed using the TIF increment revenues in 2025. The proposed plan for 2025 includes grant funded projects totaling $1.5 million, and the remaining $30.0 million in projects are proposed using the Village fundng. Funding Grant Fu nd i ng village Funding Total 2025C1Pe 001 -General lFund 1,566,237.00 1.,566,237.60... 02,0- Cap iitall IImprove rrnent (Fund 623 -Street Construction Fund 024 -Flood Control Construction (Fund 637-SI"r P TIIIF 041 -Motor IFuel Tax (Fund 0643 -Asset Seizure (Fund 049-IProspect & Malin TIIIF 056 -Water & sewer (Fund 051 -Parking systerrn (Revenue (Fund 061-Vehlicllle Replacement (Fund 662-Corrnouter IReolacerrnent (Fund ,G ra ndl Tota l 19'3,332.00 4,,7,34,,8,71.00 4,954,,263.00 1,295,00.00 4,467,322.00 5,752,322.00 - 8,35 ,000.00 8,35 ,000.00 - ,3+00,"000.00 ,3x00,"000.00 - 2,.500.,000.00 2,500,,000.00 - 64,,000.00 64,,000.00 1,775,000.00 1,775,000.00 9,x8;60,000.00 9,8,60,000.00 111,"000.00 111,"000.00 3,021,060.00 3,,021,,000.00 211,,500.00 211,,500.00 1,4114,,392.E 20.,995.,930.00 31,R,F322.00 The one-year plan (2025) can be accessed by clicking here. The multi-year plan (2025 to 2029) can be accessed by clicking here. Please see the attached Capital Improvement Plan Summary. Staff will make a presentation at the committee of the whole meeting on the overall CIP and a few selected major capital projects on August 13, 2024. Alternatives 1. Staff to discuss the 2025-2029 Community Investment Plan with the Village Board. 2. Action at the discretion of the Village Board. Staff Recommendation Staff recommends discussion of the 2025-2029 Community Investment Plan. Attachments CIP - Multi Year Plan - 2025-2029 Mount Prosjac of Village of Mount Prospect FY2025 Community Investment Program Requests IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 1 N VIII ,VIII' IIID , VIII' , IIID" � ��'�u� VIII VIII , PI��„�� VIII CapitalImprovements........................................................................................................... 3 Oneyear plan...............................................................................................................4 Multi-yearplan............................................................................................................ 14 Appendix............ 27 Econ Dev and Planning & Zoning Requests..................................................................................... 28 EngineeringRequests.......................................................................................................41 FinanceRequests......................................................................................................... 139 Fire Requests. . . . 143 Forestry & Grounds Requests...............................................................................................165 Human Services Requests.................................................................................................. 170 Information Technology Requests........................................................................................... 175 PoliceRequests.,..,,..,........................................................................182 PublicWorks Requests.................................................................................................... 203 Streets & Buildings Requests............................................................................................... 211 TVServices Requests......................................................................................................285 Vehicle Maintenance Requests..............................................................................................295 Village Manager's Office Requests...........................................................................................310 Water and Sewer Requests.................................................................................................314 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 2 m mi uul uuuuuruu°° uumuuuuumlml�" uuull IIVI uul�ililllmlm uul�ililllmlm Village of Mount Prospect I FY2025 Community Investment Program Requests Page 3 �FbtaNCapit:aN Requested btd� Fuindilinig Reqiijested by Delpairtinneint 66 CapkaIKmprovewent Projects 11111��11111 Ec.on Dev anur/ann/ng aZoning $aso/oo0o 1811 omGeneral runu<6%) $1,863,237 00 sng.neer/no(44m) $1 00 41 u2oCop/Ml /mpmv meot � und $4,r/�j,,"an00 df/p, F:manoe(0%) $75,000 00 f1f, 023suroe�/mpmvemenzconomcc/onF:vnaU6%)$So70,3 0 Fire (3%) $966,7-08 00 02+F:/oodcunzrdconmmcuonF:unu(3m $E335,000 00 � �^restry &orounds $249,2s'/ 00 u�'/SMP n� mnu{s�} $aoo.00000 /nformaL/onrec»no/oov<1m> $an.s0000 o41woAorF:ue/Tax F:unu(sm) $1,550,000 00 0 po//cepm} $39s00000 o«oAsset seuureF:u:u(om> $61/1,000 00 0 &au//u/nws(31A) $839,07S 00 owypmspeczMain r/:: F:una(sm) $�.rzs.00000 1011ryservices (om) $12S,000 00 «� osovvaue,and sewe,runu e.aao.000oo ve»/c/eMaintenance (1o«) $s.nz\00000 o51v///ooeParking sv�AemF:unu(o%) $n\00000 411 v///agemaname,'somca(o%) oo.00000 CJfA 061vah/c/aRep/acement F:und $s.ozl00000 0 wata,and Sewer (s1�m) $10,760,000 Co osaComputer nep/acemenrrunuUm) $211,500 00 rorxL $x1wmouuoo ' ' 091 � euera/o,ano(sm) $1,484,692 00 ror«L *31,480.322.00 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page T� CPumlitut4Costs III';3urt.4llkdovvuru 1i111111 Capital Costs (991/,,) $3, 480,32200 O�PE7 rationa7l C::ca t.> (l%) :v,a,G,l too TOTAL $31,675,940.00 IIIII)dlll ce Requests II tpfis Bled Requests foir 2025 Body Worn Camera and Mobile Video Recording System Replacement Savings & 4tru:~*vein uu 16tur°t:alllrdowirn p Iheire's no data faqir �n0.n111ldfrig r;ll-lar�t $300,000 11 he avoiragescirvIcc, I°Ife foir cu Lmdy r onin cairnell t k Hhin-N- to Ave Years. hin 2021, fliio 111aullua�c 11 epaiI�uan^ndtu oQ s ccuirrci nt fllrre-�l of ll>orly. rnau�iriro C:air'ncir au,� WI1111 be nalpprasdua.Ihli g fl -in ur, eirid of ^tcirvi e Rife, As slixl n, Bihor; afr;lpaird:u uaoual: uuira�ticlip aiu's t1l Il New Lockers -Men's Locker Room $22,500 I iur, ulnpall t u'rIcrit !is Iloollding W linaurr,insase at 11IC IlOCIIaCll S fa>r tah�r,° urou uo s (HAker irr,rsrun at the Iru011k c stuatJoil1, New Special Response Team Squad Car $64,000 1111ho 14Tollice II Dolpaid inna^uad Is Ilrr¢allriiu utf d: o linuuir .11'u r r. (tib unr, w q uuad r all for plhlrn sIp cli all 14s.r Irbori�se foarmi. is fl'uuirdll'nol llcmllciiraf; to mord l Ii1k vellniff1c,to111lc.'Veli�oua.lle nuirailcir1�a111 Vild-lialle1:1,elp1llaa(c"InnrualIFuund. New Specialty Lockers I he I1„1011 c z. IDc,lf art urnc.unt: l=u Ilra+.a11*lrup,„ to Il.auuir r;ll ounw 6 1 ic.w sulrra Q Grallty Ilrar,ll*a irs. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Total: $399,000 Page 5 VIII hill r IIIZequiests Iteinnized I:Zeqtjests foir 2025 Cardiac Monitors R.elplaccalll 9 cairdiac imus iI'iLoirs and liluirchase Bairn exi ra oinc fix trahning, 11 henoiflWils cul-11-onfly ill o usc well c ast I chased iin 201 7,111intirodixed iii ii 2025 fto pAirchaw h 112,025, Power Cots and Power Load Stretchers $142,500 II)i lrdl vise 4 1 cots airld 4 1 IlOAd SYStUrIM, [oil fl-111-ce firolli1:11111 ucall-Tilbulail ces and onic reseirve, Vehicle Radio Replacement $1.30,000 RelpIldclin,incil it 0 dhc eirldire irivointolly of 11�(Iil c Delpartillneint 111111 foll. alll V0111k1cs, Our cul-ircint rj(Hos airc 12 ycairs old ,,)ii id ii lo oil being saMiixxj, 1111-11 a(hjKlion, Ilraut, airy; iricaairlly ii-1111possflIble to corne Iby intoalk, i I'll,'; nrlirloir in 11-IrAlfic lelpairs Total: $946,708 Ibdhlrllidbgy i1equests Iteirnized IIe4njests foir 2025 Computer Replacement - End-user Devices $1.39,500 11 he scIl �eirlulcd ciind uscil ate Ace 1[ c1placcil nonlis ni18 desktolp cornputeirs, 25 II allptolps, 8 irl,jgg&Hzcd Ilalptolps, 10 ill'ads, 10 pi-h-itcirs, 4 sc,aii uunn ui 5 aind 25 dcs1k pli-iones, All t h oug,11-ii nal ilea 11-K)s l ain oingoling aini-Riall I di-iiase, it was ii -O I ii-ito- Computer Replacement - Infrastructure $72,000 11 hic Scheduled Ill firashil u I(Aauirc I elplaceinliciritsindwk,,: 2 sciniers, 1. 1114AScs, and 5 nicllmmirlk swkdl lf.s Alsm h H]uded ini f llw 2021) Claphall 111­1­111proveinriont Prograll-11 1s a new riire�mfall, Althim ghi this Ihas Ibc,.eii 11 Quito ongoll,lig aairuru la 111 imird asa., it war, h libil oduccd Total: $211,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 6 Downtown/Central Business District Faqade and Interior Buildout Program TheoomxAnwinFacmdaand ImcHor111,uildoutPmpiramioonriatdin�� grant pmgirain toancouriq,�epwvaLc|nvcstmemtin�xb��pmpertics|n South Mount Prospect (SMP) TIF Fa�ade and Interior Buildout Program 11 11-leSmufl-i mountPnspec11 1FFacadeand lntcii �oi'BuUdoutPmgiralinkapmsmmtoenuouiragepidvatoinveshnnient|nexisting pmpurdcs|nthe South MountPmsncc T1F11 )iS til ctThiswqoctiuunonnum|communbvinvcAmcntpirogimm Village Gateway Sign $600,000 Dostpinandcons brucduI'll o,mptcmmv/cntrwnccways|gnamcatmu|tip|c|0cationsacmssthcv|Uaac,Thecxact|ocdonsarembe d�e,mined Village Wide Facade & Interior Buildout Program $1.00,00a Th(�ViUag�cVVkIcF�xadcond11ten horBui|doutPiroairam!is amaix 111i1s�,Jrrantpmgjj-�)mtocnc(uragcnhvateinvcAmcntincxisting,nommci-�Aa| proF�!jFficsnu!idcthcT11Farcas, Total: $850,000 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page T� Brick Sidewalk Maintenance Removal/Replacement $250,000 nemovcandIflicbdcksidcwa|komandamvndtil Downtown araa. Fire Station 14Butler Building Maintenance $28.875 Peirfo,m|novallmmintenancetasks.suchaspaintingofthebu||dinmand misce|Ila neous��XUmriorrepairs, Fire Station 14Exterior Painting -------------------------------------------------------------------------------------— $4e.200 PuintaUcxtcrinrsuidaesofFipcStatiun14that aenotbrick Historical Society Campus $30,000 TheAisto,ica|8ocietvCampuscompr|sesof3bui|dinas.bui|t!In the|ate 18OO'soil ear|y19OO'sandarei^needofva,i^usmaintenmncerepai,s su'hasIromf,..sidinm.windowaetc�Thep,opvsedmaintenanceschedu|e|ndudes:�2O2S-Schmo|11 ouse— HVAcReplacement Program -------------------------------------------------------------------------------------- $69.300 11�epbccmcntof11 vAz units.asnscdcd, Other Public Buildings $165,000 lmpruvementstuv|||eae-ownedbui|d|nms Parking Deck Maintenance -------------------------------------------------------------------------------------— $1.1.1pom Staff ncnucscdaconditionas,cssmcntbrpomormeAin20o3todaerminentherurrrntmoimenonccscheAu|cwas kceping pace, with thc mt ordicter|nmt|on,Thcrcpo�wmshnaUzcd|ndud|nma5-,�aroap|ta|p|anthatcnsurcsthatthc�mctv,r— PuNicwmnompZnep|asment $40,000 Rep|acethedommsdcwate,back flow dev|ceatthePub|ic$brksfad||t» pvvExterior Door Frame Replacement -------------------------------------------------------------------------------------— $52.500 ecp|accthceutcriurdoorsandfi,amcsatthcpubUcWorks faci||tv PvvVehicle Maintenance Shop Painting $46.200 Paintilip [heinteriorofthevehidemeinteponoeshop� Total: $839,075 Tree Planting Program $249,237 11-111mmbnotrcesonIr1y11 0 s cif way andvU|agI�� mwncdpmFoirf fes, Thevillage of11'aloulit Pmspec m,,�mdvowns appmx|nmaA/25,000 Total: $249,237 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page T� � ��Ieqtmests Bridge Improvements 'Business Center Drive a Iii flieuseh||�ifcofovsnwssCcnlorodvebddoe Bridge Improvements ' Sediment Removal $250,000 sflfbuUd upaffcyc�sthmMmwandqu,fl bvofwak"rth^oighbhdmeatu|"eldsThep|anlIN]wmrkindudesnenmva|ofsi|tand gabiUAmsstircam banks mI future emaionatmulUp|ebhdae |mduding�VVufRoad 8um|ng8ush— Busse Road Reconstruction $650,000 Loca|cost Share ofthcCook [uuntv11 l|mhwavoepartmcnt'srcconst,"cdonofoussceoad,Thccost for thcItwi||befundcdbvaCook [ountvGi-ant, Central Road Pedestrian Crossing Improvements $1.00.000 -------------------------------------------------------------------------------------— ofcentra|Road curr|dorI:Iode-hriancrossinmStudy WeUeru`nshructiun $1*,00 Corridor Street Lighting $587,000 11nsmUat|onof11,sDshrcctUsh(sa|olip, ma�orcnrridoo,pnt(�^t|a|fvtunepno�oco|ndudc:oO25 RandRoad mcdocwood11 onctoCamp Mcoona|deoad2826 susseI A|annquinRoad tn11-9O2O2/ OaWon3tme 11-9OtoBmhurstRoad (111183)2O28`' CmndcvDetention Basin Repairs $300,000 Er^niuneroundthuinflowstmCturcrCnui,cs|Ong tori -in rcpmirsfor the cffcctivcoperadonofthcdctentionbasin� Dcoianand conatructlnn wi||Focus pnmo,ingstorIII MotcrtothcOutflow structurcwithmut crndingthcbottoIII ofthcbushn' Detention Pond Improvements ' Pond a $312e,000 11 1111�s Ibdesigned toIII fll le calucilyall 0ojpc'�11'flionofthede� omlion poii id system. McDonald Creek Bank Stabilization $60,000 3tall,AhzaUoii ii of streambanks a���dl)ondGreek mInoii �vcyamcc ofmm,mwatorand tl'ic|andof adjaccrmmperd,s,pircvcirit Neighborhood Drainage Improvements Cungruchonofdirainageimpmvamemsix) aUeviatemeiglhbo^homdfluodingjpirob|ems� New Sidewalk Program $330,800 �ns��|nowo@�wa|ksutbcadnn v�c�nonccun�ndvcxbtThchdbwngks�t�n ,�Ubep,nsidcmd��rthcncx �vc��r�Bu��Romd Northwest HwvaCentral Road Gateway $1,300,000 �a i�nandconsu��i^nofa�a�wmvt^indudeviUaoeen�vma��rr|orkt�v ���en.pare.pub|icparkins|otand�nne�capeatthe ime1-Secfl0III ufmmthwes *wv&CeIII tr,'1|m[L Phase 11 Bike Plan Improvements Congrucbonofshmrcduse pud-is.|lig,11-11flh-lig, aii �d asso6atcd wayfiindfing sfgrls alloirig coin hdmsdhutI fl -le goals ofthe VU|agcBike1 Potan ia|p11riommconlidbisindudrmcnsinTflonmoad.Cen0 ra|eoad'BusseRoad, RmndRoad, ondmbh_ Prospect Avenue Improvements Redeve|opmenta|vnaPmspectAvenuehaosnurred thHe desireforoutdoor seatinmIII fl -ie summermuuths'T-Wire |sconsideirab|yIII pedestdanandbicyc|eactivitvdowntuwn4th theadditiunufnew,estauranOf, andshvpp|ng.The, Vi||ame— �� vn|agomMountPmupo�|FvoousCommun|�mvonunontPmgmmRonuos� T� $640,500 Rand -Elmhurst -Kensington Road Intersection Improvements $1,235,000 Iimpairswvce.fluaffua: flow t1-mrauup,IlufIIoc;f:irii,uon,„Ikfoofemrc iiasuu.IIa:slllldawingfmmuumpallrflidom.ufIfYllu<r cIIha2022:11"Ihia cIIIIIIau;iaummuoirugdaind111.OW.acquuispt.fnaun. 2M2 .20 5Rhnme 111111 Cwntl a una;daiau a a n d r:ons N u cd oa 1E a ngi rTcl[riung 2026 2027I1 hna V111111agc ru 111111llaic,irc(tuuuu cd... Residential Street Lighting loWAll<affinYunof II II;fD qirr.e0alildulln0.ufuoWd t d u=NiiafWunull in"pgfnllrailhuryod".14''loteund«aall fWuuu-(,Iguirrdectsiuron;Ilkude:1[i3o.urinuung 113111shn II aine ka0tivcou�n h01insfing Colin IlfmyM aindf Il,:uur: td AmmmMmky MAIt Lane Ihn,tlwn eni Canner McDonald Ilfaanna9 and "mumhunulh II auona;f2a,iin r lClo,W Ibelm anrm.. Schoenbeck Road Resurfacing II Ilan, ,:n,Qapnllr�,nllf pr:n�nturnid unu Ilnnuua su Ilunarr If�nr";II a �nffung;�, nunrf ii rlu.nrr fuair a m„a,�uau,f^aa,iui ot;..f.11nn^ 0fllll�ug,;n� �ullnllallimra:f �fman nu�nuf II°n�a, Ilnr.u.0-n aaear„au rV�^af ��n fi� uf��,irrrll �,uuu f„nd,Q�: it spaoirtaffnan Rnanggr,ainn gminf: fnithe nanmuuirnt of $297,f9f9O to irr»sinulnrc'ulno Ihs,;weinnr.uk'haluim (Rand Had frr Camp - Sidewalk Replacement Program ant aQ da f;;u,u.1vn a iiallewr,!u II~rtu^ 0.11 uu auiva, 1hn nonnovill and iruulL`n ac, irndsinL Ilmdw�f:iio n of fund,. devoted to i a r,inllciru0 cost share parrrWam, Street Improvement Program I;m,,,uuirfaad,i'ongg of f:fnd 19ullllnM, strmh to m5oi o0:;aM 2a 20 ymt.nir Ililfrr'.. Streetlight Improvements Ife11ullnaa cirneii of of Qx ,f oirng; nnfa r c Illighlh is as vanlind f iramn „airnd ave uneces h' atc,” Traffic Calming $11"25,100 $335900 $4471.,022 50,000 lumpullasuM01Wivau'o5 UW, 1111rfu irr(Vllyll^!aa�fp„Ilulharnirllua:wr,m8'lfirre,c'f" Piroprainn, t1ln Village's brzaffic ca lllinniuor, Ijif agramn Armaom fs;uirr. Ih'nmuflln irc.°niidoo0 nuW vii llllrugfc HAW and can be 1irnr:arparairantul Wo the SWI Ras^umn fdan.ho 1P r.,g„m m or a MW ;allm;o W Iraircalr^r:�tr Traffic Signal Replacement $1.00,R14K) lyoradinnInsprdAaiaaoo ofuwfi tingtra °mu f 1f n k sfuudfum.sofuunt(n-ureadoin�^�u:;^;fi�;ufunula;eta:u•in�ninliunl,flln<aund�u:a�.R�^.•,^au� nf°fua ,ugwun:u a,w. ii,iu ainnnrun� au unf a;^u� ,uuun.a.u•uiru. moammrat <aird a opn2irsurK o « afuufp rnarnu.. Poarruf uc,all fao`Mm f au iluuduuufsf;:o ut unull Il,md & G_lvr m &rawd,u: wvc- Total: $11901802 IN Village of Mount Prospect I FYA25 Community Investment Program Requests Page 10 Water a�l��4 Sewer ��Iequesls Booster Pump Station Pump Rehabilitation $225,000 Inten msandI rh lb|tatono,tll IcwUmgC'scebtingh�`scmlccpunnjiss Combined Sewer Improvements $800,000 lo reparaniftrnqjl�place111-lainUilic sewc"Irsall id &,smated stirliclAinsinmmbined sxnhw,sell-vice alix"a". Deep Well Rehabilitation ' Well #16 $535,000 muintcnunceand ,chabi|itudonofthcdccnwell, |ocatcdot000sterStation 18, Fairview Gardens Overhead Sewer Program $470,000 Thecunve,sionofpmpertics |ucatedintheFmirview ("ardenssubdivisiunthathave suspocteddirectfootin:ti|econnectionstotheVi||aaes' sanitarvsewerthuscontributinxdearvVate,tutheFaimiewLift Station, Lead Water Service Line Replacement $100.0mm -------------------------------------------------------------------------------------— Rep|accmcntof|cad wmtcrscp|cc,Uncn, iii 2.025and2n26'thcIII no�ctisaUoca�d51OO.00Oeuchycarfor|cmdscrv|c(�|incrcp|accmcntcos, shan,lin oO27.thcuUocution|sthccost oom,p|ace 1O%of|sodsc^vice Uncs— Leak Detection Equipment and Utility Locating Equipment $80,000 Thepundas ofnewwutc,rcakcm,-clatnrs,neweuxusdcvvater|eakdetecdondevicesandnewmd|hv|vcuimmenulpmentT1puirch ses wiUColl inmztohc|nutiUtvstaff ideittlfy dic uxact localfoin of awater call< to w1lif) rinfin !I inize watcr and — Oakton Water System Expansion $750,000 11nstaI�|adu ofnewwate,mainsaii iirfasmodial edmaterappu��nanc�|nnewlvannexedaireastlat. do ii ror ive vUzi�,c ",aec Overhead Sewer Program $ 1.00,000 All) me,headsanhon,sewersysil en |sdedgnedtonI uven sanhomwas t e (sewmg��)fir mf1l Owl Ing bad imothmhoIII e� W11 ) l c1l o 111 occu 1, for Sewer Main Rehabilitation Street Light Disconnect Cabinet Replacement $1,0QQ,0Q@ ?c1placeirnant cxl-st4rg,,trcct|ight1ii iigdiscoll rmct calbfmtsdim magc�ocluimrine'll-lit ulpdatlN, ineettin g: iiiew code regiAllatioaand waii I, of Streetlight Improvements LED Retrofits Retrofit ofexisi1mgst�il ee01,11`�',to11s11)U�dnio|ngyA11|stiree#f,11rtswiUbeconvert�edto11soatfl-ie endnf2O24 wlthtlheexoptlonofthe I Paid< pall ding ot ighit�s,69 ledestirlain shreO 1111g1his have ber"Ill collivoll UA to 1111 110180 lede stil on - vFoneplacemenu ()rejpl'ace t1le variall �Ile fii equoicydhwes (VII:1)) at boosteir stations, V11::11Aaii c, ii oplacedoi-iusevoii yf2orcydc. 2025 V11::11D's to I 11 c1paccd:113o^sterS1 al ion�1. VFD2Boosar8talJonS VFD1BoosterSlal ion1.7 VFD32O20VF[rs— Water Main Replacement Annua|watermainnep|aoement, �� vn|agomMountPmupo�|FvoousCommun|�mvonunontPmgmmRonuos� T� $6,500,000 Total: $10,760,000 Page 11 Vel[ilcllllleMafill ftenlanlce IIID,equests Iteinnized C�Zeqtjests foir 2025 Police Vehicle Replacement �.clplaccrficiA of Police IDelpaildin-liellit roe ll lick -'s and cqliAlpincii ]I L 11 hc aninii A all vchid1c Ilr.aac Iiacyinnr.0 0s ai-c calculatud foir cach v6INdc based rain the Iffe, aA Hina V611fdr,?, calciAll"A ed h iterear t, supoirvkJoini fecs i aii 0 f he vchide account 11-jallarice, f 11 lc— Pool Vehicle Replacement $1.01,000 Replacernell ]I t of I vellides all id equipiaicil-A, esu nivall veh !Id e 11 case 1payunue ii its a -e calcuLAed foir eachi vehide llI anuli the hre of fl -le veh !I do, f 11 Y� vdhk] 11 m5e, I nell 11 ts are i a lo: Ila ted all I'lluall ly– Public Works Vehicle Replacement $2,225,000 Relplaceirriell it of PlulbHc Woll 11<5 Delpairtilinicirit vc1hldcs and cquilpirncii it, Ai,iinivall vcl-i1dc Ilearae. Ilr,ayinruv^rits aire calk ulated for CN -11h x6ed Oil � t1l le hre of flho voll1fdr., calInflated friueilros'Jind i 114� vdhir](� 0 l° aallarico. fllrcvollrurlr,.11c�uasr�–. WlIlage III IIInager's f i c IIIReclulests IternizedI°tecp jests foil, 2025 Village Manager's Office Conference Room Total: $3,021,000 $1.()(J,000 11fc.,rcinl 11y, thc Villaf,"e Mall-lageir's Office 11-11ad to coinvoi-t one of t1he cAstiling coinfcirrr11-11cc, 1[ oorns hrito ain office slpmlc fiji[ a i addcd I u. 11 11-ic Village Aainxci's ()ffiifc !is uun inced of a ceau -ilercincc iraauairmi toirvaii ural las uvcrtlings. f he cAsth-ir,,, records Total: $100,000 ifnance IReqliuests I t einirlized I°~ equiicsts f' aver 202 5 Customer Service Update Window Configuration $75,000 ?,ecoinfigure, cusil'Uncil, sci,vk,c dlivisfol-11 slpxc, era staff aire alble to facc foirwaird Lowairds rq,,sfde�nits aii id givu stallf irnaru c, usable worksl,-)acc� Total: $75,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 12 ry Services IIIIeqtmests Iteinnized I':Zeqtjests dour 2025 Board Room Screen Replacement $40,000 IWO liharecil iis wR11 o a & 19 sdzcd aspect I adu, to I L11 w ouiriio�ifl 4:3 scirecii is. ('11 iiaii ge fll lie einses 01111 thc wri-clint VWCO projcCA011-5 QO n11111 thl, nowscire c In sizes, Broadcast Pix Replacement Switcher Replacell-nell ]I t SwAdhei- foir the IBroar,Vs,aM Nx 111'%�) hn the 11 vselivice's coll ]I hroll 11-winnJAX 11 y1bidd systein Willhi 8 INI(Awoii k 1 4 SIDII inpiiis i 8SGII, C11 !I p/G1-'1j')1-1ocs c1haill-11615, 4 0/11II's, 11"Iknmlfluc3' Civics Events Electronic Sign Replacement $55,000 Ielplaceirriell it foil t1l w c'Asdrig� Ckdcs 11 �vcirit Sdpni, 11 vAn WA 11 C11 1111 11 11�" 11 lbii arid inessage WIRS fiI C0111111JI&NICO W1 SOp J RX" 11 W1 1111 1131111) 11 "IZ11 ("1111"4G, Data C01111111111iilinkahoin to 4G W11IR11 11,11 SSw/11,1111 II OF SK"I"J )Mn jplairi. H iridurlos 116,1111411 11 0111), hirancl IN Village of Mount Prospect I FY2025 Community Investment Program Requests Total: $125,000 Page 13 CaIIIpl[t4III VIIIIIIIFm lull lllir Illll nl nlllirllul m IIIdlti��year VIII' VIII VIII° 101 CapkaI Improvement Projects btdl FuirldhiligReqiuested Ilby Delpairtinneint 2025 2026 2027 2028 2029 $0 1101, E:con E)ev and IPIlanning & Zoning l::Iinaince F:oirestry & GmUnds lir rorimation Technology d/F/ F:4.A.)lic Works rffff)� 11 V Services 0 Village Manager's Office V211✓fl $241lA ON, Engineering I[:: i r e HILBrain Services Police St.ifeet', & IP.BauildliiracBaa 0 Vehicle Maintenance 0 Wateir and Sewer $36�M $311,480,32100 $45,280,202,00 $29,9M,94100 $38,943,,'75100 $32,1132,209DO IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 14 btAIIRvi'diii-ig IIecjjuested IIby Soturce 2025 $34,675,940.00 2026 $45,423,092,00 2027 $30,07,LOO 20 28 $39J80,76'ZOO 2029 $32,365,57100 $3,11,480,322,00 2026 $45,280,202,00 2027 $29,9d8,9411L4P4a 2028 $38,943,75100 2029 $32,1132,209DO $o $121M $241M $36M 0 OM Ge ne iraall Fund 0 020 Cajpl°iLal Il rn1proveirneinL F:und q//J, 023 Street irnprovernent Construcdon Fund 0 024 Flood Cointiroll Construction Fund 037 SIMP: '11111::: Fun40 d 0 0Motor Fucll Tax F:und 0 0,43 Asset S6zwe Fund 0 049 b::Iirosjpect Main TIF: Fund GF, 050 Water and Seweir Fund 0511 Vfllage IPaarlkfureg ": ystern IFLAind (OP W Volhide Replacement IFuulnd 062 4': oirnnitauu�terr 111elplaceirneint IFund 0 09� F:edeiiall Grants 999 To lBe IDeterlrnilned Cajpft:A(,bsts I3ire4kdowin 2025 $34,675,940.00 2026 $45,423,092,00 2027 $30,07,LOO 20 28 $39J80,76'ZOO 2029 $32,365,57100 $0 $12M $241M $361M Calplital Costs 41, 01peifationall Costs Cost Saviings & Reveinues g here's ii io data foii lbi, W(Hing r-111 airt IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 15 IIIIC IIIRequests Iteinnized I:?eqtjests foir 2025 2029 Body Worn Camera and Mobile Video Recording System Replacement $1,500,000 Ilam 2025, 111l a 11 loll ocr, 11 )ej:jairbl, wii o1 s clj I irc int flcc t a )f lba Ay worin caii ncir;,6 will 111 appiroadhirip, the r,�?iiiid of scirvco Iffe. As sillch, 111.11c, inced Investigations/Booking Interview Rooms Recording System $75,000 11 1 plurchaseand instzillatJoill oil aill audio,ii­"10deo roir thlo8 OCAUKI hn hinvestigatJoins arid Boolding, 1111he Mobile Radio Replacement $1.25,000 11 he 11 lolk,c II elpall till,licirlt rl,llahrO aflis an f1cot of 1.6 irnolAc radk)s aMcd Iby swol-11 o -_)e I I'll 11 v, 11 fin i I raincr" of t1h6ir dutics, and airc, ill o t1l If-' If"pah-.11-61ing ofsell vkx� and onlonirgericy callsaind (A111101' C�,Srll 0 fall Ry 202 dx(-Alirirvnt New Lockers -Men's Locker Room $22,500 1111 w (J(r,J[smirtrncii It is Ilr oldirig to iluirchasc 8 new od<CI-S F011- thC uI 110(11<ei, uroorn at t1hC l,urullicC station, New Special Response Team Squad Car $64,000 11 he lohce 11 )qwirill-nell ]I i Is 11 or, lldirig to jj.rluircll uaa.se (1 ) ni(�vv squad cair for thiv sjjwrfall Rr?sj,,x)i­ls(, leariri. 11 the If )c1pairti-irmil ]I t Is fil Il c")kIng to add Ulls vellide to the Vehicle 11 elplacell Illo-O: sell odulcuirg]eir [111111,, Vic"Illick., Relplaceirriellit F und New Specialty Lockers $12,500 11 he 11�101hcc Delpairtirrient is 11001161118 to liaoya clhasc 6 new nNlfsc6aallt: Ilrar.lkeiras. Total: $1,799,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 16 �°re ��Zequiests oaMhcwvnuo, ��� mepicraUvWbomaiOmsand purdwseanextra one hm Rainin,Themot! nr scunerdy|nuw*opc|m�pumhawd|n2OTnWurrd|n 2025forFmchase|n2025, Power (Mts and Power Load Stretchers $285900 PunJ on? 4power coNaA4mmer bad syUensfm Irm HmMmamlxibmNardow room SCBA Battery Replacement $40,000 RCOOLe a H baUrries ain SCIRAcqOjpinricint andall |lw1j)baHc,es�Added |n2O23for comJdcmtunfin 2D26 SCBA Packs and Air Bottles $600500 RepKeenWimwmmrvof1O+year oWSC%BAai,padawhiGa,econmdkrWdh201SNF: 111y, stamdavsondomsidairedobodee�New racpfeceand a|rbot|esWUalso bepurdhA(A. Thermal Imaging Cameras $e0POO Thwpno�cctwas intnoduccdtnthvCommun|tvOwmbsenA Ampam in 2024 to refdace 4 fbenmaHn-raghl Wavras (I KI hn 2029 and 2033, Vehicle Radio Replacement $130100 Rep|acementoftheendre|nventorvufFi,eDepartmentmobi|erad|osforo||vehidms Wrcurrentmdiosare 12years old and nu|onmerbeing scirviccd Wall: $1181208 Underground Fuel Storage Tank Replacement mqdacementofundmomuxdfue|sOr metankm.ThisincWes ewavalionofd`em,mntW*|MMA 2UWOmtank and I ne12POGaaUmn village Fleet Electric Charging Stations �� vn|agomMountPmupo�|FvoousCommun|ymvonunontPmgmmRonuos� T� N Requests Computer Replacement ' End-user Devices $697500 Theschcdu�d�nd-usrrd�wcapcp|��mrm�|nc|udc���dcskmpmmpu��.u�|a��p�8m�gcd�rd|ap�p�o]|Pad��Dp�mer�� scanneoand 25d�?sknhones, 4]thouuhthishas boonunoIngp|mmannuu|puirdhame, Hwas in0 11,01dvcedin00_ Computer Replacement 'Infrastructure $275,000 Theschedu|edIii fmstructupepep|acemeits indude�2seners.1NASe 'and5neuworksvNtchesA|soindudedint1 e2025[ap0111 11mpmvumcntProg,mm|sancw fiile)w,31111, Althoilgh fll Os has II ii an ongoli'lig all'iffluall puirdl ase, it was fintirodixcA Dev and & Zarifirig �Reqtjests 1 :1 Iteimizi:A Rx:rquests foiir 2025 2 () 2 9 Downtown/Central Business District Facade and Interior Buildout Program Total: $972,500 $500,000 ThaDowntown pacadeaii idime,loir 11 luild^u,Pmmiramkannatdimggil ant ImtoencomngeI cinvestirincirinexisdngpmperdeshill South Mount Prospect (SMP) TIF Fa�ade and Interior Buildout Program $250,@00 11 hc5muflh AolurillPmqpec11111[ 11 lintci[ kx BuUdoutProaiain�5,anatdinagrant It"encouiragr,m�vateinvcstinintinexisthig properbcsinthe SmvhNovntPmsn°c T11FDistil ct,ThisIinunannua|communkvinvn�mcntpmo�m, Village Gateway Sign $600,000 oe ignandounshrucionofnewvlUases|onaseatmukllp|e|OcadonsacnoSsthe v|U^oeTheewaA|ucaflonuaro tnbe dete,mined, Village Wide Facade & Interior Buildout Program $500,000 pmp��om�e��T11Faireas. Total: $1,850,000 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 18 T� Brick Sidewalk Maintenance $1,250,000 nemovcandiflicbdcksidcwa|komandamvndflheDowntown araa. Fire Station 11Roof Replacement $525,000 Removeand rep|acetho,00fatFireStation11� Fire Station 1eBathroom Remodeling $1.sm.mmo -------------------------------------------------------------------------------------— ecmodc|ing",00ursmisbing,bathmoms Fire Station 10Generator Replacement $78,75e Rep|acethemene,aturatFireStation12, Fire Station 1zRoof Replacement $425,000 Renncvcandncjplac� � fl-i� � flatroof of11 iii cStat ion#12,Thwpi-oposcdp-o�ccL wisintil "ducedinthccommunUviii vc5d mcmprogiramin2O28f^r considcotion|noo28, Fire Station 1nApparatus Floor Refinishing $150,000 mefinishtheapparatusfloor atFi,e5tat|un13 Fire Station 14Apparatus Area Painting -------------------------------------------------------------------------------------— $43.350 Fi,cS1,tion1.4appairatu,nmorwaUpaintinf, Fire Station »uButler Building Maintenance $28.875 Peirfo,m|nsVarious mmintenancetasks.sucha»paintinsufthe bu||d|noand misce|Ila neousuxUeriur,epairu, Fire Station 14Exterior Painting -------------------------------------------------------------------------------------— $4*.200 PointAUcxtcriorsunaces ofFincSodPin 14that arenot brick Historical Society Campus $1.50,000 Theniuto,ica|8oc|etvCampuscompr|souuf3bui|dinss.bui|tinthe|ate 1Goo'uorvar|v19OO'uandail einneedufvariuuumaintena lice repmirs su.hasne�ro�b.sidin�.windowsetc�11 hep,01pvsedmaintenanceschedu|e|ndude,:�2025-Schmo|11 ouse— Hw^cRep|acementp,vo,am -------------------------------------------------------------------------------------— $360.400 �cp1mccmcntof11 WAC units.asneed�d� nocPedestrian Bridges $73,000 11nspact.rep|acedeck|ngandpe,formstee|str11,110,11,111-e11-opa|rsvfthepedestrianbr|dgesinKensinstvnBusines" Center(IKBC)� Levee n7Wall Maintenance -------------------------------------------------------------------------------------— $1.25.000 Rcmov|nmandrep|mcingthejointsca|era|ongthcconcrctcwaU"fLcvee37, Other Public Buildings $825,000 impr"vementstov|||aam-ownedbui|d|nss, Parking Deck Maintenance -------------------------------------------------------------------------------------— $933.000 Staff requested ucond|tivnasscssmcntbeporilmrmedin2023todetermina!if the curncntmo|menanccschsdu|ewas kccpimspuce With the iofd�terioj[rsdon,Thcrcpu�wmstna|ilcdindudinga5Ycorcapim|p|anthatenouncsUhatthc�,truct"n:— �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 19 T� Police Station Roof Replacement $3,595,700 HdccStation roof rrp|ocememc Public Works Overhead Door Replacement $1.94,040 nep|acethePub||cmmrksfad||tv^verheadd^ors|onatedi^themaingall-age andtheveh|demaintenancesarame Public Works mpzReplacement $wm^ooa RqdmrtI 111hoPuNicVVodmfad|ftx PvvExterior Door Frame Replacement $1.31,250 11�cp|acetlie exrriordooilsandfiamesatthePub|icmmrksfaci|i4/ pvvHVAC Variable Air Volume Box Replacement $86^625 Rcp|eccHVAC,ar|ub|eAir vo|umc(VAV)boues|ocatedatPub|icWorks Fuci||tx pvvVehicle Maintenance Shop Painting -------------------------------------------------------------------------------------— $46.2e0 Paintin�,,,theill eriorofthevehidemaintemanceshop. Retrofit pvvVehicle Maintenance Lighting mLED $48.510 Rctrohitcxi,tingcncrgv|neff dont||mhtill minPub|icVYorkovchidcearagc|iahtingtvLE1 Village Hall Interior Painting mDepartment Areas -------------------------------------------------------------------------------------— $46'200 pa|ntingofv|Uaee 11114111dcpa�mcntarcas� Village Hall Lighting Upgrade $34,650 Total: $9,386,750 Tree Planting Program $1,29e953 11,11andn",treesonpull |icrimhk of woyandviUaoc manedpr"peo|ey,TheviUameoflP,o�pec1curren#yownsappro^imate|y2s,0oo parkwa'trees Total: $1,296,953 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 20 T� � ��Ieqtmests Bridge Improvements 'Business Center Drive a fin flicuseh||ncofovsnwssCcnlurodvebddoe Bridge Improvements ' Lincoln Street $135,000 Bridge Improvements ' Sediment Removal $25a0,000 S|tbuUdlupanmc��enmwundnua|hvof�n�rdn�u�/bnd�eetu|ve��Thcp|un�dwmrkindudcsncmuva|orsi|tundgnbi|iain�s��um bankstop�ven Busse Road Roadnecomtruction $650,000 I.cH41 costs1l wirc oft�Cook ��mw11 Fg,11 wayoclimi, tmcii d:'sremr�m(Aonwsvs�kuad,Thic co,�J, fair thcpof(_ctwfl|bc fluindcri byaGmk CwmvGrant, Central Road Pedestrian Crossing |mpmveme^ts $J.00,000 �m�emen��innofCmnt,a|R^adCorddu,FledeshrianCms ing��udvecmmmendatiuns�2O2S ��UeroonshruuUun $100,000 Corridor Street Lighting $2.586,000 11nstaUut|onof11,sostrr,1UmIts a|onmmm�o,corridoro,Poi r!ntfall futin ncpnojc( � s|ndudc�2Or5 nundRoad Wedgewood uancmCamp Mroona|dmoad2n26 ousscI A|goncluinRoad m11 -m3202/ DaktonStreet 11-90to11 mhvi,st1(111183)2028`' Crumley Detention Basin Repairs $300,000 11 11 osfoinunxmdtI m|nMOwSUmcme11`(�(fufl es|onmtenmropah " for t1l eeffective oparatonofdhede�untionbasiu De imnmndcom,,tmcdon W111111 focus oillm(whigsto,m%vatcrtothcOutflow stmr�tuii (" witholut croding thic. bottorn of Uhcbadu Detention Pond Improvements ' Pond a $325,000 11 11-6swro�cctis dos�gnl(A toimpl ow�1-110, capacity and oj[wnuionofd-11cdetemtionporld sys� om� Detention Pond Improvements ' Pond 6A $325,000 ��I f-, de"dginoll to|mpi,ow",the cajpadtvand "ltention ofthe dctentlonI systr,11111. Kensington Road Left Turn Lane at Police Station $300,000 ConstirucUonofaoft, tum|amconnensingtnnroad for vchidk�access tnfl-lo nd|ceocpartmentHeadquarters, McDonald Creek Bank Stabilization $2,215,000 0olbHfiadoiri of stireambanksolloing AdDoindld[ireell" toprotect mllmce ofgmnmwaterundd-le|and of adjwc�eii IIIpmperhes,pirevell �t cmaimn,andncmnveimmsiw:plaints andbi ocs, welas/weadowsPark Pedestrian Bridge $6,978,301 ConstrucMonofa11 �ridmeovermorthwest11 |ohwavand theUnion Pacificnai|roadtrarkc2O22�Phase 1snmineerino [omp|etmd2D24@202s�Phuse2sngineerinf,,2O2u�Const ruction @ConutrucdnnsnginnCrIng Neighborhood Drainage Improvements $358^000 -------------------------------------------------------------------------------------— Coil struct|onofdrainaacill p,ovemcIts toaUcviatrociahborhoodflnodir�gp,ob|cms, �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 21 T� New Sidewalk Program $1,850,00e �n�aUncw�dewa|��a�|oc�kmswh�n,nomccurncndv�x�t Th�h�|��ng|oc��nsv�Ubccnnsid�����rthcn�n fw���rz8u�aRood fmm�mncrie|��u�loll 90mLcxinmmnDrive<noii tIII - Northwest H~v& Central Road Gateway $1.300,000 oe ipnandconshrurtionofagatxwmvtuindudeviUameentrvmarke,docktmweirlmIroenspace'pub|icparkinm|utand�ree�capeatthe inte�ecionofNo,thwe�Hwr��entra|Rd Parking Lot Improvements - Public Works Back Lot $300,000 ZC113arU111Cmirlismnde�il facle U-iePuliblic Woll-11"s113'ad" 11 oL Parking Lot Improvements ' Public Works Front Lot $1.00,00 i,�Ojpalrfl-lic cuirlb and insuillace fliePulliflic Worl(s iiiroiMbol, Phase xBike Plan Improvements $11'738.872 Cunsirucl:|onofs-harcduse puths.|ishUngand assuciatcdwayfindirgo|gnsa|ongcorridomthat mcctthegoals oftheV1UaaeBihmP|an Pvlcntia|prioritvcoil, ridosInclude mcnsingtun?,uad,Centra|Road, Imoad'mandRoad, andw�|f' Prospect Avenue Improvements $125,000 Redeveopmentukoll gPruq;ro Avenue 11-11"ospun, c"ddede'Jnefor uutdoo seanmsinfl-licsumm*rn-lowit ho 11 11-11oIre bcon idemlblvmore pederu ianiandblcvdeacdivltvdmwI'll tuwmwiththeaddihonofnowlr�stauilantsandS11-1mlp1pingTheViUaoe- Rand- gm»unt-KenunumnRoad Intersection Improvements $12,640,600 lmprov�tranhcflnwthrnuahtis, triung|eill tcrscct|on,Fu||"=|nmcnmp|ctionofPhase11lin 2Oo2,Phaw 1111sno|nccr|noand ROW acpu|sit|onr 2O22-�O�5Phasc���Constru�iunandConstmcr|onsn�|n�crin���Oz6-�O�7Thcv|||a��wi||b�rcqui,cd- Residential Street Lighting $2,000.000 11nFI�a|ati^nofUEDmreediohtsill st4ectedreshlentia|neiuINbodn^*s.Poten ia|huturepn�ects inc|ude:Bumifling BushLall eheu*een KcmJngtonRoad andEmdd AvanucBu,ning8ushLumcbcmvccnCamvMc[ona|dRoad and 5zmino|eLancliAdcrRoad between - Schoenbeck ' 11 ho Ila Upavement11 las alow PC1natinma ind isduefor rosurfaciii Thevi|bgeamped foll a rid III asbeenawarded afedel-allSurfac 11 anqpur�Mon11 lmgiramF"lliantintheamountof$29/,000uaiil IopavementfillomRand Road t^Camp- Sidewalk Replacement Program $2.335,000 Rcpairdefect|mzsidcwo|ksthrouahncmmo|and rclplammcnt, Poir don offunds devoted torcs|dantcost sharcprcmmm, Street Improvement Program $39,508,066 meorfacmsnfthe N|bgestireel:stomaini-aina2Dye r|fe. Streetlight Improvements $498,077 Rcn|accmcntofcwistingstrcctUghtsusc"nditionall lid age, ne(,rsskatcs Traffic Calming $250,000 11mp|ementationoftIle, Friend|vmeiphborh^"dStreetsIrall . the vi||age'stra+fic-ca|minmpropram, Iarebnthresidentand vi||ame- in|tiatod.and can be|ncorporatediink) theStreetxesull �ncinoIii ^mramo,aMand -a|onepro�ecL Traffic Signal Replacement $508^000 �oudmcinspcc ionsufcxistiniotirafficsIgna|cquipmcntandcinghnechmestudicyofimrrscctfonsossistindetrnmininmthencccssarv �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 22 T� Wolf Road Rehabilitation $2,803100 VVnf11�oadbetwecnEud04vr:�i-/ucand[onfirm|Road was comstmctcdfin thceur|v199Oswbhaoonrirctc,S|anc,cmsc~actkmpavcmcmcThc pa.�me,�issh��n�pignsnfcrackinaandd�rrion�ionTheViUae'cannUedfoil 'And huslicun— Total: $91,099,010 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 23 T� Water ar�id Sewer ��Iequesls Booster Pump Station Pump Rehabilitation $1,125,000 In:cn msandI rh l-A|NaJono,tll IcwUmpC,5cebting11 "cmk:cpunn1ps Combined Sewer Improvements $4,000,000 lo ii-cparaniftrnqj��Place111-lainUilic 0 &,smated structilunsinmmbined sxnh�o,sell-vice allic"a". Deep Well Rehabilitation ' Well #16 $535,000 Muintcnunceand ,chabi|itutionofthcdccnwell, |ocatcdot000sterStation 18, Elevated Tank Painting $81.0,000 lnqpectA^n.nepai,andcoadnmofin0.crorandextohmrsurface oftheekovmtodwmtcrgoi,agetank, located at 2O",E�eirgi-oenAve Fairview Gardens Overhead Sewer Program $1,880,000 Th(�c"ll lvcrdonofIII mp(�11,6 �5 located |ntl-ioPmirvirwGmii dcn subdivbionM1 ia�have susperk�ddii-ec fmrIng t |cconnect !oro�oN|kag��s' saii y scw rfl-ivsnointr|buting,dcarwatertothr-,Fe|ll vicw11 �ft statfon, Lead Water Service Line Replacement $2,450,000 ���aoymyr ofeadrmtorsol-vice ||nes� lin 2O2Sund2O26tl,iepm�oc N albcatod$1OO,0OOeach Year hv|ead Service Hine nelp|aoemen cos shapep��amSlArdms|n2027,theaUocadon!is the cost tuIII 18Y',of|eadserfioeUnes Leak Detection Equipment and Utility Locating Equipment $80,000 Thcpurchascofncwwater|cukcorrc|ator«.now aruust|cwmter|call detC,t|onde,iccsandnewvti|itv|ocat|nscnu|pii I ,Thcscpurchuscs wU|cont|nuetoh6|put|Dtvstaff idcntifvthcsmact|ncationofmwmt�r|calk tuho|pmin|mizcw�terund— OaxtonWater System Expansion $758.000 11nstal�|m�onofnewwKlterinansall ldussmjatodwater mpnumanance iI'll na*lyall nexedareosthidtdonOt 11 Cc ivevU|agewator Overhead Sewer Program $5oo,000 xooverhcadsanhmrvsewcrsystonoisdexmncdtoI sanhar/=ugc, (Scwamc) momflswnsback imothehoumC, W11 lichcunocmrf0ll� dfiffeireirit ivasoll is orle of flh(�11-1111 11hriling 11-11cavy ii at in cvc in ts w1l w�ire flh�� vfllag(�,s connihlilmd SMA101" 11-1111 a !III 1S �'Pt 1111110d t0— Sewe,Main Rehabilitation Street Light Disconnect Cabinet Replacement $�0Q0,000 $500,000 Relplaccmcilit of oxistfinvgrect|fp,11 itfinmdiscoinncc � calbinctsdue, to apo, equillninneint ���I riew coc1c., rc,,gulationsairld wairlphnig of Streetlight Improvements LED Retrofits Retrofit "fcxisf1mmstirccfligl-litstoLEDtcdnno|ngvA]|stircethgll AsW11Ubccon"cii ted toLEDatthiccndof2O24wRhthccxcephonofthcNclas Porkpar0mg|o«|il;lhts69PcdcsAihfin sirccflighftslave been commrtedtnUED1Gn�Icdesthun— vFoReplacement $1.00,000 Turep|acethmvariab|mf,oquencvdriva�(v�o>atbno�terstatiunu,vll 2025v11 o'utobe rep|aced�soo�te,Stat|on�� Wo2113ooMerStat|on5 vIT)l 113ousterStmtivn1/ Wo82O29vIHo's— wate,Main Replacement $32.892^000 Anmua|wm�ormuinncp|accmcmc �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 24 T� Water Reservoir Number 11 Rehabilitation $700,00e lnsIpecb"ii �,ncpa|rardcnuingofin0crknrundcx11 criorsurfacc ofwaarstomgc tank��boatedutBoos�crStation 11, Water Reservoir Number 16 Rehabilitation $685,000 Inspme(doill,nnpai,andcoaimmof|nO.erorandexteri^rnurbre ofwatergoage taill( 16, locatedatenostcr�Aac fon 1A Wireless Telemetry System Upgrade ' PLC Upgrades $1.00,()oa UperadcSCADAtc|cmcUvto|mpmvcwatrpudhvand systemovcratiouP11 Cshave anodmokd|ifeof1.2years lin 2028,rplancmon of 11311 Csisp|onncAaLBooster StailJoris1�16,17Bevated 11'ank Fire Vehicle Replacement Total: $52,237,000 $2,964,000 Repacementof11::ipeDepail bmeotvehbesandequipnleirit, Annuall vahldeQasc�povmeits ane*akulak'�dfor euhvehh ebasedont1l lie |ifeof flic vel-ilde, mflculallxA hnteirest and trllhe~ehic|emccountso|anceThnvehic|e|easepaymentsall ,— Police Vehicle Replacement ��6,000 mcpaccm��ofi and eqii A �pmcntTheannua|vc6lide ca�puvnrmsarc cuko|ated10ncad Vchiclubasedonthe Pool Vehicle Replacement -,1ejp1x ell-nellit ofpoovo6ides all idenuipmentAmmua|vehlde|case pavmemsall calculated for each, "ehidebasudonthe |ifeoffl-ie vehide call cu|atcditai cat andfil lic.chic|coccoulit ball ancc,Thcvch|dc|cooepavmcn�apo�zo|cu|o�donnuoUv' Public Works Vehicle Replacement $5,824,000 Total: $11,325,000 triliarii Services Requests Community Connections Center $4,500,00* Cap�a fundsfnrpos���pu����vfpmn��mndcon�nu��n.fonexp ndednndrc|oc�ed[vmmunhvConn�1�nsC�x�c Total: $4,500,000 �� vn|agomMount Pmupo�|FvoousCommun|�mvonunontPmgm� m�onuo�Page 25 T� VilllIlage III IIInager`s """ f ii c IIIRequests Iteinnized I:Zeqtjests dour 2025 2029 Village Manager's Office Conference Room fcccii &Y, tlhcVillage IMaai agcir's Office 11 uad to colliver t oll �c of fl Irc, cxlMJii qa coli dcirc,,ii ucc roon-P, h of aero offe sjp:vu k a uncwly )fj(]C(j 1 1111 le W111 ige 11,Aanage.ir's Office ns h o 11-11ced of a coil 11crenc o ii ooirri ft)ir vairk)ius ii I hrgsf 11 ic oxlsdii ig iro coirds,,, Total: $100,000 II Inance IIIIequests I teirrilizedRequests foiir, 2025 2029 Customer Service Update Window Configuration $75,000 :fccoirrfigurc ( ustol-ricir scirvicc ,,Aaff aircalblc to faofoirwaird t0M)rds i[ esu&�Illts aind j�ivc Staff rm)ire Asalr)Ilc worksjj-,)ao,�, Total: $75,000 ry Services IIIII.ijests I teirinized IIIRequestsFour 2025 2029 Board Room Screen Replacement $40,000 Wo irrrMprized Sowell Is rerun lh a 6:19 soz(A a,;jpr,ct rado, to relplace f 11 m, cuirircird4:3 scir<ori, . ('11 airigfr^ fl -le Ilenacres oill t the (A,111 locint Adex) Irairojectoll's to r111111 the new scil-cell � slzcs. Broadcast Pix Replacement Switcher 4S1D1Ihnj)utso 8SG11, C11 p/Giralphiks chanii rc 11s, 4 0/11)"s, Nr; wl3 uc, Civics Events Electronic Sign Replacement 11,,aq)1aceirne"11 It foll, fll lo cXlMJ11 IR Civics Evc,,ii L fAgin . 11 wnir WA 11 C11 11 ::1 FZ 11 IN aii Id iw�,asagm ull liks h o coll-Ilphaince w/ S(A j 11"'IC 11 W11 1111 11 1111 ) 11111klll C 1111\11G. 11 )ata coil nii nuinicallAoin to 4G W11 F1,11 1111 SS w/ 11,11 ll::::: 11 DIF: SlIGINI IfData IpllQaun. 11 t IIIII(A udus IIG1114ILf l 011FIX 11)1rallld jj�)111, uRll',] 11-111 i°III i', alld 011�)C Ira thlifl— Total: $125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 26 uum���` uuu�l�` um�m uum lig., Village of Mount Prospect I FY2025 Community Investment Program Requests Page 27 � Ilu muuu m uuuum m uuumum IIIIIIIIIVIII IIII Y II ° mmuumuuuuu uul II^� l II um�m DILL uuu uuuuuum "" III mo uuuuuuu I I uuuuuuu�lou�uuuuu uumm� IIII IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 28 lllIlltmsfirmss III' ilii strict IIIIIIIIIIIaeiiinid lhnteriar IIIIIIII uflWoul: III' irogrann Ove,irvkw kxxpj('°d Owiliell, jx�oini slhallc I, w,% Dfirectoll, or ('10111ilinuilily Devidolpiriell( Dell Ia - tin lell 11 con 11 )evai id 11"lla11 iiii uiiu ig S, 7oning iyllI(' Cajjpil.'a11 II illipiroveirilicilit [)csc I i I 1 he Downtowin III -)iriid Ilrnriodoir Iffilildowt III i kaFnal,rdling, uxrrarfl progir"InAl f�o moos 0111N1"1'1C prlv,ut�e linivc�,tinnic in t hn o r isLiin> lyraapaoiril'ies 11111 i'lle, (If 1111lir a I Busilloss DiMirld 11111S proicd is -all aillilluall progrann I I )(AS Ak 11111'0aucl' I'lluiril'-Ici, Af,coui'A 11111unrillbor 11111'0�ed Life Ccitegory 1:111,forily Stirall.eglic Gxill IN flfl'i('Irailnt 11iAnd(xP Justification CID 24 01 049A0 90,0Ct0,/l0A3&00/ Yearly /10 1\41"c(rdlaifvxm!, 9..`r er;r innill-joid -iind (,1o,dl b Vflbirninid Coininunilly II Dua,1'.iiinRatloifl,,: DowinkmAllin, Ii'e hu l 1, Vill 11 r' South 'Armillill, 11111-o'ij"wd arld CWhicir Cloirninnlei-(Jill Call rldor" 1111f) Locationi 1Ihrt,rcauoflfrrr,n,r,arninuriceiruiilviirrnrs1111u-rsur:;iunvr*T, 1, inneird, 11 in proj-A.�Irt ies 11 11 o L11 le Cell it 11 '11111 A A rn..S.' 11 A"All (A i'll would ofl eirwise 11)(Kell nt i� d1l Y 1 -lot �'ee ullikeelp and I111-111pirovellineirlit, r5pecially dlw to I'l to rurirr"�Irll' fiilaurldlll diiillatethlsk illidudes lnlae�i'�ed caristinxtinin cu�s i'aInd 11-ligh ill ust i hese f 11Top rovell-rielini LI w1111 iinaiiiiLafin and eiilhisncr, dhe ncirew,ed n�.oinninneircfall vil,'Abdity ";cen by the befing buill, fin I'llhe Ceinllr&fll DNricl- Operating Budget Impact Noille IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 29 Inflationary Impact NN alpplicalble Capital Cost FY2025 Budget $1.00,000 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 111111111 ConsLructioin Cost Project Total $5001K $i00,000.00 $100,000 00 $ioo,000.00 $ioo,000.00 $ioo,00000 Capital Cost for Budgeted Years 1111111, Construction C:(,),,,t (001X�) $,"00,000.00 TOTAL $500,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Construction cost $100,000 $11oo,ow $'� oo,000 $100,000 $100,000 $500,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 30 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year 2025 2026 mom 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 0,',,9 IPiroslpect Mai'iin RIF If und Project Total $5001K $=,c: 00.E $m0,000.00 $m0,000 00 $mo,000 oo $mo,00w)o Funding Sources for Budgeted Years 9 049 Prospect. Nlafln 11 li::: i::und (100%)$500,000 ( TOTAL $500,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total PIF l und $100,000 $3.00,000 $ I oo,(xx) $1.00,000 $ J 00,000 $500,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 31 Sow µh11 III Ilbtriinit Rospect (SIAP) and Interiarlll3uflMoul: IIIII2iirogr'a�lin cNavow Ovoliell, kr'oiri 511-11allc I, m'% Dfirector o I C,aillinuifly Develojjpivieiii4. 11 )ell tin lell Imam Nox MW PKMalai C& AM01, �Q' CAAWHmKownnfl DwilpHon HH!mkmd MM%r ")Irogirailll 1:11le flll:'Dkkirld Wages INAHS ckwmy bKomy SdaiNglic/Gall Is fliN Girriint Funded? Justification /;11,1.y4 x.12: 0344U9aN%R/1R63&00/ Amind pmWwn IMMIKwhimmis 2 Very Ili 11portaint Chi 5 M bink Cann a My 11 )e,,Ulii o a lonu ,: Dmmnkn/vili, Vlll,q.,rp'solltlii I II11-osjpe(J ")11d OLI)cr Cornirneirclit Cbinrldar,; I � 11 le Coll ill lc(A SouiJI o I NwsMyl POW dsion qamwk Sk H'Soiudl o I it liru,jjpccl' to bc,'u "aAoelcoii r[ire aii id LI-ii,tviii i,,,r area w1l lidl o wI1111 W W a W ON OKO U a WOUC in& W 'ITYSM WON WMIlOwn a 0 OmAkorlirlull ity", D 11 le rrmtcll &-ig gi �mrfl jpiro,��,,raiirri 41111 lA,jI sjjuirt bu�Jii leisns mh WWu Q owins AM ov araaalld ;g W uwk0mKownmiN aA hwal Mw Uwm ty do an Me mAdQ pas wM Akwqnal how Mommy i not Ibe able to do so iun d ora Current hiriond111 aallirnal'e due Lo u-1,Jng mondhimmN YW h4m=u. Operating Budget Impact I IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 32 Inflationary Impact "larle Capital Cost FY2025 Budget $50,000 Capital Cost by Year 2.025 2026 vam 2028 2029 Total Budget (all years) $2501K Project Total $2501K $,,..nO,000 oo $50,000 00 $So,00000 $50,0000. 00 $50,000�00 Capital Cost for Budgeted Years $0 $ 21K $241K $361K $4,81K 0 Construction CosL (100% $250,000.00 Construction Cost TOTAL $250,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Consbructloin cos4 $50,000 $150,000 $50,000 1150,000 $50,000 $250,000 Totall $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 33 Funding Sources FY2025 Budget $50,000 Funding Sources by Year 2025 2026 mom 2028 2029 Total Budget (all years) $2501K Project Total $2501K $".30"000 oo $S0,00000 $S0,00000 $So,000 oo $5o,o0w)o Funding Sources for Budgeted Years $0 $�21K $241K $361K $4,81K 9 037 SIM P TIF (:::unci (100%] $250,000.00 1111111111 037 SMP 1111 F: F u in d TOTAL $250,000.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 037 S M ll) $ 111D 11 ru in d $50,000 $50,000 $50,000 s5o,000 $50,000 $250,000 Totall $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 34 VilllIlage Gateway Sigriul 0v(,,irvk,w kxxpj(''d Ovvinell, )ell aa r tin lell ri iy1po jx,oiri slhallc I, w % Dfirectoll, or ("olinlinuilifly Develolpirif,1111( 11 con 11 )evai id 11"llaii iiii uilu q,, S, 7onling Cajjpil.,a11 II uuop:riroveiruncint )csorilpfloin IMN Vill kwatioii"-, aoros�;the Vill bl�go tolkde�einrdined. I innages )(A"Als 11,11roject 11+3irdber Aecountr IINunmdheit 11,11roject Aff, Category 11,11-10111ty Stirateglc Crmll IN difs Gir,iiritii,iindpd? ('11) 24 0/1 1311) /1.0 111,llscrdlzainrous 3 II inl-mirtaint Goall 5 'VIbraii it ( oiiroiirouinity DcMJIndtlan";�°DrAvvinLowin, SmAlhi Mount 111irosIped and othcr ("ol'iriffirl("Ir6:A1 C'oinrldarc, No Justification As, l of L11he biraindin"', '�)kln to ci'eat o a con,;�,;b �Irlt iiln��ge and birand ror the vfllage, insuillhing g,'Anwaylcinl rainceway Supnage %41111 crow- ,e a "onse oi Vill 11 W"c/i ienipflinlberirll 000d ldentlty "311 d s11111ow vlsloars 11:11u Ilenow t 11 ry are lin Arxnl[ 11111u,,pcd:, Operating Budget Impact 1\101111e, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 35 Due Ix) f III I I adan, 1,11 le cost: or ca, uuirmi,inii I a, o rnal,eir!! all s u^, exipecI,ed to k l Capital Cost FY2025 Budget $600,000 Capital Cost by Year 2025 2026 2027 2028 Will Total Budget (all years) $6001K Project Total $6001K $600,,000 00 $D000 $O000 $Woo $,0000 Capital Cost for Budgeted Years $0 $I501K $300K $450K $6001K 0 Const.rucLion CosL (100%� `�,600,000.00 1111111111 ConsItructloin Cost TOTAL $600,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total (1,01ISbructloill Cost $600,000 $0 $0 $0 $0 $600,000 Totall $600,000 $0 $0 $0 $0 $600,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 36 Funding Sources FY2025 Budget $600,000 Funding Sources by Year RM Total Budget (all years) $6001K Project Total $6001K $0 $�501K $300K $450K $6001K 0 020 Calpitall irnpiroverneint FLAnd Funding Sources 020 Capitall Ilurnpairoveinient. 11wind Totall $Ea00,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irnprovorncni::und (100%)$600,0 TOTAL $600,000-00 FY2025 $600,000 $600,000 Total $600,000 $600,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 37 � ?0 VilllIlage Wido'.1 IIIIV������acade & lhrileriar ullWout IIIICiiuroiliiuriiiiiri 0v(,,irvk,w kxxpj('°d Owiliell, jx,oiri slhallc I, w,% Director or ('10111ilinuilily Devidolpirif,1111( Dell aa - tin lell 11 con 11 )evaii id 11"llaii iiii iiiii ig, S, 7oning pYjjw Callpil.all II illipiroveirilicid [)csc ir i pfloin RieVdlagcWide 11:�wadcaild lirograinn ka prolperkie,,-, ouLdrkHho p f )cta i I S 11,11rojecil, INUI-111ber 01) 24-03, h,cmvnuIN unroll 020.40.90.00 D.710 636.007 Flilojed Life Aninuall jjprop;,rann rlatq�,pry 71.0 111,lkcellaineous 11,11-ioril'y 2 Very Il riniportarit Stiral,cgkGoall Goall 5 Vilbrairit Coiniiiiiijil lity Desth lal,ial,,:DowilLowil 11, 11,1,andhiji-,;d village, SoW h 11,4oiji-it lirwqperft all id OL11 lor Con-lirricirciall Caiiiiudois kflflsr 4 all it 11uii ded? No Justification p 11 -if, gj,rajjnt, jjpjfrngj-',aJjjn il-[centivizes pirlvAe inveshirient ill Irrojwr rtlm, whol e p 1111: noney N na�: availalblrt all id Ullatwould otherwisr, 11)(Ar"llifl Ally unmot,, See uIpIkeelpoll id e,Jpc( ally due to tho cli ii-irenill, hilaii cfall rlliuuuaate 011 uaat lirnduudes ui ic irea,,,ed ( cni%brucUoin u),As and h(ugh fini,eii ccl. ii A cc, p Ihue,nssee ill 1111I)ITMA nlellt�s Willl 111W)ill IlAilli allid �=Illhai-Ke I he r:oilriilnorciall vialbility t Ihureaoug,,lhe,uit the Village. Operating Budget Impact None Inflationary Impact lkm lie, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 38 Capital Cost FY2025 Budget $1.00,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 1111111111 ConsLructioin Cost Project Total $5001K $i00,000.00 $i00,000.00 $100,000 00 $ioo,000 oo $i0o,o0w)o Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� $S0C),000.00 TOTAL $500,000-00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total coinshrur-01011110 st $100,000 $ 1 oo,000 $100,000 $ I oo,(xx) $100,000 $500,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 39 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year 2025 2026 mom 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 1111111111 020 Cal pitall Ilirm1piroveiment If und: Funding Sources 020 Capitall hirnpiroveinient 11wind Totall Project Total $5001K $=,000.00 $m0,000.00 $m0,000 00 $mo,000 oo $mo,00w)o Funding Sources for Budgeted Years 9 020 Capit.al Irnprov rncnC i::und (100%) $SOO,O TOTAL $500,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $1.00,00() $100,000 $100,000 $1.00,000 $100,000 $�5oo,000 $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 40 mu � ���I,I m uumuull� lumi VIII uullll mu uuo uuuuuuu uouu�uuuuu uuuuu uuuuuum II umm uuuuuuu uuuum uuuum i�,. uuuuuuu IlVmmulm Illlu.. uuuuuuu SII IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 41 IIIIII ridgeusinInnes Center,1irive 0v(,,irvk,,w kxxpj('°d Owiliell, IAaH II ;Iwirlr', vfllklgeFingilincell, 11 )ell pa - tin lell 11 pYjjw Cajjpil.,all II lillipiroveirilicilit [)csc I i I 11311 Hge relplill's l:o Ariniiit,�)Iin dic w;(!rull fille offtr;h I ess Cenll,eir II urivee birldgm. I i 111,111s,Mlle "Sceill'o, 11 ir1ivel"ridgv �I RS`UaHs 11111'0ucl, 1'1Ih,llrl1,-)u1' 17 II)W 00038 Accoui,A111wri-ilbeir 020.80 90,00,1,/Ob.6/8,008 11111'0led IIffe 30yean, siustalincflblhly to key dhielhusihrw,�, pai'llk. C�,)egory 705 1:11110111ty "', ilnjparl,,'11111� Shr,Aeg,lr, Goal Go�fl 3 pbjp Cjl,lalfiyVlllapinfirash lidure: 1114kjnced and lrwwp ive Conlililli.A1111HY inivesIllnolill, 11 a dllair, Grailnt 11ljinlded? III Locationi Justification flhe2023 111,irldge inspectioin Relpait ccoini-noinded lelp.All-sto III lie whigwAll, ,irld the hoaprlanrrdl, Operating Budget Impact 114oiie. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 42 Inflationary Impact Nolle. Capital Cost FY2025 Budget Total Budget (all years) $1.05,000 $10 5 IK Capital Cost by Year Project Total $1.05 IK 2025 $105,00000 $0 $30 IK $601K $901K 111111111 Consltruction Cost Ob Constiniction Engineering QJJ Design IEfnglinoorling Capital Cost for Budgeted Years 1111111111 ConstrucLion CosL (76'X) $80,000.00 4111 Corst.ruc6on E.:ngim.h.ning (101%) 100,000.00 fpp I)esIgn � ngineei incl $l,."000.00 TOTAL $105,000.00 Capital Cost FY2025 Total J1 lgill')OU'llIg $1 5,000 Coil rAirm"doin 11:11lip'll le(111,111111P1, $1 (),000 $10,000 Clonstirluctiolin Cost $80,000 V.w,000 Totall $105,000 $105,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 43 Funding Sources FY2025 Budget $1.05,000 Funding Sources by Year RM Total Budget (all years) $105 IK $0 $30 IK $601K 020 Caaital llir>rn1piroveiry"irt: IFLAnd Funding Sources 020 Capitall Ilurnpalroveinient. 11wind Totall Project Total $1.05 IK $105,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irnprovorncnt i::und (100%)$105,0C TOTAL $105,000-00 FY2025 $105,000 $105,000 Total $105,000 $105,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 44 IIIIII ridge I hricdhn Stareet 0v(,,irvk,w kxxpjos° Owiliell, 'AaH ;Iwirlr', vfllklge Fingilincell, 11 )ell aa - tin lell 11 pYjjw Cajjpil.,a11 II illipiroveirilicilit [)csc ir i pfloin 11311 Ila ge repnill's l:o Inroariuutain u 11 le u A scruill hile of 11 incoll in Silli biridge. I i Lliricolin sljrccl1151, idge �L)(A;Ak 11111'0�ucl, 1'1h,llrl1,-)u1' 24 II)W 00 100 Af,coui,A 111unrilbor 020.80 90,00A,/ObA/8,008 11111'0ed IIffe 30years siustsllincflblhly to n6g,liborhood paii ks roir 1-1-iotollisi's, picyclisLs& jjpedcMlrlair� (,:�J1eqrvy 705 1111110111ty 31 iirijjpnirlall� Goall Gonll 3 pbjp Q1 nflily village IhiltIrashl U(A uire: HARlicedand 11111-oK�(Aive Col-nin-luillity 1111IV12FI117101111p s t 11 In (1, a int 11 u A inded? 11 j Locationi Justification p he 2022 1131rldge llii is vas ctioni 11aqjpsiirt i, ecoii ni[neirlided i to t1he deck soffit, Operating Budget Impact 114oii(= IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 45 Capital Cost Total Budget (all years) ..A. IK Capital Cost by Year FEE t$0 :$401K 0 Desigin IErngliirneeriimn Project Total $1.351K $13":1,000 00 $801K $MIK $$($ Cckin ftiru.actioi r IE:,irrgiii eeiriiing Capital Cost for Budgeted Years <.:rrror>ta�ura.irrrr I:::Irrr;'ineer lrig (rl`Y) $15,000D;} TOTAL $135,000.00 Capital Cost FY2027 Total 9e,1giru IE iru ,1irora':u 1umtu, 120,000 $20,000 f;arussbrua i u rnIll:Ing'ii un' eir1umg, $15,000 $15,000 0 d,uuirosbrun u.oiru Cost $1.00,000 Wo,a,)oo TotalV n,(135,000 $135,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 46 Funding Sources Total Budget (all years) ProjectTotal $1.351K $1.351K Funding Sources by Year $1315,000.00 'N 020 Calpitall llir>rnl irovaairrcneint:IFaairnd Funding Sources 020 Caap itaall Ilurnpairoveinient. II wind 1p ottalV Funding Sources for Budgeted Years 9 020 C;::zapit:al IrnprovcrncnC i::und (100%)$135,0C TOTAL $135,000.00 FY2027 `oa135,000 135,000 Total $135,000 $135,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 47 VIII ridge Sedfinneml., IIV' ,eiiinn aVIII 0v(,,irvk,,w Owiliell, "U1 11,1wil-ir" villklge Fin gilincell, 11 )ell aa - tin lol 11 �Yjjw Cqjpil-a11 hillipiroveirilielit [)csc I i I Sili'l-xii1d aI -) Gaffed 9I rk nwannid cl , ii�,� Ili y of wat�a 11, U Air(^ rirwAinii i rfl inultill-do bir dges hinicluding: 0 wolrl'load I If I ktaik 11111-0aed Nuinher 1 / 11)w 0003 / Accwnl: 111undbeir 020.80.90,001,/ObA/4f.008 11 Life }raa,elrc Cntegory /05 S, GoAtteirs/.SidewAlks 11 111-fority 3 11 iTillpoirlaint Stildilegic C(")all Griall 3 fojjp O6uAlLyVII111,Age iifra^,h 113,flanced and lro,wllve Cqjifn inn u in !I ty inw-Anneinil. kflhi�-, Graint 11 ijindled? "k) Locatioi� 11 Justification liri,,Jjpr�dion rell-joirl"3 "nid hold (AbsollwWolis by"I'A I! I rol-ifili'll r I l I llr� One flowotwal'or. Operating Budget Impact Noille, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 48 Capital Cost FY2025 Budget $250,000 Capital Cost by Year Elm $0 °;601 Desigin Engineering Total Budget (all years) $2501K Project Total $2501K $2S0,000 00 V201K $1801K $24010 411 Construction Einglineeiring Capital Cost for Budgeted Years 9 Const.rucLion CosL (80%� $200,000.00 411, Consuuc�.Jon I: . ngineeIing (818) $20,0MOO fllt1)eGIgn nginee6ng $ic),000.00 TOTAL $250,000.00 Capital Cost FY2025 Total 11)(�S1glrll $30,000 ("ollsbructloin 1: Ing 'i I-11 ceir 11111 g, $20,000 $20,000 C<)Irrsbructioiri Cost $200,000 $200,000 Totall $250,000 $250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 49 Funding Sources FY2025 Budget $250,000 Funding Sources by Year RM Total Budget (all years) $2501K Project Total $2501K $0 $60 IK $�201K $1801K $2401K 020 Caaital llir>rn1piroveiry"irt: IFLAnd Funding Sources 020 Capitall Ilurnpalroveinient. 11wind Totall $2SO,,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irnprovorncni:: und (100%) $2S0,0 TOTAL $250,000-00 FY2025 $250,000 $250,000 Total $250,000 $250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 50 VIII ridge Seeewixn Aveintje 0v(,,irvk,w 11'1,eqiues° 0wiliell, 'AaH II aIwirk�, Whige Fingilico, 11 )ell a - tin lell 11 inginiceiriling �Yjjw Cajjpik11 IIaIroplroveIruoaaIilit )CScirilpfloin 11311 Hge lrejjx�,dirs l:c nwiii itAin ill le mcifull hile lif seegwwn Aw'11 I, I je bil idge. I inniages lkv7wun Avrinix Bridge 11X«AIS 11111'0a rl, 24 II)W Of) 10 1, Af,coui,A 111wri-ilbor 020A0 90,00A,/ObA/8,008 11111'0ied IIffe 30years siustsllinlblhly to neighborhood paii k�, roir 1-1-iotoliki'ti, picyclisLF,& pedc"Ll'.1bir, 705 11,1110111ty 3 iirijjpnrlani� SPi Goall Gonll 3 bjp Qi 4nlily Village hiltrash w l ure: %flailics'dand 11"110adive C I onnin-luillity 1111IV12Stlllloillp Is this Gir a int Funded? Wo Locationi Justification g he 2023 1131rldge llii is pectioni 11+qjpoirt i, ecoini[neilided i t0 t1he be;IMS a A ItS, Operating Budget Impact 114oii(� IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 51 Capital Cost Total Budget (all years) $1.351K Capital Cost by Year Rim $0 $401K Desigin IErngliirneeriimn� Project Total $1.351K $13S,000 00 $801K $MIK 411 Ccimftiructioin Einglineeirling Capital Cost for Budgeted Years Corist.rucLion CosL (74%� $10c),000.00 CorisuucaJori E.:ngi neer I rig (11%) $15,000DO [)�,sIgri � ngiriee6rig (1,,:,%) $20,000.00 TOTAL $135,000.00 Capital Cost FY2026 Total Desigin IE irugilropa':11,111118 1,20,000 $20,000 ("ollsbructloin 1: Ing 'i I-11 ceir 11111 g, $15,000 $15,000 C<)Irrsbrucdoiri Cost $100,000 $ioo,000 Totall $135,000 $135,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 52 Funding Sources Total Budget (all years) ProjectTotal $1.351K $1.351K Funding Sources by Year RM 'N 020 Calpitall llir>rnl irovaairrcneint:IFaairnd Funding Sources 020 Caap itaall Ilurnpairoveinient. II wind 1p ottalV $1315,000.00 Funding Sources for Budgeted Years 9 020 C;:.zapit:al Irnprovcrncnr i::und (100%)$135,0C TOTAL $135,000.00 FY2026 135,000 Total $t 15,000 $135,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 53 VIII usse iload 0v(,,irvk,,w Owinell, 11 )ell a - tin lell pYjjw "U1 11,1wil-Ir" vfllklge II :ragillwo, �� )csorilpfloin Loc,Al (wAshnicor Ihe('ook CaIIIII.Yll fighwayll Iqpaii 11�'oad flheroM for UhejjpiroQ rlwflll llae runded I nages 1113usse 11o�ad (xxxishrucHon �L)(A;Ak 11111'0aud, 1'1Ih,IIrI1,-)u1' 21, II)W 00033 Accoui,A111wri-Ilbeir 020.80 90,00,1,/04.6/9,028 11111'0ted IIffe 20yean, Slusta !III I c111) !III H Y 11101ke I h w1111 pi-o1T10b-,, pedustirlain and b1cycle ad vky and pimvidc d conii wrtIon torlark, C eg r) l'Y 704 S uree I, ( 'o ii ii I c o ii i a I) d 11 �' era D in ii r n 1:11110111ty "'rinpaid"'11111� Shr,Aegft, Goall Go�fl 3 pbjp CjualfiyVfllapinfirash udijrc: 1114kjnced and lrwwive Col-11111`1111I.A1111HY investivoint 11 11 fl'i Gran� 11Ijinded? Yrs Locadoin Justification po provide streol: Iglhflrg;uhall "alliarrd use 1pAd811I r,, w, paid or do lecolvAlludJoin jjprollod- Operating Budget Impact Annuall ii-naIntenance, of stireetlights,and sl,oired us(�r of Iybailhaa, and 5ti-retfight enei,gy cost ,, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 54 Capital Cost FY2025 Budget Total Budget (all years) Project Total $650,000 $6501K $6501K Capital Cost by Year 2025 $6,50,000DO $0 $2001K $4001K $6001K ConstrLJ4„T!101fn COSt Capital Cost for Budgeted Years 9 Const.rucLion CosL (100%� $65c),C)00.00 TOTAL $650,000-00 Capital Cost FY2025 Total coinshrur-0101111 Cost $650,000 $650,000 Totall $650,000 $650,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 55 Funding Sources FY2025 Budget $650,000 Funding Sources by Year RM Total Budget (all years) $6501K $0 $2001K $4001K $6001K 020 Calpitall llirnlpiroveiry"tint IFLAnd Funding Sources 020 Capitall Ilurnpairoveinient. 11wind Totall Project Total $6501K $6SO,,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irnprov rncni::und (100%) $6S0,0 TOTAL $650,000-00 FY2025 $650,000 $650,000 Total $650,000 $650,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 56 Operational Costs Total Budget (all years) Project Total $401K $401K Operational Costs by Year 2025 2026 2027 2028 2029 $0 $2,51K $51K $751K $MIK 1111111111 Aninuall Olpeiiafloinall Cost $.O000 $m,(. 00 00 $m,000 00 $m,000 oo $m,00w)o Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $40,000.00 TOTAL $40,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 013cii abionall Clost $0 $ 10,000 $'lo,000 $1.0,()00 $1.(),()00 $4o,000 Totall $0 $10,000 $10,000 $10,000 $10,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 57 Cenlion IIitoad Pedesbian Crossing Illhinllli tiro verneilial ts CWavow Lucadoin RNWM Omni' 'AaH Departivelifl 11 11111'0tec� IIffe CAAWHmKownnint AsApHon 2025 $100,000 hmoges 93 DoWls Lucadoin 11111'0ucL 1'1u1n1,-)u1' 21, II)W 00032 Af,crjui,A 111uirirflbor 020�80 90,00A,/04A36033 11111'0tec� IIffe 20yean, &nW.W11fly IC 01hem,11hy, 1:161psand hrnjjpndu oin omthronrincint, Caieqrvy 1111110111ty 1 CrNcall Sratogir, Goall Goall 3 pbjp 1, 1 n -1114Y W111age infraMii U( uire: AWxK md Is Ufln Ceant 11uinded? 11 j Justification I We SpRwaveds am WKWed to Nwwwse sdeLy Q pednWnN and bkydNh cRndug CenAM Had. Operating Budget Impact MANUMMe d RMUM owns MA pawmm"Wkhm A hwwobw IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 58 Inflationary Impact Silnplplychain aiic] Ihlholl, shrnrlage�� Ihaw, iu11cire,used [i,affic siginall eqijllpinrwintcosi�s, Capital Cost FY2025 Budget Total Budget (all years) Project Total $1.00,000 $1001K $1.001K Capital Cost by Year 2025 M0,000 00 $0 $2SIK $S01K $751K $1001K Capital Cost FY2025 (Ioi-VAI[ lwboin Cost $100,000 Totall $100,000 Capital Cost for Budgeted Years 111111111 ConstructJon Cost (10101%) TOTAL Total $100,000.00 $100,000.00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 59 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year RM Total Budget (all years) $1001K $0 $251K $501K 020 Calpitall irnpiroveirneint FLAnd Funding Sources 020 Capitall Iluvpiroveinient 11 wind Totall Project Total $1.001K $m0,000.00 Funding Sources for Budgeted Years 9 020 Capit.al rnprovorncnC i:::und (100%)$100,0( TOTAL $100,000.00 FY2025 $100,000 $100,000 Total $ 1 oo,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 60 Operational Costs Total Budget (all years) Project Total $81K $81K Operational Costs by Year 2025 2026 2027 2028 2029 $0 $500 $1 IK $L51K $2K 1111111111 Aninuall Olpeiiafloinall Cost $O000 $2,000.00 $2,000.00 $2,000 00 $2,000DO Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $8,000.00 TOTAL $8,000-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 013cii abionall Clost $0 $2,000 2,000 $2,000 $2,000 $8,000 Totall $0 $2,000 $2,000 $2,000 $2,000 $8,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 61 (1-1.arrldar aiur :IllI ig�htfirg Ove,irvkw kxxpjed Owiliell, 11 )ell a - tin lell pYjjw 'AaH II ;Iwirlr" Whige II ingilwo, 11 ng'inlefo iriiig Cajjpil.'a11 hillipiroveirilicid �� )CScirilpfloin 11 irv;LadlrA loll "o of 1111 :11) �;hl eediq I' it's s11biilp' Ini a jal coirrldor'n' 11 loteinflall I it ituire jjpiropeds fil ll( 11111 de: * 2025 Ilwlandl,'mad * 2026 115ius,;e1;'Wfd * 2027 Oalkton Sh-ccA 11 90 to 11 riflimi-A 142,nana U 41111 83) * 2098 (kflf 11�nmJ * 2029 11 udldAvanue Ifr.diinlhuii,�tRoadX1111.83; ur)Wcdf Road I imagles Coil I, idor sl'iroct 11 p"11 itill ig Dct'IHS 11:111lojed "'kirriber Account 11,Juinribeir 11:111lojed' Iffe Slustalinalbifil'y Clategory 11111-ini'Uy Sbr"-Ar,gdlc Go':d IN dhi,, Gir,'�nt II unded? 18 11)w 000481 001,80.90.00.1..705.(�76.001./02'r).B().90.()C�.l.."/i^'V5,`/"`(,.O1V`/' 30years 1.11.111fixtil lires use coll V;ideiralbly less eiriergy (11hain iiii icaindcscent lixbi ww�, 705 klr,-,i iirfw ling./Cifli'll-A & 3 11 irnportaint: Go,)11 3 kqp Q1j,)1!tyVH1,-q"e Il nlirasbrixlhllor: Ilk) Justification CI(aillrollrllr,at(^ d;pl'aar ,11u„1111P:il[-[4",illq)llo,„i,i-ia�q�I'Vi"i1111ap,'fC(ni-ii'li(,VV,'ai,.Il,lylli„,,,11-otiron; �l'acVVIII ,a,�,,r.,si,ii<)st:rii,f,f4uciiiuiiy�ii-tivellr ap 4.1'('.'("t:^,,11-uc�()C•,,til'i")Iro cairiicpV(llou(.11r� �,,I[(ut:y w1111 'll nlldeiitif�ird IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 62 Operating Budget Impact Aninuall eller lirkAycrant: and Inflationary Impact SUJI)IJ117ChAlrlSSUCSHld 11,oIborshoil 4ages have irff.reased flhe Cost oi Sti-ectlight nriateri.fls, Capital Cost FY2025 Budget Total Budget (all years) Project Total $587,000 $2.5861M $2.5861M Capital Cost by Year 2025 $s8'7,000 00 2026 1-384+,000,00 2027 S."so,000 oo 2028 $sS3,000 oo 2029 $GU,000.00 $0 $1501K $3001K $4!..;OIK $6001K 11111111, Construction (.:bst 40 CoinstiructJoin Engineering (91) Desigin Engineering Capital Cost Design II irigine(aIriilg coinshructI1011-11 11�'Ingllneeiriing (�oirrstr Ac� �011-11 (�ost Totall Capital Cost for Budgeted Years $7,10o,000.00 41, Construction E.:nghnccring (8%) $210,000.00 ellp Design Engineennq (11l) $276,000.00 TOTAL $2,5865000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $3/(300 $43,(oo $�)4,000 168,000 $84,(xx) $2/6,000 $50DOO $36,000 $45,()()() $4�,�,,(xx) $210,000 $500,000 $310,000 $360,000 $450,000 $480,000 $2,100,000 $587,000 $384,000 $450,000 $553,000 $612,000 $2,586,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 63 Funding Sources FY2025 Budget $587,000 Funding Sources by Year RM VMM RM Total Budget (all years) ,ml Project Total $2.5861M $g4SOr000.00 2028 °$,SS +,C:DQ)QJ.00 2029 W2,000 00 1.$0 $1501K $3001K "$4.501K $;6001K IIIIIII1 0011 Gerneir;all If'laund 4111 020 aaar,)Ra 111 Ilimlti ioverneirn�t IFund Funding Sources 001 Gninor all II ilalnd 020 C„ill:rli�t all Illnnlpirovc.Inneiir �u II::'ulradt Totall Funding Sources for Budgeted Years 9 001 Conerel I::unG'l (23%) $;S87,000.00 +411, 020 C;aaipitalIrnprove ment. i unci (771X,)$>1,999,0( TOTAL $2,586,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $58/,000 ",$58/,1:00 $,'M4,000 "TA50,000 Ja55111,0$.0 "'a612,000 "!1,999,000 587,000 $384,000 $450,000 $553,000 $612,000 `2,586,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 64 Operational Costs FY2025 Budget Total Budget (all years) Project Total $5,000 $251K Operational Costs by Year 2027 $5,00000 2026 f,5,o0ar.00 2029 $ ,00w)o $0 0L21 c ; x 1111111111 uirniruu.a4all C.)qr eii afloiru4all Cost Operational Costs for Budgeted Years 9 Annual C:Ypcmi or7al Cost (100%} $2`x,000.00 TOTAL $25,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total In lrn!aal C. 13cii aabionaal a".a.ust "$5,000 ;C 5,0oo `5,000 $5,000 $5,000 $25,000 TotaalV $5,000 $5,000 $5,000 $5„000 $5,000 $25,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 65 hire iiinilll VIII °II, ein iiii iiinIll1113a iiii iiiriil IIIIV° , Illpal liars 0v(aIrVli ,w dx puje>d:Owrllor„elr 'fl,ut,d II;Yvr^Irfr,VIIIIII;ngeII ingiuwo, 11 )ell partin lelllY'p: t�tiuno�e�lriIvut; pYllpr�:. CaIGpi l.,all II uuop:plroveIraoaaa"d :acscirlilpflloin I app,dapunaround Hire r�Iflaawr,Lrl..iluirera=qluif,tsllana7;torrnhulI,),')firs ror[iheeffeftiivearlci',0)�faoili�oft 1111cu�dlelonLiionl1br,.11ini I'ues!„'nairrdraolrsllraiCA! oil I,waillllfa�aaa..uss0lll r`iraw1lrFS m, .ai inn wa,a0 eir ara 0110. oilLkflow ^,�Orlwd uuu as r vldh o ua eii whin, t Ih e Ihta;A rum of P:Ihe Iha:+rJnil. I i L,t(AS «kII <g 111111"0�cl, 11`1V„V I'Yr br,,"' 25 I)W 00008 r,cou.ul"rO:lYrdlwrlfulaaulr 024.801 90.0U0,/0Z6IZ009 11111'0ed 11 l fe 20 yean, Category /02 1111cpod (.;w ink-olll swma`l lnarllatre 11'roile(, t,rs u'fa irfl:y rf 11lnnglsrrlrl,uinr Stirall.eg„Ile.Gxilll Clo,�ell3 paps C ijl illf yVfilllln�n,,ullnifraAiilructu re: 11 ,alh,uuwed and liroad ive a' oirnirn ulnllfylllnivest:Innn�.InrO: Is flhN g' irwn�t 11 unln0ted? i Justification I rn,rR folll o rsreru. nd t ll le of flow Aruch A r F, N e rarnll. ng; sil. airudf it g water aiiid lnroy aull oder'rrifine,. 0 hehiI u(cglI i O y of P:hc ,toinnn sewer. Operating Budget Impact deruua:r, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 66 Coina,r�U, ",III Id al")01- cosus condinuu to rise, affectinv, ronstiruction Capital Cost FY2025 Budget Total Budget (all years) Project Total $300,000 $3001K $3001K Capital Cost by Year 202S $300,00000 $0 $801K $160 K $24,OK construcfloin cost (11 CoirlStiruC60irl Einqir*eiding 41111, E)esigin Engineering Capital Cost for Budgeted Years * Const.ucLion Co= L (83%� $250,000.00 DosIgn Engirscc6ng �81X) $25,000.00 TOTAL $300,000.00 Capital Cost FY2025 Total 11)cs1gin 11 11 K,Jilccirfi q-,, $25,000 $25,000 (:oinsbru(boiri II ngIII coilinqg $25,000 $25,000 Cloinshnu hon Clos^ S',250,000 $2SO,000 Totall $300,000 $300,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 67 Funding Sources FY2025 Budget $300,000 Funding Sources by Year RM Total Budget (all years) $3001K $0 $801K $1 GO K $240K 024 IFlood (:wtral Cwr stwCflO... Funding Sources 024 11 II«~od Cointii oll CoinsLii uuction Il uind Totall Project Total $3001K $300,,000.00 Funding Sources for Budgeted Years 9 024 f:: lc)od Cont.rcfl Construction f:: und (100%) $ TOTAL $300,000-00 FY2025 $300,000 $300,000 Total $-00,000 $300,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 68 II IIutentiani IIIIC2ord Pand 6 Ove,irvk,w 16 :1W 00025 Owiliell, "Ul 11,1wil-ir" villklgeFingilincell, 11 )ell�a - tin lell 11 nf'7'inleeiriiit"' �Yjjw Cajjpi0.'a11 IIuuop iraoveIruoata"'ot. [)csc I i ptioin o ill inillpirove Ulle cal-mcfLy and ojjpeir�'Aiai i (A [Iilcdeteirdloin I �;yMeinni, I I 11101111d 6 f:NA41S lrojod1114urrll.,x-�r 16 :1W 00025 Account: 1114wirillite1r 024.80.90.00.1.703 677,005 11:111ojodIffe, 11'5 Yea 11' C jai ea "o ry 7W Soiliirtl Sevver 1:1111oll'ity 31ilnjpoirl""ull� 5� III Go'; 1I Goal 3 pbjji) Quallily Village infirash tid ure: Frjbjnced ;Ind IIalarrain4 ive ConlililliI.A1111HY inlvr.stilllollt flfl'i Glrailnt 11iAnd(xP Yes LocalJoin Justification 11 le V111116""'o of Imam lit 1i-osjw,,ct I,,; res1pai sible loii iniainLaining LI ic delpLI o of Keii I,,Iii r"'ton 11 Wshi less Center deteirlhoii ii poinchi, 11 ui ding firorn 11 kxjse 111011162 linp1 a,Aiructijre inqP11 (well-liell A eglqlWinin� 0 202"-5 11 ill lall 11 )esig'ii oFinglineurling as 2025 Coiristi,udioiii o 2021S Operating Budget Impact ;. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 69 Capital Cost FY2025 Budget Total Budget (all years) $325,000 $32511 Capital Cost by Year Project Total $3251K $325,000.00 $0 $F.K)1K $iGOIK $24010 $3200 1111111 CcmstrUCtk:)1r) COSt llI Construction Engineering Desic.Jin Englineeding Capital Cost for Budgeted Years 1111111 Cunsuuc0un Cast (86%) $280,OMOO 4111, Const.YucLicn E.ncfinr_ruring (8%) $2,1,,000.00 OR, Doslcm E.:nqinoorlrsg (6%} $20,00CX00 TOTAL $325,000.00 Capital Cost FY2025 Total lip sigin 11 �11 Piinccil ill qj $20,000 $20,000 Coirv;hrur boll -11 11 �11 q'irwciriii oP $2'000 $2'),000 Coin,41rixdoin Cost $280,000 $280,000 Totall $325,000 $325,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 70 Funding Sources FY2025 Budget $325,000 Funding Sources by Year RM Total Budget (all years) $3251K $0 $801K $Tl601K 024 IFlood Cbntrol Cons twd.110... Funding Sources 024 11::11ood Cointii oll Coinsb uuction 11uind Totall $2401K $320K Project Total $3251K $325,,000.00 Funding Sources for Budgeted Years 9 024 f:: lood Cont.rcfl Construction f:: und (100%) $ TOTAL $325,000-00 FY2025 $325,000 $325,000 Total $325,000 $325,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 71 II')etentiani IIIIC2ord Pand 6A 0v(,,irvk,,w Owiliell, 11 )ell pa - tin lol �Yjjw Callpil'all hillipiroveirilielit [)csc ir i pfloin o ill i Ulle cajpaci4,Y and opeiraLian oli [1-rde[eiritioin i �;yrleinni. I inniages 1011d 6A f:NA41S lrojod 1114urrll.,x,=r 16 :1W 00026 Acounl: 1114wirilliteir 024.80.90.00.1.703 677,005 I'll ojed IIffe 11'O Yea 11' cafegory 703 Soil iira Sevver 1:1111oll'ity 31 ilnjpoirl,,aillh 51 i G,all Goall 3 pbjji) Quallily Village infirash tid urc: Frjbjnced and lirfv"A ive Conlililli.A1111HY inlvrstirlleillQ 11" flhis Grailnt 11iAnd(xP No Justification 11 le Village of moull lit 1i-osj-xct l,,> res1poii sible loii inaiii�Lahnlng, 1.1 ic delpLI o of Keii l,,Iii i -ton 11 Wshi less Cf.�nter deteiril[kiii ii poincN, as 2026 * 2026 CoilFAinucLioin * 2026 Operating Budget Impact Noille, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 72 Inflationary Impact Hie incircase in furA coskswilll tIfrc(A, 11111ccs or tlh(s0o Capital Cost Total Budget (all years) $3251K Capital Cost by Year NXIM Project Total $3251K $0 $80 K V601K $240K $320K $325,00000 111111111, ConsLructloin Cost 411 Construction IE inglineeiding Q0 Desigin Engineering Capital Cost for Budgeted Years 1111111, Corstruction C:(,),,,t (861Xo) $280,000.00 CorsuucLion E.�nqinoorinq (8%) $25,00().00 flllp resign I ncD rRsei incg {C%) $:2o,o00.00 TOTAL $325,000.00 Capital Cost FY2026 Total L)esipirliJngiineciringi� $,20,000 $20,000 coinstructiolin 11�'Ingincci'iing, $215,000 $25,000 Coll VA11 lictiolin Cost $280,000 $280,000 Totall $325,000 $325,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 73 Funding Sources Total Budget (all years) $3251K Funding Sources by Year RM Project Total $3251K $0 V30 K $�601K $240K $320K 0 024 Flood (:wtral Cwr stwCflO... Funding Sources 024 11 1100d Colintil oll CoinsLii luction Il u1nd Totall $325,,000.00 Funding Sources for Budgeted Years 9 024 f:: lc)od Cont.rcfl Construction f:: und (100%) $ TOTAL $325,000.00 FY2026 $325,000 $325,000 Total $325,000 $325,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 74 lKensiii ngtdill Iit VIII eft Fixni IlI ane atIIC2dRceStation 0v(,,irvk,,w Owiliell, "U1 11,1wil-ir" vfllklgeFingilincell, 11 )ell a - tin lol 11 �Yjjw Cqjpil-a11 hillipiroveirilielit [)csc ir i pfloin cH lurn airicon Kerla;lrlglxml road foll to Hic 111011k�cIIq,,)ai,lllllcnU1 I inniages Keill�,lill7l,()n k,wxj ,A: I'dice SlMJ01111 �LRS`UaHs 11111'0aucl, "'1h,llrl1,-)u1' 21, II)W 00028 Accoui,A 111wri-ilbeir 020.80 90,00,1,/Ob.6/8,005 11111'0ed IIffe 20}re an, Category /05 11:111,foirfly 4 11 e%,, 1111'111�,mirtai'14 Stirall.eglic Gwll G�o,dl 3 papa Qijcfll uy V!11,n,,u Ilini9rTarspo lucture: 11 Mlaii wed and IIlroraa 4 ive CoinnifnuinHy IIinivr.,sbinenit 11F, llh!�, GraiN 11vinided? i Locationi Al Justification t 11 le imil I o Ilauora is a 11 equill elifliell ii, CA U1 ic Village's 1111 K)t perillitgrii antil op, auuns lo Kell ish lq,Ooni Il ,rmd t 11 is Vu age ced to coll Istiruct t 11 le tull il arle WIL11 ilin five years of ksuance W thf., pcirinit Operating Budget Impact 11401111e IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 75 Capital Cost Total Budget (all years) $3001K Capital Cost by Year RM Project Total $3001K $0 $f.301K $1601K $2401K 0 ConstrLJ4„T!101fn COSt Capital Cost coinshrur-0101111 Cost Totall $300,,000.00 FY2026 $300,000 $300,000 Capital Cost for Budgeted Years 9 Const.rucLion CosL (100%� TOTAL Total ■ 1,300,000.00 $300,000.00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 76 Funding Sources Total Budget (all years) $3001K Funding Sources by Year RM Project Total $3001K $0 $f.301K $1601K $2401K 0 020 Calpitall llir>rnl iroveirnint: IFLAnd Funding Sources 020 Cap itall Ilurnpairoveinient. 11 wind Totall $300,,000.00 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovorncnC i:: und (100%) $300,0 TOTAL $300,000-00 FY2026 $300,000 $300,000 Total $300,000 $300,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 77 I IIIMVIII' )an,4u4 Ore6lk. anIkStablllzafian Ov(,,irvk,w kx pjer dOwiliell, I 11'awl-ir" Village Fingilico, 11 )ell pa - tin lell 1 11 lypo Callpitall hillipiroveirilicid [)csc I i I SLIaLAI72LIOI'I,lA Sh-Cainnl ('11rook Lo thic Laindol reiinlilve i1riva'dw plairits, and tui I i NA41S lrojed 1114urriber 16 :1W 0001, 6 Accounl11"Ilwirillbeir 024.80.90.00.0.702 677,001, 11:11lojed II ife, 20 year us C a er "o l'Y 702 11:1oorl Caillrolairld I'elated Ifprojedn 1:1111oll'ity 2 Very rinpai Oili4 5ti Goall Goall 3 iblp Quallily Village infirash tid ure: ItaaIlalncedan<dllplrrrraa ive Conlililli.A1111HY inlvr.sblllollu IN flfli Gil 11:�ljnld(xi? I'M Justification lice 11,1( 1Dul lald cira..dk 11 khrilk St'abill."zition Repairil. rornp1(Ax.,.d iii 112022 (AW111-wd recnlllilllcii idations to lgir atect t1l le sill"caiiii p -H.y iii ic 111i ide: 111 vegetation, roviovall Sill-ealin lball-1111" giradill iig * Stone tw� pil otection * Illative veg,(' I.a Lion iii ,A all Ila u laii i a 5 - u ( 9 u all �u t a 11, 1 i 11 i i a o il 11 lispoffoll 11 all id ion:; Wr.re divided Iii of o,,eveii o (7? readhcs Sill gle projed " all'o 11 [oo 11 le ell Wire 11 eadl les And Work car Ibex accoll-111PHS11 led rin a yeItirly IIlwsls in 0I le i-nost ai iticall * 2025/2026� 11,1riniovall of well, Oca�.(,d 111 urdid all III] Kell Sill 11p,t,Dili M; sPmaii n bainilk skabilizat ion, * 202 112028tiSerflinnunt ronnovall 11 �irnii H wood ddeii d ioii ii ba:Jin (wildeiriling, of flireek S(AlUll of 11 'udld� IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 78 Operating Budget Impact Nolle. Capital Cost FY2025 Budget Total Budget (all years) Project Total $60,000 $2.21.51M $ 2.215 IM Capital Cost by Year 2025 $60,000 00 2026 $330,00000 2027 $lso'00000 202 350,000 00 2029 $3125,000 00 $0 $4001K $8001K $� 21M 1111��11111 Consltructloin Cost 41 Constructloin Englineeirling Design IEnglineoning Capital Cost for Budgeted Years 1111111111 ConstructJon Cost (791%) $1,750,000.00 4111 Corst.ruc6on Engineering (91X,) $205,000.00 nesIgn I ngineei ing) (01M) X,260,000.00 TOTAL $2,215,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Design 11 J1 lgi1r)(AI'llIg $260,000 Coil 0:1FIActiolin 11:1111gi'll le(111,111111?1, $1.50,000 $25,000 $205,000 ('10111stirluctloin Clost $1,:)(Jo,8"Yclo $2fA000 Total) $60,000 $330,000 $550,0001,350,000 $325,000 $2,215,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 79 Funding Sources FY2026 FY2025 Budget Total Budget (all years) Project Total $60,000 $2.21.51M $ 2.215 IM Funding Sources by Year $330,000 2025 51,350,000 $60,000 00 2026 $60,000 $330,000 $150,000 $1,350,000 $330,,000 00 2027 $ ISO,(= 00 2028 $TI,3SO,000 00 2029 $325,000DO $0 $4001K $8001K $C 211vT 11111111111 024, IFllood Control Construcflo Funding Sources 024 11 Ilood ointii oll CoinsLii uction 11 uind Toulli C Funding Sources for Budgeted Years 9 024 f:: lc)od Cont.rcfl Construction f:: und (100%) $ TOTAL $2,215,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $60,000 $330,000 $150,000 51,350,000 1325,000 $2,215,000 $60,000 $330,000 $150,000 $1,350,000 $325,000 $2,215,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 80 IIIMdIasIII eado ws IIII 'adl4c, lllridge Ov(,,irvk,w 16 II)W 00036 11"'equord OvIniell, I Lawirlr', `Jo111l age II :rrgillwr„rll' 11 )ell aa - tin lell 11 �Yjjw Callpitall II illipiroveirilicid [)csc I i I calMsildionora 1131-idgeovor "Ibil LhlwcM, IL 11""llwayarld dic Unfloinlaclk 11�ailiroad hr�xlc;� * 2022. 11 111 Ime 1, II::iv.,lineeiriii ig 1'101IT111PIeted * 2024 &, 202,"i�p: 1111wv,e 2 111 niglilieerliliq Aclas/Mcadovvs Illaarlk 1110de"U'lall ll Biridge I ktdls 11111-0led Nuirdber 16 II)W 00036 Accw'A 111wrnbeir 020.80 90,00l,/OltA/9D02/091 11 Life 30yeai[<, Sus t a II 11 1 a lb11 11 fl,y 11 1, rop�� jjlr[Opillult !I IInada^scJ Lir I impoiN at loil, theildby, reduding rutoifflolb !III e 1:I-f1pu„ aInd ill inipwt on Olhfill-0111-1-101 u:. Clategory 705 S, GuU 11,11-ioll'ity 2 Very inniporLank shrape g,II Goa 111 ('paaall 3 pfrjp Qualli(y Vlllap, Ilonpra,,hi tfl,J urea 111allanced and 111iroadive GiiiniiinuinHy lllrov2u,gomiaAfl Is t] lis Gir all it 11uii ided? Yes Justification Locatioin p 11 le bil idger WI1111 allllow salle pfAestil ill-1/bilke acce", aci-05„ tl le ir,dlii oad bi acks and Noirthrm,.,,,t 11 lighway, withi 11 Ill lace 11 conrillpleted lin 2022, t1l ra Village alplalledfai in 20231, ithe Villagre received an addlUoinall $2,()X1,824 fa -a rin llhi:,Sp Ill Shared 111irogirairri, Aild lin S(I'loolIDIM irld -57, Sq,- hooll 11 1214 aii d Air 11 !1 ilf"Lon Ilk igll it S hava oxjpre^ised "UpIpy'-rid fm flhlejpiroccl, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 81 Operating Budget Impact 11Colut ill wall 1111 INd inalintonall ce'. Capital Cost Total Budget (all years) Project Total $6.9781M $6.9781M Capital Cost by Year 2026 $6,978,30100 $0 $2 lA $41M $6110 111111111 constructlon Cost 4�W� Canstiructlon Einglineeirling Capital Cost FY2026 Ccu insbructlioiri II ilglinecilinlqg $634,391, CoirvAiruclJoill Cbst $6,34,3,910 Totall $6,978,301 Capital Cost for Budgeted Years 111111111 ConstrucJon Cost (91'/',,) $6,343,910.00 4111 Corst.ruc6on E.�ngineering (91X,) 'Vi34,3'.--)i.00 TOTAL $6,978,301.00 Total J;634,3,91 $6,343,910 $6,978,301 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 82 Funding Sources Total Budget (all years) $6.9781M Funding Sources by Year 2026 Project Total $6.9781M $0 $21M $41M $61M 020 Calpitall irnlpiroveiry"aint FLAnd Qj' 091 Federal Grants Funding Sources 0200 apiikill hinprovoinneii iru 11 und 091, 11::edcirall Grall Its Totall $6,978,301.00 Funding Sources for Budgeted Years 9 020 Capit.al rnprowarnomt i:::und (29%)$2,007,6 411, 091 federal Gran[s (71%) $4,970,65ZOO TOTAL $6,978,301.00 FY2026 $2,00/,649 $4,970,652 $6,978,301 Total $2,00/,649 $4,970,652 $6,978,301 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 83 Operational Costs Total Budget (all years) Project Total $1.5 IK $ 1.5 IK Operational Costs by Year 2025 2026 2027 2028 2029 $0 $L21K $2 41K $3�61K $4 81K 1111111111 Aninuall Olpeiiafloinall Cost $O000 $.0000 $5,000.00 $5,000 00 $5,00w)o Operational Costs for Budgeted Years 9 Am-WDI C)pcmir.Joral C.,ost (100%� $1S,000.00 TOTAL $15,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Closn $0 $0 $5,000 $5,000 $5,000 $1 5,000 Totall $0 $0 $5,000 $5,000 $5,000 $15,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 84 1>ralhnage cNavow RNMM Omar l DepartivelinI 11 nginlef�iriiig "w CAAWHmKownnid DwAption Car�brii(1,lan oldraiinagre ill n1proverneills to allevlall,n nei�,,Ihlborllood floodling ploblenns. I mages Rain Gardo i INAHS Af,counl111wrinbeir IiQyUlffe &nWMwily category Awity Wahyc Goall k IN G.9 BMW? 11 II1W 00021 0240�90.00 O./02,6//DO� 30years hads; NaMs and wakr Awrlbild nalk m,AdWW A am An Mdm aHmAng hKaWmmin 11he M,ornnr&nmeii systeilrii d L Ill! rig heavy Ir.aiul I evi Ba,. 702 II:1ood Cord Ircrll and cd lirojecl.^> �Ahhmmww,n: (Soall 3 I61P-Qwallty V11111age 11111firabriuch re111,allaii cednd Iii oa(Alve (.oini-nii inilty invesbirnonl. l Justification I he VHKWP Doxd aplgcmid T"w oMn* W m%ms thwnK aNKAW, M& xqw, omms molAu%"M S QPM) pi kWhin Chn wdy 11 am am 4 AWs BUM HA, Nowlbk IMNC Owl wM Sall lbw Rw Ke w=Whirlol approxinnat61y3 411ocalJoioar 1perrnir. Operating Budget Impact Nome IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 85 Capital Cost FY2025 Budget Total Budget (all years) $1.50,000 $3501K Capital Cost by Year 2025 2026 2027 2028 2029 $0 $401K $801K $12DIK 11111111111 ConrAructlion Cost Project Total $3501K $1150,000.00 $S0,000.00 $S0,000.00 $S0,000 00 $5o,o0w)o Capital Cost for Budgeted Years 9 Const.rucLion CosL (100%� $350,000.00 TOTAL $350,000-00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total coinshrur-10101111 Cost $150,000 $50,000 $!;(),(xx) $50,000 $50,000 $350,000 Totall $150,000 $50,000 $50,000 $50,000 $50,000 $350,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 86 Funding Sources FY2025 Budget Total Budget (all years) $1.50,000 $3501K Funding Sources by Year 2025 2026 2027 2028 2029 $0 $401K $801K $ 201K 11111111111 024, If lood ConLrol ConsLrucflo Funding Sources 024 11 II«~od Cointii rill Coinsb uurtion Il uind Totall Project Total $3501K $1150,000no $S0,000.00 $S0,000.00 $S0,000 00 $5o,o0w)o Funding Sources for Budgeted Years 9 024 I::Ic)od Cont.rcfl Construction f::und (100%)$ TOTAL $350,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $1.5(),000 $�5o,(000 $50,000 $-50,000 $50,000 $350,000 $150,000 $50,000 $50,000 $50,000 $50,000 $350,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 87 New SidewaIIIIIIIIk. III' irrogrann 0v(,,irvk,w kxxpjes' Owiliell, )ell a - I'll][ lell I pYjjw I Lawirlr', Vf1lage II ]ngilleor II irvx},iuno�o=iriuut; Callpitall II iiiii1piroveirincid )csorilpfloin * Busse load trona Ilunipeii fall Coiiii-I, to 11 90 feast sido) * 0'aldon Shred, 11'swin 11 90 to II e)"Ing-toillDirive, (111oll th a�.Jde) * Oalktoin Si'lle(A firoirin 11 90 do � he hils!0, (soudh side) as 11 urtalfid Avoi ue firorn WI Imling Wrad to Wolf I6loact (sr"Alislide) * 11 udid Aveirue firorn Wolf III Lo lltiiveir IRoad (south sldi:�e) I Imagles New Sidewalk �1)CL,)Hs 1:111rojed "'kirril")eir Account 11,1wi-ribeir 11:111rojed, Iffe Sustalinalbilli'y Clate teary 11,11-ini'lLy Sbr,-Ar,rdlc dao al IN 1,11his Gir,,ont 11 funded? Justification 21, ll'J'W 00039 001.8 1.90.g' 0.1.705.(a 75.009 30years 11 x1pnin(fing k sy"IC1111 proll-lotes'lind 'iriodeolfbiranisIlrx irtailan. 705 Ilae I irfw ling.A. W ICILY; & G I U1P1`s/.SidMNJ11 III 3 11 irnportaint: Go,)11 3 kqp QuallityWIL.""e Ilnlirasbrixli.uilor: 111,-dani-led .-and inveArneni. I'lo Pira sa ILai ge Liad"llog oil Ilaaa afloiawlwirrsidowalls Ill hisl.alll All 111irloirityls g1l ve is to 11 ocat o ns a 11 a rip, a I, teirll all 'i til eut " foll 11 Owed Ih y Collude dOils a 11 lid t11-1 Ilocall11 cads, p he 'Pil !!oil lity un,otil lx rA/I1111 11-,a11 flk inroi5s1ii Ig I,11dewAlk segirincills rr(A�oir-,wil1111Rbllsriliriiclli.udinc aiil�)y des H 1-0 s hero u ,,, sA,ic 11 o as sc hoo 11 S, 11 aa 11- 11-11 u 11111 Iw, sl-qjpjpli I rid I es La Il Ira 1111 ss. Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 88 11,101111(", Capital Cost FY2025 Budget $330,000 Capital Cost by Year 2025 2026 2027 2028 om Total Budget (all years) $1.851M Project Total 1.85 IM $0 $1001K $200K $3001K $4,001K 1111111111 Con!Arkicfloin Cost $330,,000 00 $3,'S0,000 00 $370,000 00 $390,000 00 $400,000 00 Capital Cost for Budgeted Years 0 Const.rucLion (100%$1,85c),Ooo.00 TOTAL $1,850,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total ("Onsbrucdoill Cost $13,30,000 $35o,000 $370,000 $390,000 $410,000 $1,850,000 Totall $330,000 $350,000 $370,000 $390,000 $410,000 $1,850,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 89 Funding Sources FY2025 Budget $330,000 Funding Sources by Year 2025 2026 mom 2028 2029 Total Budget (all years) $1.851M Project Total 1.851 m II $0 $1001K ��.�200K $3001K $4,001K 1111111111 0011 Geneiiall IFMuind $330,000 00 $3S4.5,,000 00 $:3'70,0041.00 $.:"90,000 00 $40 ,014)41.4141 Funding Sources for Budgeted Years 9 001 Coneral �::urwl (K)0%) $1,85o,000.00 TOTAL $1,850,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 001. Gencirall 11 und $330,000 $350,000 $370,000 $390,000 $410,000 $1,850,000 Totall $330,000 $350,000 $370,000 $390,000 $4,10,000 $1,850,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 90 Northwest 1°°°�Iwy & IRoad Gateway cNavow RNWM Omni' Nlatl Departivelifl 11 "w CAAWHmKowniod AsApHon De�,igilandl ('an';t1i'llurAlon W a gahway Lo WdUde OaWo milpmake; cksk Men, gfTxqwmdmbk pwWng ki and SUNYMPP at HKAndismAn of Nhill-iWest 11 Nwy& CO3 lilt rall M Wages DOWHS 11111'0� cl, 25 II)W 00012 Af,coui,A 111unrilbor 049 80 90,00A,/04A41DO1, 11111'0' ecIffe havrdlffeireiia� pn*nolre. category 704 1:1111oll'ity 2 Very II Irl npoii lan� 5trategdc Goall Goall 3 pbjjp Qualfiy Village infirash tichire: Frdailced and 1111avxive Coll"11111i'llU111HY invesbrinolln, 11 " flhii Gil 11:�lAnd(xP I'M Lucadoini Justification H a pYMdwlH ad ame% diamMuNU" uM awn a W Mx"W= a W WO won Ww"Mmin, Operating Budget Impact 14 PWMW Wkywe WW&I Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 91 Lal")011- a Ind rrakirlall coms, vaii arrect r oiistirucuoin ii-,fcis Capital Cost FY2025 BudgetTotal Budget (all years) Project Total $1,300,000 $1.31M $1.31M Capital Cost by Year 2025 $1,300,000 00 $0 1111ill' ConsLructloin Cost Capital Cost Desigin 11.1ingineell-fing (.,oinsb-130:110111 Cost Totall $4001K $8001K $� 21M ON' IDesiigin Einglineeiring Capital Cost for Budgeted Years 0 Const.rucLion Co -,,L (85%� $1,loo,000.00 4W Design E:ngneenng (15%) $200,C)MO4: TOTAL $1,300,000.00 FY2025 Total $200,000 $200,000 $1,100,000 $1,100,000 $1,300,000 $1,300,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 92 Funding Sources FY2025 Budget $1,300,000 Funding Sources by Year RM Total Budget (all years) $1.31M $0 $4001K 049 11"yiroslpect mafin nil Fund Funding Sources 049 11irospeir, t Mahn i1111: lFund Totall $8001K $1121M Project Total $1.311A $�,300,,000.00 Funding Sources for Budgeted Years 9 049 Prospect. Nlafln 11 l ::: i::und (100%)$1,300,000 TOTAL $1,300,000-00 FY2025 Total ,$1,300,000 $1,3oo,000 $1,300,000 $1,'W0,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 93 Operational Costs Total Budget (all years) Project Total 1.I 1.I Operational Costs by Year 2025 2026 2027 2028 2029 $0 $L21K �_ /oIK $3.61K "'i4,.8IK 1111111111 uirniruu.a4all C.)qr eii afloiru4all Cost `1.O000 $.0000 $5,000 00 Operational Costs for Budgeted Years 9 4nraraal C:YIpcmi orral Cost (100%} $1`x,000.00 TOTAL $15,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total In lrnuaal C. a3cii aabionaal a".a.ust ",fru,;) $0 ` 5,000 $5,000 $ 5,000 oaf `5,000 TotaalV 0 $0 $5,000 $5„000 $5,000 $15,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 94 IIIII)arll VIII otPIII IbIllic W()iiuHks IIIIIIII ad1k.11111,ot 0v(,,irvk,w kxxpja»d Owiliell, 'AaH II ;Iwirlr', Vilhige Fingilwo, 11 )ell pa - tin lell 11 lypo Cajjpil.,a11 II illipiroveirilicid [)csc ir i pfloin Fl,epnii, Ohon ojrhandIra lublicware rlk�� "ack ILot. I i 11,1111blil:: woilk^, Back I'M [)(AS Ak 11111'0a cl, 22 II)W 000/9 Accoui,A111wri-ilbeir 020.80 90,00, 1, /06.64 9,020 11111med Life 20yean, Category /06 W 11)idblic 1131ijildlings 1:111,fori9y 3 Il ilnijpoirl,uinn Stirall.eglic Gxill Clo,dl 3 lop Qij�flfiy Vl11,n,,u llnilrTa,,pu ll cture: 111 alh,auwed and Ilalroad ive CoirnirnuinHy inivesbilnenill. Is flhN Girwnt 11 �ijiiided? i Justification I'lavelinciA his Ibegu.un, to hill aild is ill 11 Iruecd or resuiffach ig Ila,a oire del'u'lorat lail o progircssc', (o as poillIll w1l icire coilillpleterecoii istiruction is i1equiii(A Operating Budget Impact 11,101111e, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 95 Capital Cost Total Budget (all years) $3001K Capital Cost by Year RM Project Total $3001K $0 $f.301K $1601K $2401K 0 ConstrLJ4„T!101fn COSt Capital Cost coinshrur-0101111 Cost Totall $300,,000.00 FY2026 $300,000 $1300,000 Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� TOTAL Total ■ $300,000.00 $300,000.00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 96 Funding Sources Total Budget (all years) $3001K Funding Sources by Year RM Project Total $3001K $0 $f.301K $1601K $2401K 'N 020 Caalraitalllllirnl iroverneint:IFaairnd Funding Sources 020 Caap itaall Ilurnpairoveinient. II wind Tota ll $3 00,,000.00 Funding Sources for Budgeted Years 9 020 C;:apit:al Irnpro rnomt i::und (100%)$300,0 TOTAL $300,000.00 FY2026 `oa 300,G: 00 Total $300,000 $300,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 97 IIIII)ar VIII otPiuIblllic W()uuHks I of 0v1,,irvk,w Owiliell, "U1 11,1wil-ir" villklgeFingilincell, 11 )ell aa - tin lell 1 11 lypo Cajjpil.,a11 II illipiroveirilicid [)csc I i I Fl,epnii, Oileojrhand Aflblicwarl<I� Front Loll - I I 1lj1h1l1:: Wall lk^, 11:�11-011-10Lot [)(AS Ak 11111'0a cl, 1'1IhAlII1,)u1' 22 II)W 00080 Accoui,A 111wriAlbeir 020.80 90,00, 1, /06.64 9,020 11111'0aed Life 20yean, Category /06 Ao 11)idblic 1131ijildlings 1:111,forily 3 lllnngparrlrlAin0 Stirall.eglic Gxill Clo,dl 3 lop Qij�flfiy Vl11,n,,u llniprTa,,Ilii Acture: 11 lakiii wed andliroad ive CoirnirnuinHy inivesbilnenill. Is flhN Girwnt 11 �ijiiided? III Justification 11 ,a - Id I ij, at Ursa elinivil l( III As bci,a All I (r) FTflll xi iiaI is An riecd app rusurf a Jii i,,, bclore dctcilirji,rAlon progilesse" if,) a 'johnit VV - 10 ` C CoiriniplIkAu recai isill-1 A (Airm Ii i ed, Operating Budget Impact 11401111(". IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 98 Capital Cost Total Budget (all years) $1.001K Capital Cost by Year Project Total $1.001K $0 $2SIK $501K $751K $1001K 0 ConstrLJ4„T!101fn COSt Capital Cost CoirrAirucboin Cost Toulli $i00,000.00 FY2028 $100,000 $100,000 Capital Cost for Budgeted Years 9 Const.ruc6on CosL (100%) TOTAL Total sloo,000 $100,000 $10c),000.00 $100,000.00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 99 Funding Sources Total Budget (all years) ..A. IK Funding Sources by Year Project Total 1.IK $m 0,000.00 Cl00.00 $0 $2SIK $501K $751K $1001K 'N 020 Caalraitalllllirnl iroverneint:IFaairnd Funding Sources 020 Caap itaall Ilurnp iroveinient. II wind Tota ll Funding Sources for Budgeted Years 9 020 C;:apit:al Irnpro rnomt i::und (100%)$100,0( TOTAL $100,000.00 FY2028 ■ Total $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 100 VIII �)�hase VIII l Illlllll Eke Ov(,,irv�icw 11'1,eqiue�d Owilell, 11 )ell Ia - tin lell AYjjw I II awirk, W111ageFingilwo, Callpitall IIilillpiroveirillcifl [)csc I i I CarAxii(Alon okl-wired ij:;c ilia this, lighUing -Ind a I;lipi I,; aII (Ing(,an, idors Uhak rineel. L11 lie goalk (If theAllage Bflke 11:111 all 11, :NkeirOJAI pi'lorily corrldoi-e hllcliAeKe1llSh1l'r1't01ll wIoad, Ceill'i"111 Zoad, IBus"e 11aoad, Zand toad, x1lidwolf IW,A2Ad. * 2025 Keirlshington llkeasal I Win -ling Il klilh 11 In to raflil oad til acks (SMe IhQwfl,es to SCII-looll GilanlQ * 2021, Clonball "oad 1111 ase 1111 inglineeilfling $200,000 as 2026 Ka ^nw, 1111,, tx)ii ii III nad a l. li 11 ira�u,ad bra clks (1111 )0 Cansl.iru(Aloii 11 $294,500 * 2026) Algoiniquilin 11wnadFllhase 111111 ( , on,;lrurl:lon $2,303,872 * 2026 ",use s:Zoad 11111hase 1111 ingiii CN, -n Iii g $200,000 * 2026 ("criti-all :,1,oad 11111hase 1111 $300,000 as 202/ II udid Awinuu IIA 1haw, 1111 ngliv;eii uohip, $200,000 * 2027�Wad llha-,e 111111,11 lglrlrurmJrlg $300,000 * 2027 eilball Zoad 11 aild Acquisitioin $900,000 * 2028 MAU Road 11111 1111 ngliriecirlirig $200,000 * 2028 $3oo,000 * 2028 $500,000 ru 2028 $2,500000 2029 $2Q(),0()O 2029 WoU r,oad 11111 ase 1111 11::irighi eeirfii ig, $300,000 2029 Il Adl lid Aveii lue 11 aii I(] Acq u al Ulaf I $M)0,000 n 21029 $2,500,000 im a F ,f S �i Detaidls Q:II""Iluurnber 18 ll'W 00044 Accc,xunt Nuirl-lbeir (�2(1,80,90,0(),l,,/05,6/9,02//091, uauJcxep IIAfe 20 ycairs sustahnab!114Y Proinnotesinij110 category 11111 ioll �ty 2 Ve i, y 111 n 1po i, ta 'It Si; ratc,"gic Goal G o a 113 Q o I Qu a 11 11 ty V! 11 a go 11111 f ra 5 t ir IA Ct u re 11:: 11 a ii ii ced ,-, i i -i c V III' ii o (A 1 ve Co ri-I ii i -I u ii I I"I ty 1111 Ive 5 t ii I I r-, ii It 11,; tlfl^, Graint 11:uirlded? yeas IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 101 Justification f he Village 113ilke Plan Ileas a goall of cimaiiing and devr.1k) I,-)! iru,, a safc�, colinilo I' lalblo a rid Ilbiicyclle kieindly elivi I[ oll I i I II i'M rtIncagjragcs x"olp1le ofaIll 'iges fo use Ibiicyclles foil eveii yd ay ul airlsllpoirfallluin. f lh e lincore asQd accwas La safe Ihailk, i wflll Ile^rad o Iheaall4lhloir Ilfife skylQs, f-n1)i-owd air arid wakeii qualfl y and as i ei, lerh,,y erfwlerlL uransr)oii talfon wsl,eirri. Operating Budget Impact hirisil'allailiolin Capital Cost FY2025 Budget Total Budget (all years) Project Total FY2028 $200,000 Capital Cost by Year $1,000,000 2025 $64,0500 00 2026 $3,098,372 00 2027 $2,250,000 $640,500 $3,098,372 $1,000,000 $,000,0(w $,000,00(:xoo ROM $0 $11M 0 Construction Cost Sj, I::)esiqin ErGlinee6inq Capital Cost Design Lingfinceiring Construr-Coll 11 ['11 ngf'iceilrfillg Coll lstiructloi-i (.;ost Totall $3,,500,,000 00 $:T"500,000.00 $2M $3 im 411 ConsUruction Einglineeifli-x] Capital Cost for Budgeted Years construction Cel-(62%) $'/,286, 122.00 (.onstrucdon Engincoring (6%) 'J752,550.00 Oillfi ")esign I rigineering (3?1%) $3,700,000.00 TOTAL $11,738,872.00 FY2025 FY2026 FY2027 FY2028 $200,000 $500,000 $1,000,000 $1,000,000 $40,100 $212,450 $250,000 $400,400 $2,385,922 $2,250,000 $640,500 $3,098,372 $1,000,000 $,000,0(w FY2029 Total $1,000,000 $31'/00,000 $250,000 $752,550 $2,250,000 7,286,322 $3,500,000 $11,7,:W,872 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 102 Funding Sources FY2025 Budget $640,500 Funding Sources by Year 2025 Total Budget (all years) $ 1. 1.7 3 9 IM Project Total $ 1.1C3 9 11\4 $640,500.00 2026 $3,098,3172.00 2027 $ ,000,000.00 2028 . �,,Sowxx) oo 2029 $:3,!w,000 00 $0 $11M $2M $31M 111111111 020 Calpitall Illrmmlpra veirneint IFUind 411p Cnl IFederal Gifairas Funding Sources for Budgeted Years 9 020 Capit.al IrnF rowarnomt i::und (80%)�'[,9,401,,E 411, 091 Federal Grant,, (20%) $2,336,99000 TOTAL $11,738,872.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 020 Caplikill hinpiroveinneii u' 1 und $,14 1, I'm, $960,//4 $ 1,000,000 $3,500,000 It, 9,4 0 1, P, 8, 2 091, 11::edcirall Grall Its $199,392 $2,137,598 $2,336,990 Totall $640,500 $3,098,372 $1,000,000 $3,500,000 $3,500,000 $11,738,872 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 103 Operational Costs Total Budget (all years) Project Total $81K $81K Operational Costs by Year 2025 2026 2027 2028 2029 $0 $500 $1 IK $L51K $2K 1111111111 Aninuall Olpeiiafloinall Cost $D000 $2,,000.00 $2,000.00 $2,00000 $2,000DO Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $8,000.00 TOTAL $8,000-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Closn $0 $2,000 2,000 $2,000 $2,000 $8,000 Totall $0 $2,000 $2,000 $2,000 $2,000 $8,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 104 IIIIC Averifue Ov(,,irvlicw fecpj('°d Owiliell, 11 )ell a - tin lell fy1po I )csorilpfloin jx,oini 11,611b, lublicWark", Callpitall hilinpiroveirinclit Llhededre roirolAdooii scalfing, 41 lhc'Alnlaiiqeir uniollithis. More ,)edlesbian airld I arAhlity drevintown wilt 1111 t he addi'lon (A Ir "lee I l,aurainlh and s[loprAng. Ile, oad to devela p a plan Llh at consldvi-., outdcarse, a thlp,,, pede,50 !I a I I(, I hilnu-,,Vcl-flde Li-aw 1 & parldine ja ries, Hie fill,A rAqjpwflll lx„ I,o jjx;iifcjnnu a 111haw 11 Study that evaluates, -'eveirall ojptloiia, and todetell I n !Ili Ile the iii-elenred altarinative thatwilll Tiove I.(,) &,,Igni and cowbrudJoin. o 202'5 Phase 11 nkijrly I fnagles []���He..Existjng Dctaik 11111-0led Nuirdber 2S II)W 00009 Accw'A111wrnbeir 049.80 90.00; 1,/OnIA4 1 DOI, 110 IIffe 20yem , Category 104 Shred Coll r;Urudioll Y and 11"ecoll �etiructlan 11,11-fol-ky 2 Very IIIIIrllltaoirl.allnll4 Stildilegic C(")all Griall 3 ktIp 06 AILyVf11,A6e Ill ifra",,h uctllire: 113,flanced and 11r1adive Cqjifn inn u in !I ty inve-Anneinil. IN this Graint II Ilauoaded? "ka Justification fo provide a ausni less firiondly orivii-oii nlwirO 11.1hat alm onhall lc('an safef Y foll, 0 11 w girowdl o of jja!dcs0 riaii ii aind hikp activdLy hi o H e downLovvii I. Operating Budget Impact yalintell lal Ic(? of thc rra,,adway, fighthilig, all Id an(hr n1phnig, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 105 Inflationary Impact ,aboraind niia0cirifll (al risc, Capital Cost FY2025 Budget Total Budget (all years) Project Total $1.25,000 $12 5 IK $1.251K Capital Cost by Year 2025 $US,000 00 $() $30K $601K $901K $�201K 111111111 Design Engineering Capital Cost for Budgeted Years 111111111 [..Eeslgn E.ngirscc6ng $C,,,000.00 TOTAL $125,000.00 Capital Cost FY2025 Total 11)csigin 11urs giincuiriing $1,25,000 $125,000 Totall $125,000 $125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 106 Funding Sources FY2025 Budget $1.25,000 Funding Sources by Year RM Total Budget (all years) $12 5 IK $0 $30 K $(:'i IK 049 11�iroslpect Main nil Fund Funding Sources 049 11irospeir, t Mahn i 1111IFund Totall $901K $�201K Project Total $1.251K V25,000.00 Funding Sources for Budgeted Years 9 049 Prospect. Nlafln 11 If::: I::und (100%)$12S,000 0 TOTAL $125,000-00 FY2025 Total $1.25,000 $1.25,000 $125,000 $125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 107 Operational Costs Total Budget (all years) Project Total $21K $21K Operational Costs by Year 2025 2026 2027 2028 2029 $0 $500 $1 IK $L51K $2K 1111111111 Aninuall Olpeiiafloinall Cost $D000 $D000 $D000 $.0000 $2,000DO Operational Costs for Budgeted Years 9 Annual Operadonal Cost (100%� $2,000.00 TOTAL $2,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 0113cii atlionall Cost $0 $0 $0 $0 $2,000 $2,000 Totall $0 $0 $0 $0 $2,000 $2,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 108 VIII . hurl Illllllllll;Illlliiiu° 11111 iiurm lull . iiu� �iiiliiuriiul iiirl Road Ibmtersectican cNavow 16 1W 00030 RNWM Omwir IAaH Departinnonl 11 anf,7,iurmef161111g; 50,1 eAirs Category AsApHon I rinprove braffic rlmA' dhir(xigr1h Lk WAVe inWraYLIbm FbIhowhg crnrNhUon oH%w; It 2022 U 2Mb o 207 hrvfllagr�. W1111 he 11 (x:11dined 0 bm"M Ow howl WWI Oran I on H 11 nghnevidin, KI,W xquNHonq and caiarnmdoiwnghwuIng grants h duo dun 0 1 XA MM hward Mv mmy, M cm, M UUM nm V111 11 age W111111 oinll Y 11 o arespoinisH Ale foir q 11ue rxahslhar c Wages AndI InhumtgwNhoniii hnteicctloin Dodls 1111iroje6;;G"Jurnber 16 1W 00030 Auount 021OR9010,1,,/04,6 /3,009/001-80,90,00,(1 /04,6 /100 V09 1, Numho, 11111-0ret II.ffe 50,1 eAirs Category /04 SUE CwAmWw a,ud lecoii Ysnrurtk)n jj,jjlrjojj,Il Y 1 CrItIcall stiraVegic Goall coall 3, �011,-j Qualn,y Allage Intl 35bructure: Balainpi,ed and 11111 IN dhis Crainl. 11 uildiyj? Yes Justification Ilmse E 2018 1022 (GAQuk) F*msQW!ksQn 20222D25OhWgdedandawaQA) t $685MOO SfPgrant 2. $05POO Voagehv& 1111hase III III: 164 g1h CA Way Accp,i bY don t $""Woomwit A $1b85400 RYKrAdNumUonwygmn1 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 109 $4!nom V11111"IFeh,l1lds 11:111-iiase III 111111:� C ontrud larl all id CoirArucl mala 'nFi ineeiri ing 2026/2027 1,$2,/00,(H)0 51111grai0, 2$5,31,5,000 3,$3,390,600 VllligcfunaN' Operating Budget Impact "lair" Capital Cost FY2025 Budget $1,235,000 Capital Cost by Year Total Budget (all years) Project Total $12.6411M $12.6411M 2025 $1,235,000DO 2026 $11,4-05,600 00 $0 $31M 111111111 Construction Cost C1, Desigin Engineering Capital Cost Desgiri 11Irqdirlccii ing Conshrl wholl 11 II glineelding, Conshructioll 11 Cost 1-0tall $61A $9 A 41' Constiructicin Engineering FY2025 $1,235,000 $1,235,000 Capital Cost for Budgeted Years 11111III (,.onstrucLion (82%) $10,36E.3,700.00 4W ("onstl,uction E.ngmcticnng (Sw") 1,6756,7 J 4/1//, DQ.,,Ign Er�--Jincornj (101%) $1,2.35,000.00 TOTAL $12,640,600.00 FY2026 $1,0316,900 $10,3368,700 $11,405,600 Total $1,235,000 $1,036,900 $10,3368,700 $12,640,600 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 110 Funding Sources FY2025 Budget $1,235,000 Funding Sources by Year Total Budget (all years) Project Total $12.6411M $12.6411M 2025 $1,235,000.00 2026 $1 �,405,600 00 0 0011 Geneirall Fund 411 023Stireetllrrprovc:iriieir)t6:oir)^.a.. @J, 09a f::edeirall Grants Funding Sources for Budgeted Years 9 001 Conera I i:::urwl (2% $240,000.00 411, rnprovernenL Cansrruct.Jon und (: 4111t, 09" f ederal (..;raWs ('MIX) $9,00z"000.00 TOTAL $12,640,600.00 FundingSources FY2025 FY2026 001. Gowirall 11uind $247,000 023SU-eetIliriroipii-ov(:ii-ne.i-iifl.Coil vu�.irii.ucA.ioiii 11 uind $3,390,600 091, 11 crIlln-all Giall 01S, $9818,000 $3,111,: '000 Totall $1,235,000 $11,405,600 Total $247,000 $3,390,600 $9,003,000 $12,640,600 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 111 IIesident!4aireet IllI iglllhltfirg 0v(,,irvk,w Owiliell, 11 )ell a - tin lell pYjjw "U1 11,1wil-ir" vfllklge Fingilwo, II irvx},iuno�o=iriunP; Cajjpil.,a11 II illipiroveirilicid [)csc ir i l Miro studlA !oil lof 11 NAonl.Acill fubuire jjpirojedslixlude� U Burning Blush II ail -110 YAWCCII 11KC1111'ArigIoni t,oad a wl 1::w1ld Avenue 0Wicir ",oad hr"(Ween 11 hic,olin Shrect riirid G,611 Illuond 0 Grq�ory Si lrerA bel, ween Waic-,irnnaini Avenue and i Street (1111, 83) I imagles 7(,,sldeil9:iia11 ShredLighling, M.",)Hs 1:111rojed "'kirrilsel, Account 11,Juinribeir 11:111lojed, Iffe Clategory 11:111-ioidty "iter ateplir. Goall IN 1,11h is (Sraint II unded? 18 ll'J'W 0004 7 020,80.90.00.1.705.6 76.008 30 Years 705 & ("ball 3 p olp- 0113all 11 ty Vill age 11 In I ra, brijda I I, e: 11 1,daii oxl a nd 11 1i-wvAfvr (: oinn irnijnllty 11 niver,hrnen l. l Justification p 11 le rwm 11 � �, tl i oil n O hir, 20 1A 0 millivull lil ty Su I'VPY 11 tmJ t 11 at respoii ldeii s 11 d""I'l 11-ji1a111 Y oll 11 1 Jall 11igll it 111 g. 11 ased ai o t11 w sli i, vey ii espoii isc, resideii ii p 41 sti ed hZ11 its i s a pii 0ii lty go�fll of Ll ic 2021 Strategic 1:111a ri, Operating Budget Impact Airlirlu;jll cost air eneirgy aii-K.1 rilaii-itenairice, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 112 Inflationary Impact S11311rul6bll;ra'Ihalin Ni ,ixc, and Ila l.rrur sllhoirl.ag wr; haw, rx,l oga^,r•d dlw col,oin d lred lllghl. in a'teiriall=s. Capital Cost FY2025 Budget Total Budget (all years) Project Total $300,000 1 1 Capital Cost by Year 202S $300,000 00 2026 $350,000 00 2027 $4F50,000.00 2428 $4,50,000 00 2029 °g450„000.00 0 V201K $2401K $'5601K 1111��11111 Cr nsl:ruua:tloirT 6:'.`ost 41 Con,sstru ctlloin If.:,u glineeirfiing dUl%a I:::resig;gn IEn gill Bening Capital Cost for Budgeted Years lllllllo C:onstructJon Cost (78) $1,550,000.00 4111 < uri=t:rua'Ciarn I:::Irrginaharing (IAF%) `u2I0,000.00 fpp nest gn I n girtieei inc. (9%) ' lf,.0,C)OO.00 TOTAL $2,000,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total )Csi �1n Ell lginl(A`:Ir11V g � � $1,3�4"D>a„)a„ 0 ar 30,g„;Pg„;P0 $40,0000 $40,C000 $40,0000 $180,0000 Coil abg:Ir'luctiolin ll'utlg!glil lead-il ig $40,000 $50,000 $60,000 `l,60,000 $60,000 0 $270,000 ('101119stirl,ac l loo n g""sust $230,000 $2/0,000 Iz'3150,000 $ .a"”: 0,fgu. 0 "E+, fg, PO,Q.gQ. 0 $1,5!)0,000 TotalV$300,000 $350,000 $4,90,000 $450,000 $450,000 $2,000,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 113 Funding Sources FY2025 Budget $300,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $21M $0 $ 201K �2401K $3601K 1111111111 020 Cal halal IlirnlC.rircveirmo �,int If und: Funding Sources 020 Cap itall hirnpiroveinient 11wind Tota ll Project Total $21M $300,,000 00 $3SO,,000 00 $4SO,00000 $4S0,000 00 $450,000DO Funding Sources for Budgeted Years 9 020 Capit.al Irnprowarnomt i::und (100%)$2,000 TOTAL $2,000,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $'I'loo,6boo $350,000 $450,0()0 $450,000 $450,000 $2,000,000 $300,000 $350,000 $450,000 $4,50,000 $450,000 $2,000,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 114 Operational Costs FY2025 Budget Total Budget (all years) Project Total $5,000 $251K Operational Costs by Year 2027 $5,000.00 2026 f,5,o0ar.00 2029 $ ,00w)o $0 0L21 c ; x 1111111111 uirniruu.a4all C.)qr eii afloiru4all Cost Operational Costs for Budgeted Years 9 4nraraal C:Ypcmi or7al Cost (100%} $2`x,000.00 TOTAL $25,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total In lrnuaal C. 13ciil aabi Calnaal a".a.ust $5r000 $5,0oo ` 5,000 $5,000 $5,000 $25,000 TotaalV $5,000 $5,000 $5,000 $5,000 $5,000 $25,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 115 SIll loeinbed IIIitoad IIIIesixrfadng 0v(,,irvk,w Owiliell, "U1 11,1wil-ir" vfllageFingilincell, 11 )ell aa - tin lell 11 �Yjjw Callpil'all II illipiroveirilielit )csorilpfloin he as pliallil. jjpaveiineill� I a low 111011 all I d iaa d w fool 11 r -,L I irfadirig. p 1-levillb,"c all pjpfied to a indhi�,r, I awairded a fedell all Suirrace firairiv;j1pold a Hoill 1111`0F;1`,'Vll grairithill 1,111calimurd of$297,000 l.orc,,uirfwe dielpaveirliPlilill. 11`0irn faind Zoad to(laii,iril[ull',4r:ll)c)iiiifillrII'Zoad * 2023/2024 IIlh ,xe 1111 in ,ui n+.r.0 urrpi4 * 2024/2025 as 2095 CnnAiruction I irniages 11,11rijed1l"lluildbor 2, 5 11 1W 000 1, 1, Account l4wrin1kir 0218030,00,0,/01a.6/8,003 11aooje*et.ILAff,, 20years Category /Ob IResin (at: ing./Cin I & Gutteirs/.SWewallks 11,11-iolirlty 2..y,eryIlinrulyuaaurLainit Strategic Goall 4.lad1l 3 pojp Qualk (Y Village 1111 ifirastil uctuire: 113'allariced andliirorwftive clailiTillinity investineillL IN flik Granit II ljnde& Yes Locationi 1 011 Al Justification iQsuirllacfirlgo I dicas Jill 7 aII t: paverilleirit is iereslWairy "or Lho ,afar -a i I r4hck1 nil, bravell o[ vedh d1k.,s. Operating Budget Impact Nolle. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 116 Inflationary Impact Laboirand rnarlall cwsgs wflll arrect calsbrucUoin )WIS Capital Cost FY2025 Budget Total Budget (all years) Project Total $396,000 $3961K $3961K Capital Cost by Year 2025 $396,000 00 $0 $1001K $200K $3001K constRACT110111 COSt 411, Construction Engineering Capital Cost Cloirrshnuhoil 11.111gineciring, Constructiolill ( o5st Totall Capital Cost for Budgeted Years 1111111111 CbrsuucLion COSL (91%)' %0,0o(:x00 Cn 0 osl.ruc.Uun E:ngmeenng (91%) $36,000JD0 TOTAL $396,000.00 FY2025 Total $1 31 6, 0 0 0 $"m'000 $360,000 $360,000 $396,000 $396,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 117 Funding Sources FY2025 Budget $396,000 Funding Sources by Year 2025 Total Budget (all years) $3961K Project Total $3961K $0 $1001K $200K $3001K 023 Street irnpirovement (Ions Qj' 091 IFeubderal Grants Funding Sources 023Sfi,PM hrinpirovcnrionCoin,,hrm:Uoir 1 11 Uind 091, 11::edcirall Grall Its Totall $3196,000.00 Funding Sources for Budgeted Years 9 0231 'Arcct hnprcwcmc�A C'omstruction i::und (: 411' 091 federal Gran[s (75%) $297,00(100 TOTAL $396,000.00 FY2025 Total $99,000 $99,()()() $297,000 $297,0010 $396,000 $396,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 118 Sidew4Ilk III° . °°°IIIIIIIIIaceiinIaleiiurillt IIIIV iiilrograhill n 0v(,,irvk,w Owiliell, "U1 11,1wil-ir" villklgeFingilincell, 11 )ell pa - tin lell 11 lypo Cajjpil.,a11 hillipiroveirilicid [)csc ir i l lo-inlovall allid relplacellneinil- lorl.lonol Furwisdevoled tore„idonl.rwd dhaiejjpiroprainn. I i Sid(wr lk Cwd. Sllzwe 11'roprarn, 111110ed Life sinta!111c111)11hly Category 11:111,foirill'y sbratepjk, Cimill IN Otis Giraiilit IIllinded? 21, 1W 00040 25 ye,'irs "laink,linlingr Lhovillage's Sifiew"11111, sycl.eiri piloirl0kni �S, pirlioldilizus -an alluirinalle iriode of 0 rarlr,jpertal.11oil. & 3 Important GoJ 3 iolp-01jall ity Village illfi,usbrild u I re: 111,A niced rind lir()�RA fve Colinill 1-1111jilill ly 11 live'A lilel A No Justification A ir , ir , u a 1111 y, L 11 r e V ii 11 age r;o 11 It 110 ix 1111 It ef 1: u o n "', o I a p 0 ir cr 111 La ge o I t: 11110 id d evva 1111 � n 0 hAn ii- I -y ild n t Yl 111 g d fef d (wwa 1111 e l' 0 11- 1,e11 ll 1 0 1[ n 0 ir 11,11-o"Ictlive ly idell 11(iryhi if, Sidewilk irell-1111rmenric n l: 11 ull"Ps r cchxe t1l le village's Iliiaolfriillity iuo Lirillp a rid fll ll au: cldrmnts 11 xjxirids sidew ill k inniproveincii lis 'A inhi uilirrudl cost. Il Iii ofect cost", 11 d1c(ft 411 Ie Il well Half rc5ldei-0 j.xwU6jp,-Aio11 1, Operating Budget Impact 11401111e. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 119 Capital Cost FY2025 Budget $335,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $2.3351M Project Total $2.3351M $0 $1201K $2401K $3601K $4,801K 1111111111 Construction Cost: $335,,000 00 $500,000 00 $500,00000 $Soo,000 oo $50o,00w)o Capital Cost for Budgeted Years 9 Const.ruc6on CosL (100%) $2,33S,000.00 TOTAL $2,335,000-00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total CoirrAirucboin Cost $335,000 $500,000 $500,000 $500,000 $500,000 $2,335,000 Totall $335,000 $500,000 $500,000 $500,000 $500,000 $2,335,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 120 Funding Sources FY2025 Budget $335,000 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $2.3351M Project Total $2.3351M $0 $1201K $2401K $3601K $4801K 1111111111 0011 Genei[all IFuiind $335,000.00 $500,000.00 $500,000.00 $SOO,00000 $50o,00w)o Funding Sources for Budgeted Years 9 001 Coneral f::Urwl (K-)0%) $2,33S,000.00 TOTAL $2,335,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 001. Gencirall 11:::uind $335,000 $500,00o qs5oo,000 $500,000 $500,000 $2,335,000 Totall $335,000 $500,000 $500,000 $500,000 $500,000 $2,335,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 121 Streel: IRrogran 0v(,,irvk,w Owiliell, "U1 11,1wil-ir" villklgeFingilincell, 11 )ell pa - tin lell 11 lypo Cajjpil.,a11 hillipiroveirilicid �� )csorilpfloin F"esilli Ml,eels to liialliliGuln u 20 yearlire I i Stireel, firiliproveirlient: 11'roprarn, �L)(A;Ak 111110aed Life Category 1:111,fori9y Stirall.eglic Gxill IN 111 Ifs Girciirit 11 lilinfled? 21, 1W 00041 9000,0 /U�,6/3,002 20 ye,'irs (:;amll 3 lop-Quallity Village 1111 ifil"u•�U1,113dure111mll inicedind )i,cmdfve Cavii-iijinilly llii lve�d i H No Justification 11qpaiir d 1/l1111age stiree(s to Fwrwidwl;ifv aii iii krnoolh liaaveineini, loir niol,0111�,ts arld to preverit dhe Vlllhge rill corrill-Aelbe "Aireel, recol-isill-mAJOIn. IMMurials te"i.ingwilll 1-wconducted ill"u'll'oll Hils i (he Vill 11 age's c(Acs Operating Budget Impact Ainini,iFill cirack,'x2allin8, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 122 Capital Cost FY2025 Budget $6,471,322 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $39.5081M $0 $2.511,4 161M $7,51A 1111111111 Construction Cost: Project Total $39.5081M 6,471,:322.00 $7, � 18,454 00 $7,830,299 00 $& $9,474,662D39 Capital Cost for Budgeted Years 9 Const.ruc6on CosL (100%) $39,508,066.00 TOTAL $39,508,066-00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total CoirrAirucboin Cost $6,471,322 $7,118,454 $7,830,299 $8,61.3,329 $9,47d,662 $39,508,066 Total) $6,471,322 $7,118,454, $7,830,299 $8,613,329 $9,474,662 $39,508,066 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 123 Funding Sources FY2025 Budget $6,471,322 Funding Sources by Year RM Ill Total Budget (all years) $39.5081M Project Total $39.5081M $6,47�,322.00 $7J 18,454.00 2027 $7,830,299.00 2028 $,13,613,329 00 9M $9,4-74,662 00 $0 $2,51M $51IA $75 A 023 Stireet irnprovernenit Conis 4111 04p MoLoir �::uell Tax I Funding Sources for Budgeted Years 9 0231 E�t.rcct. Ilnprcwcmcr . Construcaion �::und (£ 411, 041 MoLor L uel Tax L and (ISIS) $7,2SC),C)MOO TOTAL $39,508,066.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 02,3,Stirort li-in p rovai lrio I'll t Coil list 111 wind $5,021,322 $5,668,454 $6,380,299 $/,163,329 $8,024,662 $32,2b8,066 041.h6as'oirlucll Manx11::uind $1,450,000 $1,450,0010 $1,450,000 $1,450,000 $1,450,000 $7,250,000 Totall $6,471,322 $7,118,454 $7,830,299 $8,613,329 $9,474,662 $39,508,066 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 124 Operational Costs FY2025 Budget Total Budget (all years) $63,61.8 $331..0761K Operational Costs by Year 2025 2026 mom 2028 2029 $0 $201K $401K $60 IK 1111111111 Aninuall Olpeiiafloinall Cost Project Total $331..0'761K $63,6M 00 $64,89000 $66,119000 $6'7,5�4 00 $68,864DO Operational Costs for Budgeted Years 9 Annual Operadoral Cost (100%� $331,076.00 TOTAL $331,076.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 0113cii atlionall Cost $631,618 $64,89'0 $66,1910 $67,51.4 $68,864 $331,076 Totall $63,618 $64,890 $66,190 $67,514 $68,864 $331,076 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 125 11150 Sulporild oil Idell I l, lubfir wodks� II irvx},iur,o�o=irivat; hillipiroveirilielit �� )csorilpfloin III, qP11 a ceinol -I � of cxisfil I g, s� rccUlghll, as randiHon a nd af,,c nocc;sH�at�os. I inniages Stired, 11,1i,Ih9: �LR�UIHS 111110aucl, "'IIh,llrl1,-)u1' Accoui,A 111wririlbeir 111110aed IIffe Category 11:111,foirfly Stirall.eglic Gxill IN 111 Ifs Girciirlt 11 1131111dpd? 23 'W 0(,096 020,80.90.00 1./05,6/6.001, 20ye,'irs & 3 11 inportaint: (.:��mll 3 k)jp-Quallty VdIage 1111 ifil"uSU1,113dure111mll iniced ind )i,cmdfve Cavii-iijinilly Ila lve0lmii H No Justification I u ^: ta 1111 In ow S t w ig 11 a ts (o i 1111 1 ve ( -;1 1 fp i a L V "i ir 10 1 0 �: a I: i o n ^s o n V 11111 11 ir 1, , 1, 00 111:^> t III i g, 1110 1 a L L I V u 1111 Youill, liloslwd,wilh belpluderit -b,,jplaccirrlcii it (If 2.5 sb-f,,fAhg11 it jjpolc,,s lfrrei year, p 11 le zpjpil oxhmAc rcjpkwcny11 it cosL is $2,250 1peiilhuaullc, Operating Budget Impact I budget lirnlixid. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 126 Capital Cost FY2025 Budget $93,980 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $498.0771K $0 $601K $901K 1111111111 E..�qullpirneint IPuifclhase Cost Project Total $498.0771K $93,980 00 $95,85900 $97,776 00 $102,664 00 $KY7,798DO Capital Cost for Budgeted Years TOTAL $498,077.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 11 . (Jullpirincint 11311uirdl mse CoM $93,980 $95,859 $97,776 $102,664 $1.07,798 $498,077 Totall $93,980 $95,859 $97,776 $102,664 $107,798 $498,077 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 127 Funding Sources FY2025 Budget $93,980 Funding Sources by Year 2025 2026 mom 2028 2029 Total Budget (all years) $498.0771K Project Total $498.0771K $93,980 00 $95,85900 $97,776 00 $M2,664 00 $KY7,798DO Funding Sources for Budgeted Years $0 $601K $901K 020 Capit.al I rnp row arnomt i::und (100%)$498,0 1111111111 020 Calpitall im1piroveiment If und: TOTAL $498,077.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 020 Capitall llurnp hove^nuent 11 wind $93,980 $95,859 ;f;97,776 $102,66,1 $107,798 V98,077 Totall $93,980 $95,859 $97,776 $102,664, $107,798 $498,077 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 128 Fir affic Ulhrdhng 0v(,,irvk,w Owilell, 11 )ell a - tin lell QYjjw NUA 11,1wil-Ir" vfllklge II ingilwo, II irvx},iuno�o=irivaf; Cajjpil.,a11 IIuuop iroveiruoaau"d )csorilpfloin Shooll:F, III rogii a rn, 11affic Cflialfing, I lrojert� 41re Imdhi hniHau ed,arld Can boh-coll poi,flcd Notheshrect Zc,,Ilirllaclillg doll-lolpirojerl I nages RafficCallinlill"; NA41S lrojed 1114urnber Accounl: 1114wirl-lbeir 11:111ojod IIffe, Sud Ain)I)IIH Y Il aadllrir,s�r;��¢vat II uauarfs:af"" 21, III) W" 00075 02,';,',Q),9Q).f)0.Q).71,(,).679.020 25 yeair�s nir r,ii firilirc, redil uco, l 111 Ive wqped.i of w1l uiideu 11 A w and 1 -,)Il kn kl/e 111rid pi -011 noto, I 1.1-11ain, all A bicycle ii nork�s of ti-xinspor tal,loii I A10IIYsudlni[ cow, 3 hinjpoilanl Gw,dl 3 P)jj)-0ua1HyVd1iq,,CnhrasliriwlureII'lall anced,--irid II "u c„ r,:div f::aainroii7rouuir7�lid:yllir7wa':T,duinreinQ: N () Justification 1111 esc,, 111 In 11) 1 ve 1111n e 11 o ts a re rite ii a d ed t o I e d uj ( o I I o d !I n g ii d ii ii e ig I I b 0 - 11 o a 0 d c t 1: 11 o 11 U g 11 11 I� ; I n d 111 In p 11 a V Q Id c �; t iii tI in au ii ii d 11 ) I ke fa 1111 L 11 ropcts IC d CA 11 rn f 111 (A Q 1111 an aS I'll 0 Qd e d -) a ,is by I c -a1 d c� n I: I eq ul e I, ti, uw 11-11 d skiff o b cxI V � a t ii o I Operating Budget Impact Aininuall inohnlorl,,aiice or f i 'af fog. cfliinllrli,, 111-11msilrq*F,, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 129 Capital Cost FY2025 Budget $50,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $2501K Project Total $2501K $".30"000 oo $S0,00000 $S0,00000 $So,000 oo $5o,o0w)o Capital Cost for Budgeted Years $0 $�21K $241K $361K $4,81K 9 Const.ruc6on CosL (100%) $250,000.00 1111111111 Construction Cost: TOTAL $250,000-00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total ('10inshrur'boin Cost $50,000 $50,000 $50,000 s5o,000 $50,000 $250,000 Totall $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 130 Funding Sources FY2025 Budget $50,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $2501K Project Total $2501K $0 $�21K $241K $361K $4,81K Funding Sources 023Stiicsc,.,Lllirnlpiroveii-n(, i-iitCoii-ii=,tiiuj(,tif)iii 11 und Total) $50,000 oo $S0,00000 $S0,00000 $So,000 oo $so,o0w)o Funding Sources for Budgeted Years 9 0231 'Arcct hnprcwcmc�A C'omstruction i::und ( TOTAL $250,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 131 Operational Costs FY2025 Budget Total Budget (all years) $3,000 $1.5 IK Operational Costs by Year 2025 2026 2027 2028 2029 $0 $800 $11,61K $2�4K 1111111111 Aninuall Olpeiiafloinall Cost Project Total $15 IK $3,00o.00 $31,000.00 $3,000.00 $3,00000 $3,00w)o Operational Costs for Budgeted Years 9 Am-WDI C)pcmr.Jorsal C.,ost (100%� $1S,000.00 TOTAL $15,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Closn $3,000 $3,000 $3,000 $3,000 $3,000 $1 5,000 Total) $3,000 $3,000 $3,000 $3,000 $3,000 $15,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 132 Firaffic Sign4�l III°' ,eIllllullace nr,iu e n't Ov(,,irvk,w kxqiue, Owiliell, )qjpa - lell lypo 'AaU II aIwirlc, VillageFinfrilinco, 11 ngfinlefo irfiig Cajjpik11 hillillpiroveirilicilit [ )CSC il'i pfloin Foo Aline iiirv3jjroecl iron iss or exkJiilg Lir -of 1nr dJgnfl �Njuijpiw in 1, wind cinglineeirlilip, ;budics of ii rd:er��ed lonis a sdsl iiiii dok�11'11'11lii I ing th ui relpl,'xenniond ,ii-ld upprade oilr�quillpinneind riewrablinet l,10.wc,-1bl1rlrA ne,,vcablinell. )c tA i I S lrojr�rl 'Aurnbcr Ar,rount 'Auirrilh(j )1rojer'll, Jf(; Operating Budget Impact lkmio Capital Cost FY2025 Budget $1.00,000 Capital Cost by Year 2025 2026 2.027 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 111111111 ConsLrucfloin Cost Project Total $5001K $100,000 00 $i00,000 oo $ioo,000.00 $ioo,000�00 $ioo,000 oo Capital Cost for Budgeted Years 111��11111 Corstruc,tJon (100%) $Soo,wo.w TOTAL $500,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Construcholin cost $100,000 $,qq oo,000 s114,o,000 $100,000 $500,000 Total) $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 134 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year 2025 2026 mom 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 1111111111 040 IM o to r IFue1 If ax IFullrrd Project Total $5001K $m0,000 oo $m0,000 00 $m0,000 00 $mo,000 oo $m(t,o0ao0 Funding Sources for Budgeted Years 9 041 MoUw fax f::und (100%) $S00,000.00 TOTAL $500,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 0411. IMotoir 11 U011 11 )x 11 11 und $ 100,000 $ 1 o0,000 $'loo,000 $100,000 $ 1 oopoo $"3oo,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 135 Wdlf iload Ove,irvkw 11'1'eqiue�d Owileir )ell aa - til 11 wil IYjjw [)Csorilpfloin l IIaIwirkr' Whige Finginco, 11 ln�'7'inefo iriig 4-ajjpik.�11 111IIII11piroveirillent wolflZo"A IIsaAween Ill Ilan, III(] Averlm and Cenbrall in diecall Y 1990swillh „gin CCJIIIICINAe' 5 sed:lon x.wernent. Hlepaveinicilkis llr: Vfl1ag'c'-q)j)11 lr•d i o1r alrld hin" hr.TaIn wr��r ded ,i 11O'darall Sur racc Lion 11111 nnA,lrcnlnro gil all Hi 11 l 111r, arriol n11 0 M * 2020 * 2097/2098 * 20281 CloirlAiriidian I mages ktaik 11111-0aed Nuirdber 2S II)W 000 10 Accw'A 111wrnbeir 023.80 90,001,/04AAW09 11 lirol("^d IIffe 30yem ' Catep"ory 104 Shred, Coii itrudiai Y and 11,1,ecoii Y,,Uructlon 11111-fol-ity 2 Very IliTilpoirl,dint Stil allegic G(") ll Goall 3 �ojji QuAll (y Vlll,q?e 1111f1"aAii ixtilire: 113allainced and 1111ii-aidive Colininnlinity inve"Llin-1011A IN LINS Gir'�Ilnt 1:1131inded? I i`e's Justification Operating Budget Impact Nodule Locadoin 1 011 Al IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 136 Inflationary Impact ,aboraind uniia9airifll cosUswilll aficct con"brildJoill bid" Capital Cost Total Budget ((all years) Project Total $2.8031M $2.8031M Capital Cost by Year 2026 2028 $0 $8001K 1111111111, ConsLructloin Cost 430 Desigin Engineering Capital Cost L)esipirliJngiineciringi� coinstructiolin 11�'Ingincci'iing, Consh Acdoin dost Totall $2S0,000 00 $7161M $2,411w1 411 Construction Einr ..yIneeifling FY2026 $2,AOOO $250,000 Capital Cost for Budgeted Years 1111111i Construction Cost (Bi%} $2,2,000.00 a Cor stn.icLion I nginooring (8%) $232,100.00 GIR Design E:ngneenng (9%) $250,000DO TOTAL $2,803,100.00 FY2028 ,$232,100 $2,321,000 $2,553,100 Total $2S0,000 $232,100 $2,321,000 $2,803,100 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 137 Funding Sources Total Budget (all years) $2.8031M Funding Sources by Year Project Total $2.8031M 2026 $250,000.00 $0 V3001K $L Gig $2 414 023 Street irnpirovement (Ions 41' 091 IFeubderal Grants Funding Sources 023Sfi,PM hrinpirovcnrionCoin,,hrm:Uoir 1 11 Uind 091, 11::edcirall Grall Its Totall Funding Sources for Budgeted Years 9 0231 'Arcct hnprcwcmc�A C'omstruction i::und ( 411' 091 f ederal Grans (661X,] $1,914,831..00 TOTAL $2,803,100.00 FY2026 FY2028 Total $2!iO,000 $638,268 $888,268 $ 1,9 14,83,32 $1,914,832 $250,000 $2,553,100 $2,803,100 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 138 uuuuuuu IIIIIII� i I uuuumuu loml um�m um�m SII uuuuu uuuuu�lumu I �N uuum uuuuuum Illm. Village of Mount Prospect I FY2025 Community Investment Program Requests Page 139 (-AjstuilinerService Qpdate Wfiridow Ov(,,irvlicw 11'1,eqiue°d Owiliell, knnHer 11il tzgeirall d, 11 )ell ulu ty 11 A 1011' of 11:'i I, Oil ice 11 si. S� "1111 1l )aC, 01/01/2025 11 si. Coinillpletion II amf;a 06/30/2025 Delpartimp,11H 11 illance �Yjjpe ("allpiLd Illrirolpraaveirilleird )eScrilpfloll o space, .,o st,'ffl Iru alble to rx�o forwailr.� l.ow< ,rds re:Jdenis and give .;tdl` i I i DOGAIS 11,11 oject I nbol, Account111u1rmbeir 11,11rojeU Il.Af , SuStAinalbillfty Category 11,11-iol-fly Strategic (3oall IN thi" Grant II iAllided? 25 11:11 001 020.80 %00 3- 106,6'j 1-001. 10 "loine /06 11 m1provenneirit to 114uuulblli1r I 'Wlldhng,,� 3 11 innportairig. C,oall 1 11 ffective Village Govell-11 ill 111 NO Justification Greel'and bealble L( P a Ile, eylbua - d aurid ii riuve a rou ind Uwhr Operating Budget Impact I IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 140 Inflationary Impact None Capital Cost FY2025 Budget Total Budget (all years) Project Total $75,000 $7 5 IK $7 5 IK Capital Cost by Year 2025 $75,000 00 SII Is Capital Cost (IoirvAinwboin cosk Totall $20K a;.401K $601K Capital Cost for Budgeted Years 111111111 ConstructJon Cost (10101%) $75,000.00 TOTAL $75,000.00 FY2025 Total $75,000 $75,000 $75,000 $75,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 141 Funding Sources FY2025 Budget 1'5,000 Funding Sources by Year RM Total Budget (all years) 15I $0 $20K $">401K 020 Caalraita 111 llirnl irov€ irrrn€ int: IF aiiirnd $601K Project Total 7 5 SIC $75,000.00 Funding Sources for Budgeted Years 9 020 C;:apit:al Irnpro rnvnt i::und (100%)$'75,00 TOTAL $75,000.00 Funding Sources FY2025 Total 020Caaptlitaal hirnpiroveinient. I wind $75,000 $75,000 1p otaalV $ 75,000 $75,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 142 uuuuuuu uuuuuuu uuuuuuu uuuuuuu uuumi�m�ll uuumu uuumu uumum uuuuuuu �, uuuuuuu uuuuuuu Village of Mount Prospect I FY2025 Community Investment Program Requests Page 143 Cardiac IIII iniiitars Ove,irvkw kxqiu('d,f Owner 11 sl. Sf "1111 11 �)af C, 11 sf. ("'olrivillpIkAloin IDale Delparfineii H pYjjpe I'll IdWIC K1DVVD1C7YIk, IlMaauuageivoill Aiialy"� 03/01/2025 06/30/2025 11 ilre ("allpit'all Il ilillproveirilleird )eSciriplJoin ".rejpkxe all 119 (�ard !I ac 111noillil'oll's all lid purch'asc ail ext ra oinulair bra !I nill 11g. I 11 urn inroou11!1tors r1u r reiilIlY !I n we wore Ila st pui,dhased !I in 2017, ilbrodurxA fin 202`a [oil- OI In 2025 I Images Cairdlac Monitor '10j0d "JUMbO' A( count "Juinnbeir Project Il Are Category 11111-iol-ity Stil ategk' Goall Is tlfl^, Graint Funded? Justification 25 1:11) 002 020,/0 0,00,1-/09,66A32 2033 /09 Noin Autoin-lotIve 11 qufj',)iincii iD 1, Cliticall Goall 1 11 IffectIve Village Goveirii iineinL: 11 linanclally Scmind, I'm elptionall Seii A e 11,10 he 111-1101-11IL01[s aim fulictlonall foir t1he 11 -1 -lost pairt wwc' IIkcelCaoin rejjpaiir,. 0he blggv,t fsue i, 11 -low 11-inuch Led-lindogy h,,.r; uum0.nroved airlcew�ir II,aFL I,auuu dha-,v0 lv-"e rnjarovo-nonf,,s iirnr..Ilu de: 11 ntxj'rated 111[loll lltoirfilrig, jjpadnrl4 qarc dasll flboand fi'' U, and paLiell 0 Walk, 'and aleirf of p"A fell H dechil 110, albfllty Ilxr ',hroailin wit1h 0 hr, ho";JpH all, ill liepi al;y11 Wlve Mask, (111WIM) recdlmdf w1l lidl 11 pir evend �' oveir vell ltdaf oll Operating Budget Impact aft eir 2030 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 144 Inflationary Impact "loirle Capital Cost FY2025 Budget Total Budget (all years) Project Total $674,208 $674.2081K $674.20811 Capital Cost by Year $0 $2001K $400K $6001K 0 E:qullpimeint IPurchase Cost Capital Cost for Budgeted Years Capital Cost FY2025 Frju�lpnrwint Pijirdhasv Cos� $6/4,208 Totall $674,208 M E.:quiprnent Purchase C.:o,.;t (100%)$67/f,208.00 TOTAL $674,208.00 Total $6/4,208 $674,208 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 145 Funding Sources FY202Jyry 5 �Budget '`•• , 2 08 Funding Sources by Year RM Total Budget (all years) $674.2081K $0 $2001K $400K 020 Caa raita:n l llir>rn wiroveiry"a i rt: IF aairnd Funding Sources 020 Caaptutaall Ilurnpairoveinient. II�u. ind 1p otaalV $6001K C Project yry Total p $674,208.00 74,208.00 Funding Sources for Budgeted Years 9 020 C;::zapit:al Irnprov rncnt i::und (100%)$674,1( TOTAL $674,208.00 FY2025 $674,208 674,208 Total $674,208 $674,208 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 146 II ir' (,'." oiiu IIII ower VIII oad St: retdhers Ove,irvkw 11'1'eqiue�d Owileir 11 sl. S� "1111 11 �)a� C, 11 sl. CoinillpIkAloin 1 )a lc Delpartinell I DYjjpe Nlld-wle Koaralciylk, Aanageineid Aiialy"P 01./1"11 /2025 06/30/2026 11 ilre ("allpill'all Ilrrolrwnaaveirilleird )eScrilpfloll o 11:11 1111'r,11w;e d "mweir (:ol.sandl 4 power oadiy,,A.en,is loir thii ce firoinflliine aiinhijlano^s andl one irc,,',eirve. I l to weir Cotand Load SyrAcin DetaHs 111110fed I'llumber A(,(, ounl: 11"Nluirildbeir 11:111'oef' � Life Category 1:111-fority sbrategk Goall 11 u, dhN Grant 11 llnlded? 25 11:11) 001, 020 /0.90.00 1./09 6&>D32 / yeall S /09 11',loii ii AiAoiriliotllve V, qulpinai H 2 W ry 11 rrilportaint (30all 1 11:: ffective Vlll'7gr COV011-11 inell d 1 11 fil ancldfly Souii iid, 11::xuajptioii w1l Seii vice "do Justification We retic wd arle 10 Year oldv'A firailli all [ 11!'1114",. Grove towns,Ihljp aaflbulan�iI' D the rAheir dhree are du"� to Ibe replaced w, they have irr adwdl L11 iriir Iliife expertancyol 7 years and have exporlencr"d inuITIP1,01A I'll-lailill'onallice lF'Sues Operating Budget Impact 1\011 le expected 71:1 wowlIll l did ase a 7 year wairrainty, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 147 Capital Cost FY2025 Budget $1.42,500 Capital Cost by Year mom Total Budget (all years) $2851K $0 $40K Enquillpirnent IPa.uirc lhase $8: CK $ 201K Project Total $2851K Capital Cost for Budgeted Years TOTAL $285,000-00 Capital Cost FY2025 FY2026 Total 11 . (Jullpirincint 11311Airdl mse CoM $1.42,500 $1.42,500 $285,000 Totall $142,500 $142,500 $285,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 148 Funding Sources FY2025 Budget $1.42,500 Funding Sources by Year VAIM NM Total Budget (all years) $2851K $0 $40K $80K 020 Caaital llir>rn1piroveiry"irt: IFLAnd Project Total $2851K Funding Sources for Budgeted Years 9 020 Capit.al IrnprovorncnC i:: und {100%)"285,0 TOTAL $285,000-00 Funding Sources FY2025 FY2026 Total 020 Capitall llurnpairoveinient 11 wind $1.42,500 $142,500 $285,000 Totall $142,500 $142,500 $285,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 149 SCIIIEII IIIIEII3atlery Ove,irvkw 11'1'eqiue�d Owileir 11 sl. S� "1111 11 �)a� C, 11 sl.CoinillpIkAloin Il aml;n Delpart imp'11H GYjjpe Nlld-wle Kovvalciylk,Aanagein�eid Aiialy"� 01./01 /2020 05/31/2026 11 ilre ("allpiLd Il ilillproveirilleird )eScrilpfloll � ".ejpkxe a111 IIbaA Aerles on SCII aAeclulpi'moi 1u and'41111b'wJ<uj.) Ilya H,crles. Added ulro 2023 lar uxnnsldeiralkii ii ulro 2026. I l DOGAIS 11,11 oject "hil nbol, Account 111umbeir 11'uaujeUIlAf, Sustainalbllity Category 11111-iol-ky sbrateglc (3oall IN thi" Grant II lAilded? 24 11:11) 003. 020�/O.%00 3-109,66!)D21. 20,'X) Im rejjpl<� ccrrlerlt lin 2032 `,11A /09 Il,loni Autoirrlotive IFquafilpr7ent 2.."; e i, y 11 rin po i, ta n t C, o a 111 11 1 fec t fi va ; V� i 1111 a ge G ove ir ii i ii in e ii ii L: 11 1 ii ii �w i i c u a 1111 y So u ii ii d, 11: xf c 1p t i () in a 11 Se ii v e NO Justification A1111 LxAAQi-le,7, oin cw[ rent SCUA equlpi,irienil, were 4pill4 ased hin 2018, aind wl1111 be A 11he and ol dhelir Ilfife cycle fin 2026 Operating Budget Impact None. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 150 Capital Cost Total Budget (all years) $401K Capital Cost by Year RM Project Total $401K $0 $MK $201K $301K $401K Enquilpirnent P�jirclhase Cos�. Capital Cost 11(Jullpirincint :)AIrdImse Cost Totall $40,,000.00 Capital Cost for Budgeted Years E.�quiprncnr. Purclw�so (..'osL (100%) $40,000.00 TOTAL $40,000.00 FY2026 Total $40,000 $40,000 $40,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 151 Funding Sources Total Budget (all years) $401K Funding Sources by Year RM Project Total $401K $0 $MK $201K $301K $401K 0 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Callikall hrnlpirovonicnu I1::wnd $40,,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irrprovornent. i::und (100%)$40,00 TOTAL $40,000.00 FY2026 $40,000 $40,000 Total $40,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 152 SIIIIEII IIIPadks and Aiit ottes 0v(,,irvk,,w Owilell, 11 M. Coiririjjpletlo If o 11 b lc Delpartinell I IYjjpe 'Aldhole Kovv,-dciyk, Mainagoiniod Aiialy,;P 01/01/2029 08/01/2029 ("allpill'gall II ilill1proveirilleird )cMscirijpfloii 0 ".ejpkwe ellill.fire finvenil.ary o 1.0 - ye,n olk I SC11,A aill padlks whidl are (minilphaii lt wil.110 2015 1\111 II1y ;kvldai-& and canideired 11',low Fwejjple(xs and all, L)CAUler, wi1111 ;drm lxpurdhased. I inages SCII UA ",,wk rwid Air 111,0A le Dctaik 11:111ojod 11"llurnbor Account ',Jwifil-ilranir 1:111roject Life C �fl egory 11,11rioll'ity sbrM,qdr, Goall Is flhN Gil II unded? 25 11:111006 Q)2U),7),9U).i)0.1,.709.663,004 2039 709 11',,Ir)in Autoinrlotive 11 :qunil ,,)rnoi il, 1, C11 htcall Goad 1 11 ffective, Villige ("joverni'll-loillL 11 fillorldally Sound, 11 xq:qptioimll Seii vlrxv "lo Justification kns1 11"ji, c1l lased lin 2,017 rmil,h lundfing firnn,,oUh2016 AllG prxi il, Q 1 -le, 'ww 501 ',A will ll birling us' ill ll'o cornplialinc(, vvldh cijirrc,nl,airldnii ck nii iid givra � 11 le firePlgll ltell , tltueIlaeirunrlitMounoeased safety eii 11l wi-N:cnnci lts, Operating Budget Impact U 11 iirz olpeirathi iig judget wl111 bc,,Weded by $1,500 to replace/ii-qpall, rinkcrAlzu ems lteins like slxajj�s. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 153 Capital Cost Total Budget (all years) $6001K Capital Cost by Year INIM Project Total $6001K $0 $�SOK $3001K $4501K $6001K Enquilpirnent P�jirclhase Cos�. Capital Cost 11qu !I princint :)AIrdImse Cost Totall $600,000.00 Capital Cost for Budgeted Years E.�quiprncnr. Purclw�so (..'osL (100%)$600,000 OC TOTAL $600,000-00 FY2029 Total $600,000 $600,000 $600,000 $600,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 154 Funding Sources Total Budget (all years) $6001K Funding Sources by Year INIM Project Total $6001K $0 $�SOK $3001K $4501K $6001K 0 020 Calpitall irnpiroverneint FLAnd Funding Sources 020 Cap itall Ilurnpairoveinient. 11 wind Tota ll $600,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irnprowarnomt i::und (100%)$600,0 TOTAL $600,000-00 FY2029 ■ Total $600,000 $600,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 155 Operational Costs Total Budget (all years) a I Operational Costs by Year NM Project Total 1.5 I ".fat $40C $800 $1.21K ,� nir Ua:al Oi eireaiu'.iioiraaul Cost Operational Costs Anirnu!aalla 13ciiaabionaalla".ost 1V otaalV $lh500.00 Operational Costs for Budgeted Years 9 4nrWal C:Ypcmi or7al Cost (100%} $1,1ioo.00 TOTAL $1,500.00 FY2029 Total $ ,500 $ ,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 156 Ihnnaging Carineras 0v(,,irvk,,w fecpj('°d Owiliell, 11 M. Coiririjjpletio If o 11 b ic Delpartinell I fy1pe 11,lidhele Kovv,-dciyk, IM,eaun.al oiniod Aiialy,;P 01/01/2029 11/01/2029 ("alpiLAI II iiiii1proveinicird )c�scirijpfloii � f he projed. Was hili xodixwill ko hs ("ornilruilRy inve:sUrnent 11:1ii ogrniin lin 2024 to 1, 4 flienixill 1111,1agh Ig Carini��iras vf C,j in 2029 and 2033 I i fheiriix,111 11 ktaHs 11111'0tecf I'lluinber Accoui,A 11"Nifuiririlbeir 11,01 f,. IIffe Category 1:111,foll1ty St aAepjk, Grx,)11 IN 1,1111" Gii-'-init 11 unided? 25 11:11) W5 020./O 90.00 1./09 6&)D43 p he inexiA ,are due ix,Ibe i fin 2033. /09 11',loin AiAoiriiiotlivo Lquipincid 1, Cii Ulcall (30 4 1 11 11 fin")i1d,illy Sound, A,qptloinall Seiviice ', o Justification f he raillrwira-, sjllow w>Lo quirkly oq�aLc vidiJi-w, [rapped hrdiglhteire,, dieck lor filre Qxtririslioiri, arid Well iffy hol, ,jpol:^, oin dw firegirouii id. f hcw Operating Budget Impact Allow $500 Ipae.0 yr forincide-M.4 a ejpAirs !if nooded, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 157 Inflationary Impact Prices alre fikvlyno hwilea,,c Il effmcm can puimlhase Iii o 2029 Capital Cost Total Budget (all years) $601K Capital Cost by Year 2029.-) Project Total $601K $0 $i KIK $301K $45K $601K 1111111111 E..�qullpirneint IPuifclhase Cost Capital Cost 11 . quipinneint Ifaulrclhasc Cost Totall Capital Cost for Budgeted Years 9 I quiprrent Punche Cost (1(X)%) $60,000.00 TOTAL $60,000.00 FY2029 Total $60,000 $60,000 $60,000 $60,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 158 Funding Sources Total Budget (all years) Funding Sources by Year Project Total 'N 020 Caalraitalllllirnl iroverneint:IFaairnd Funding Sources 020 Caaplitaal hirnpiroveinient. I wind Tota ll Funding Sources for Budgeted Years 9 020 C;:apit:al Irnpro rnomt i::und (100%); 6.0,00 TOTAL $60,000.00 FY2029 $60,000 $ 0,000 Total $60,000 60,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 159 Operational Costs Total Budget (all years) $500 Operational Costs by Year NM ".fat $120 $N Anirnuuia 111 C:.ili eireafl oirmlll Cost Project Total $500 $":n00.00 Operational Costs for Budgeted Years 9 4nrWal C:YIpcmi orral Cost (100%} V.300.00 TOTAL $500.00 Operational Costs FY2029 Total InV lrnuaal a 13cii aabionaal a".a.ust "d,500 $500 Totall $500 $500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 160 V&hldIeIRadioVIII° III VIII iiiriu ml iiirm l° Ove,irvkw 11'1'eqiues° Owileir 11 sl.slail Dalo 11 sl. CoinillpIkAloin II )al c Delpartinell I pYjjpe Nlld-wle Kovvalciylk, Aanageinueid Aiialy"� 01/03/2025 07/30/2025 11 ilre ("allpill'all IIIrill1 lraoveIruourlyd )eScrilpfloll o "'.ejpkweinenl. of Ulle eNJre inventai yof IiHire 11 )qpaii tirwint urraar1hile radlos fair alll vehildes. Our cuir reirflaradios ai,e 12 yeai's old and Inca Ilongeil Ilbeiii u< seirAced. Illn ad d lt ion, pa - ts alle iaa�=airly lirnpo"'slIblo. to conrie by inalkiing i-ninoll ilea housem1pnirs d !I ffirAjIll, I l Adbile Nladlos MAHS 11:111ojod 11"llurnbor Account 11,1wifirdbeir 1:111rojed, Life C afl e'gory 1111i'loirity sbrateglr' Goall Is flhis Gil II unded? Justification 25 11:1) 004 rt)21),7¢).9).P)0.1,.709.a°r68.001, 2035 709II',,loin Autoinrlotive 11 :qulj,,)rnoi il, 1, C11 H'Jcall Goall 1 11 ffective, W1111,ge ("joverni'll-loillL 11 fillandally Sound, II xq:qptioinall Seirvkx� "lo Nail H vvosp Cenu rall 11 )ispatcl-I Ill as coll Fill'i'll-led Ow"Y all, �n l ar! 11 lig alll or oull, sollable 11' 'xjios [hir(wg1h Mol'aroll a, a 'xi - dhas�curi-oll Idly lin tr 11 le 0111) lo - 2024, As a ii osi a 11 t of 1,11e poll t Able irm I lo pull rdvsc:; con tir ad, Wll 1,1111 11\k)irthwc);cru 111,11 1111 II Yspat d1l, lNda4 ursda ls of rung us a 3 /% d S(�:Qu 11 lt (good fou- 18 11-noiliths) On I y6blIe radias an, wd[ Carr' !I darling L I ur� age o� olu I[ moblle radios and t1he dfa ffic-ulty of SF21[ Vick lig t11 win, wc� wairill, tr0 1 a ke advaintage of Lhis discount l'o jjpuircdhas(29 11 affios (1 for eacdhi vol-licle uIn ouir Hoot aind 1—spaii nil. Operating Budget Impact p Ilhe orally opol-M kn 1111 costs would be unlloiro,;eein rel paiii s. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 161 Inflationary Impact 4 we pi.iirdwe un 2025, we wflll save 37%, Capital Cost FY2025 Budget Total Budget (all years) $1.30,000 $1301K Capital Cost by Year 2025 $0 $401K $80 IK 111111111 Ex:jullpiment Purchase Cost Capital Cost :Equllpirncin11:1urd-11'Kie Cosd Totall M Project Total $1.301K $i3o,00000 Capital Cost for Budgeted Years ,1111111111 E.:quiprnent Purchase Cosl: (1001%) $130,000.00 TOTAL $130,000.00 FY2025 Total $1.1110,000 $130,000 $130,000 $130,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 162 Funding Sources FY2025 Budget $1.30,000 Funding Sources by Year RM Total Budget (all years) $1301K $0 $40 IK 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Callikall hrnlpirovonicnu I1::wnd Totall $8CM $�201K Project Total $1.301K $�30,,000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irrprovornent. I::und (100%)$130,OC TOTAL $130,000.00 FY2025 $130,000 $130,000 Total $130,000 $130,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 163 Operational Costs FY2025 Budget Total Budget (all years) Project Total $1,000 $51K $51K Operational Costs by Year 2028 $¶,000 oo 2029 $,00w)o $0 $250 $500 $750 $UK 1111111111 Aninuall Olpeiiafloinall Cost Operational Costs for Budgeted Years 9 Annual Operadoral Cost (100%� $S,000.00 TOTAL $5,000-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 013cii abionall Cost $1,000 $1,000 ,CiI,000 $1.,000 $1.,()00 $ 5,000 Totall $1,000 $1,000 $1,000 $1,000 $1,000 $5,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 164 i u iuuuuu uum mu �IIu�N uuullllp � umi uuuuuuu uoiiip uuuuuuu uuuuu uuuuu�luu uumumu lump u., mu�m�0 uuuuu r I u, mu a mi uuuum uuuum IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 165 Flree IIII IIIIIainultlhnfgVIII' 2irogrann cNavow RNWM Omni' Dave 11111111111, 511111po'hilloid01110 Departivelinf FAeQj&GmwAF, "w CAALall mKownnid AscripHorf xwevum I moges Ree odwic DoWls Accoui'A111uirirflxir 11:11lojecf IIffe, category 441ty Slahjc G&I Is thir Graint 11 bided? Justification 21, 1W 000// W11_MM7'.GMA7 QD.671008 Aininuall Iluirrye ct 710Ilriu,exnllaineoijs 2 WG ry 11 nrlportaint Goall 3 1111011'rishrii chji'e. 11 Salaincednd Iii oxs flvc Corninminilty investrincii H. " o n W mbwk Mal 6 W amomm PbAlig mmmumn 4 0nem aloin to cai lffrue lo add irefoii estatloin ri CuC¢s Was wMA; Ma Q0, wawm wRAH Q 00 AK Or Pon YT oslawwd Abe UhMy wnw0Qmd nmonall 111111AITII-)or's aveirage -.qpjDi-o)dvnMeQ 410 tmes pa year, I he VHhgds Oan h to Oat Kproxlmate[y 6MJ MAI Ur s qT "an We um-ently plarL an1froyfinicately 450 replammak M, p, ror Oyold yemt and add appoxhuLdy 150 NSmshUbn hNns M, year Now &I =- liankhog ohTpbamwi A Mtn has been KmOMM M don (mime 2017L we haw, dva=W tY mmw% are bvs Manod anmmHy buL hanand U w ske of be UTes we are plaii iq ing, Stail dii lg he 2018 a; W wM&A C AW 2W, U w "HmmNsW 0-ce wc plainted was 2 a lucaurruenp'cii , will.h 2 5" rflalyvAcir fi'ce"� 11)(Ang the tyjjpkal'Jze113udgro pell-IT111t ling, we w11111 contlinue to 1-1-lakc All 11 epIL-iceir[leirit fii ee,s aii iid irnx oro,,Uloiri tircc,, 2,5cqu"uittneateir, Operating Budget Impact hrl:,tallfiio, gal:oir IIxigs aroi.iild inew IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 166 Capital Cost FY2025 Budget $249,237 Capital Cost by Year 202S 2026 KOM 2028 2029 Total Budget (all years) $1.2971M $0 $801K $i601K $240 IK Equllpiincnt iluirchaso Cost Project Total $1.2971M $249,237.00 $254,22100 $2S9,30600 $264,4SO 00 ,5269:9„739%.00 Capital Cost for Budgeted Years 9 I _quipment Purcha,...e CoL TOTAL $1,296,953.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total .quilpincint RIJI-C11 am”, Cost $249,23/ $2,)4,221, $259,306 $264,41)0 $269,/39 $1,296,T)", Totall $249,237 $254,221 $259,306 $264,450 $269,739 $1,296,953 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 167 Funding Sources FY2025 Budget $249,237 Funding Sources by Year 2025 2026 2028 2029 Total Budget (all years) 1.2971M $0 $801K V601K $240 IK IIIiIIIV 00111 G:aa>inei[aall IFund Project Total 1.2971M $249,237.00 $254,221.00 $259,306.00 ") 264,4 iG'.1.00 $269,739.Q O Funding Sources for Budgeted Years 9 001 C neral I::unG1 (K)0%) $1,296,953.00 TOTAL $1,296,953.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 0017cu7cirall11:u.iund X249,2:7 $2.54,2.21 `�i2.,59,306 $264,450 $269,739 $1,296,953 TotGaIV $249,237 $25,221 $259,306 $264,450 $269,739 $ ,296,953 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 168 Operational Costs FY2025 Budget Total Budget (all years) Project Total $5,000 $251K $251K Operational Costs by Year 2027 $5,00000 2028 $5,o0o oo 2029 $5,00w)o 1111111111 Aninuall Olpeiiafloinall Cost Operational Costs for Budgeted Years 9 Annual Operadoral Cost (100%� $2S,000.00 TOTAL $25,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 013cii atlionall Cost $5,000 $5,0oo $5,000 $5,000 $5,000 $25,000 Totall $5,000 $5,000 $5,000 $5,000 $5,000 $25,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 169 I.. I � �I (IIIIIIIIIIIIII 1111111 � IIIIIIIIIIIIIII�� IIIIIIII In. IIIIIIIIIIIIII IIII�IIIIII IIIIIIIIIIIIII IIIIIIIIII IIIIIIIIII� � uuumu a uuumu IIIIIIII uo � uuuum uuuum II Village of Mount Prospect I FY2025 Community Investment Program Requests Page 170 Canwrrmxnity Center, cNavow RNWM omwir I A"WHOW 11 M. ConriplotJoin DaIc !"MAM111I ")o Julio K,111-11(% Dh ortoll, o 111611, 1 ain so'Accs 01,10112027 12M10T8 Humon SaKes ("alIA"111 II inn1prowirincint AsApthn CaNbd UK rm pinsiNc pnchneoFpYpoqyand nmskucUm &an "mudod and I mag:s [)(.,UA1S MyMct Nunber Account 111uml3cir Nted Uft, wnwwAty liroject Codc 411,1[r(njr,:ct Acccui oUiw) cawwwy 145MY SWUM4 GKI Lux IN GWA wndm? Justification 202NHS501, 0w7,5PWfS W 40 WUS I IdA /06 1111 n1proveirineint to 11 lullifir, 1:1,01111 iings 2.\Ir,l,ry 11 -jrqpfjj-t, gjt C&A 1 1 Ac&e VNyp GowrnmcnWWaxWN AwAj Amomm! SuWr� NO Operating Budget Impact IlifVII111agi-ww1d no ongei-pWMKw"qww 5, IWAQWd mks W WnUn He QdUyh&Wc WWW% Waning and Anm smwkc IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 171 Inflationary Impact NA Capital Cost Total Budget (all years) $4.51M Capital Cost by Year RM Project Total $4.51M $0 $L21M $2.41M $3.6110 Capital Cost Coll -VAI[ lwdoin COM Totall $4,500,000 00 FY2027 $4,500,000 $4,500,000 Capital Cost for Budgeted Years 111111111 ConstructJon Cost (10101%) $/"S00,000.00 TOTAL $4,500,000.00 Total $4,500,000 $4,500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 172 Funding Sources Total Budget (all years) $4.5 IA Funding Sources by Year Project Total $4.51M $0 $L2M $2,41M $31.61M 0 999 To E.3e Determined Funding Sources 999 R) Be DcAcii-irinfined Totall $4,500,,000.00 FY2027 $,I,!5oo,000 $4,500,000 Funding Sources for Budgeted Years 9 999 Tc) E3c Dcr.crrrflncd (100%) $4,S00,000.00 TOTAL $4,500,000-00 Total $4,500,000 $4,500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 173 Operational Costs Total Budget (all years) Project Total $171K $1.71K Operational Costs by Year $0 $2,51K $51K $751K Aninuall Olpeirafloifmll Cost Operational Costs for Budgeted Years 9 Annual Operadoral Cost (100%� $17,000.00 TOTAL $17,000.00 Operational Costs FY2028 FY2029 Total Aninuall 013cii abionall Cost $8,!m $81,500 $1.7,000 Totall $8,500 $8,500 $17,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 174 lllllllu� uuuumi umoil umi �ouum i � uuuuu " um�m �IIIIII uuuuuuu uuu II uuuuuuu �m �uuuuuuu� uuuuu uuuuu�umu I^^�s�i�l�l uuuuuu) u m uu°m ( uuuuuuu III uuuum uuuum Village of Mount Prospect I FY2025 Community Investment Program Requests Page 175 ll ;iiiridl use r,1)evices 0v(,,irvk,w 11'1,eqiued Owiliell, Iedhinolojy all id Il innovaliollorficeir Dellbsartiiaicil Jon-riallon Iedhiiology �Yjjw Callpitall II Irlrod'alrerveIruoaall"oL [)CScirilpfloin Rie�wllcdulerlondl aptop', 10fl"Ad", 10 pifinll.eirs,4 scanneirsairld 25desk plhoiries Althour, ,11h this hio,,, Ibecnain purd[o,e, !V was linibi odur:ed linto HheCorni-i-luillityinve,,,hnrieni111ii-orrailin MairLh-q,,jn 2018. I I NAAHS 11,11rojed 11"'Iluiriber Accoui,A 11",11wiri-lbeir 11:111ojed Iffe ca� egory 1:1111oll1il'y Sbrall,eglir: Goall 11s dI Grant hundled? Justification �,uj,,,ged 11 all A11'4 11 1001, ( �62,20,90.00. 1. 70 7.65 5.00 1, Aii orluall 11 y 707 CoirilljpAcr 11 2 Very 11 illjportanf: Goall 1 11 iffectiveAllage Goveinnrneiiil,: 11 finairidally Sound, 11 xo'jptloinall Seii vlirx:. I Ili ituril lall Ilc,ase payliniell ll-', ai'c umrade on C011 -1,111,311111[e I, Ihu.asus to ell lwrc I'll lal, I'll oc.1 c aalruu funds nvallablc roll i'll 1611, Irerl.nllnu urricirit whui i ii leeded � hu cx Iwcted ife 0 eii id U.50i, devir.es is� o I yi-, Lablos 0 5 Y11 S. 11 uggfAxnj klj-Aojp,� o 6 yii s. dcslktoj,.ur,, IIallatopr,, seini uggedized av / yii,�.jjpirhll,ei-,s 10 Yll de,k jpharlea; Operating Budget Impact wheill lielpl",aco'nent ep'llpillent I,,,au.uldun ed,sInewraauatudorIlalcneIIjayirrei7dsvn1111Ilaa�,ra>Iu"ndocaliderLoei,uulroahutltua�rflnlrudunf, III equijjii-ieii[ fs ird p1,11lCh"V;ed1 doll Ulle desigroled yer,uur, iLs in"placerneinil, A1111 lr�ove do the lollowfing Year. IlAa l"11311al rel`ire ,hick, ofcannjputeir Ilrsalralwaalrr einsuirewe have 11 rdhablc and uj.-p to dale cquipineiiiifor cirkkall ryMeirri Lr) ',(nrw1,11c publif'. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 176 Capital Cost FY2025 Budget $1.39,500 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $ 697.51 $0 $401K $80 IK $120K Project Total $ 6 97.5 IK $ ,4.)".a00 00 $1:,%500 00 00 $139,500 00 $1:39,•"3631.00 Capital Cost for Budgeted Years PurcI,,asa CosL (100%)@ 697 TOTAL $697,500.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 11cpfllpirncint PiArdImsc Cost $1 39,500 $139,500 $'u),95oo $139,500 $139,500 $697,500 Totall $139,500 $139,500 $139,500 $139,500 $139,500 $697,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 177 Funding Sources FY2025 Budget $1.39,500 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $691'0511 $0 $401K $801K $ 20K 1111111111 062 Cornlputeir IRelpllrmcerrrent F Funding Sources 062 CoinnipAcir3clplaclovcint Fund Totall Project Total $ 6 97.5 IK $139,500.00 $1;3'9,500.00 $1:.''9,500.00 $ I �9,soo 00 $139,500DO Funding Sources for Budgeted Years 9 062 Cornpur.cr Roplacernont i::und (100%)$69' TOTAL $697,500-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $139,500 dal` 9,500 $139,500 $139,500 $1.39,500 $697,500 $139,500 $139,500 $139,500 $139,500 $139,500 $697,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 178 lhnf rastructuhire 0v(,,irvk,w 11'1,eqiues0Owilell, lechinology all id Il innovaliollorficeir Dell �artii 11 wil ii-Jon-l-lallon ledhinology lypo Callpitall II ilillpiroveirillent )CScirilpfloin he sdI ledulcd iii firashrucb3ire irp jjplax� iinlents iinckj6, 2 seii veirs, 1 I1,1ASes, aii id 5 rlol:wark swH dhes. Also iii iduded fin tho 2025 Calpltall 11 m1i)rovoineii H lirograiln is to ncw fiir(malll A11H Ihoup,11 i r hils has hoolill all I ollippling arlirluall 1puull d lase, it w.is iii it read uced linto 0:11le Corrirriuilllty Ildnve shnorill. Iii ogirain sLarbinF lin 201.8 11,11roject INUI-111her AIA 11 F 002 h,count Nuirinheir 062.201 90.Q1C'D1, 707 655.001, F111 oje t II ifF, AnnuJIlly flateg'ary 707 C arriputeir 11 ardwaire/Soll.waire 11,11-ioril'y 1, Cril'icall stiral,cgki Goall Goall 1 11 ffectivo Village Govelinnillell Ill,: 1111 are-lally Saull id, Fxcu','Jptloiriall seirvk�e Justification 111nrt.eiwuuuallllleasee Dayll-liell AS alre Ill01,1 C01-1,11ID11111 orpurdl ux�es to ell ein C? � 11 la� � 11 lcre airc hjnd„avallable roll 01 l6ir ii oj,-Aac.eilineint wher ii coded, fhe expected IIllie or ri M-astructure devlces is: o 7 yrs. scrveils n / loos. 11 mAsmorlk equlpil I'lell [(, sAorRge Operating Budget Impact Wheill 11-c1l4 ace=rune:rd eq ui pnrnel'A il'i I'mi-chlosod'n 11 low I-11 aul H of Ileasr, payll neifl " willl 'wgilin lirn oirder ter onsuire, lout uire full Ohng 1111 equill mirlo-0 is 1111M puird iased hi t 11 ue designaLed yeall, h S relplacell nentWrIll innove toI �c 10110wiii g yeaii, RI.egulaii refireshes of conn1puteir 11 mirdwaire einsuires we have reliablIc airid ul u O o datrr 0�1U11ATIC411l, for cirr(kall 1yAoiifv. Ira �aeirve t1 tcq jpiul-Alc. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 179 Capital Cost FY2025 Budget $72,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $2751K $0 $2010 $401K $601K 1111111111 E..�qullpirneint IPuifclhase Cost Project Total $2751K $72,000 00 $77,000 00 $42,00000 $42,000 00 $42,000DO Capital Cost for Budgeted Years E.:quiprncnr. Purclw�so C'osL (100%)$27S,000.00 TOTAL $275,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 1!(1uullpirncirlt 11311uirdmse Cost $72,000 $ 7 7,000 $42,000 $42,000 $42,000 $275,0W Totall $72,000 $77,000 $42,000 $42,000 $42,000 $275,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 180 Funding Sources FY2025 Budget 72,7000 Funding Sources by Year 2025 2026 mom 2026 2029 Total Budget (all years) 2,I $0 $201K "i401K 60IK 1111111111 062: Corm auteir If epllacerrra*irA IF... Funding Sources 062 t::a inniipu a¢Ir I11klclrllana c�iva' i nt li wind Tota 11 Project Total 7I $72,000 00 $77,000 00 $42,00000 $42,000 00 $42,000DO Funding Sources for Budgeted Years 9 062.Cornpu r.cr R Irlacernont i::und (100%)$27. TOTAL $275,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $72,000 $77,000 $42,000 $42,000 $42,000 $275,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 181 uumuuu ump mum �oml uuuuuuu Vu,. umm VIII uuuuu uuuuu mud IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 182 ody WarniCanneriiurlll III ldbillllle Video iiecardfinly Systeric Ov(,,irvk,w fab lllar>d,'p: Owilell, Delpartinell I lYjjpe [)cMscirijpfloii � I f,iii t Rvecdle, II br>A'rl,a't':y ClhkJ 01,/01/2025 12/31/2029 lollo> ("allpill'Al II ilill1proveirilleird l heaveirageseirvl(�e fire foir - body warin c:aivlora 11', thice Lo fiveyears, II in 2025, the lolkx: 'IclAor body an ol-1111 (�aArleir"V;WHII Ibe approndhhlig H -wend okeirvlce Ife.As- sudh, thedelparIrl nciN need lo rrjjplx�e lherarrier,u fleO--mrld amisodall,cd rxr,(:.ssorlcsnll, Hhna tlirrle. In wJdltioin, 11he dc,1xidinell L WHII all So ball, Lo re, placv the rrlolblli:.* video recoird !I ing sy:Aeiins lor all 11 field velddes to einsuiro ouii Ogltall vld) systorm, syin�c wiu I i uAch 011hor WHII ewlhjaAe coil 11(ell,lj,mir,7,aIlry voin(birs sA LIO tlilrw� I Images :1 lrojed l4urnber 21, 1111) 005 Ar.counQ ',,hjinnlbei� 02060 90 00 1 707 665.056 11,11roinct Life l 11 [c' cijilrvrx11114ve 4 ': P yelwM cii Are Ife. SuN ,t All o111:Ni11lklly Zoplaching t ille body worm rarnorm"�s arld IllrllohPIllc vldeo rcccndei-'s vvilll all ow officers to inneet stote nandAesaii [d l po,31tive servf(:e lx) the C01,111,11M (-Atu�,pry /o/Q1(, II In111alaA:p',,, ii 11,11-ioll'UY 2 Wry II1Ifn11harcaarl.an( SlUr'Acgic Goall Gudll 1, 11 ffiOivc, V11111age Govelin a11K�l at� Hnaiwiflly Sound, II xfejjpl,Aons)11 Service IN Lhis Gir,,ant 11unded! Ill Justification Loc'adoin Addre,as. 911. KerrAingWin 11o�.ad l 11 le an reirlt fled of body wnii in can-wilas and rnobfle Dada eo ii sys'�Oenrls rAdlll conne to lts eind of service llHe ai ld ii equiii c, ii oplacenricii 0. Body woilirn U311 11C111 as all C 11 FXpilil ed for the 11 IdliceDelpaii fin-loints Iby fl lc 111111knok, II ogldltwr el IIle body worin c; inneii -A and vell 11do i-nobdo vWc,'O ii ccw dling sys4 (,i,n prcvlde,, A ;,nr,,pa1-e11 lcy wN 11-111111 flhe col-ninuinity and pi-ovlde,, doc.umentatlon cA officei cai dw ji-dessk)irialfisi n and dedslai onialklnA, hk, Cajj)ltall Iii VOSbI11101 d WHII pirmfide 'al loplarenrient o[ alll Ibody..wa n ii cairler,'is, i nd,,Ale vWco rccordlirig ryM.vrrl,, vlil loo t ir,'3inslei, ,hUait s, ,iii linuall dol ,Aoimt,c ( o"As, and suppoillil ig soflmmrc ficun,4ng. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 183 Operating Budget Impact i1helprojed wfl1cost$300,wo pu 11-c hzreand a bansflilonall [ceol $75,000 lordkmd I bodywai ncaueraand poll -Ale video ii ecor6ng fooage Inflationary Impact 11"10 projected illiflationairy inrilpacta(dhs thmc Capital Cost FY2025 Budget $300,000 Capital Cost by Year KDM 2026 2027 2028 vam Total Budget (all years) $1.5 11\4 $0 $801K $160K $240K 1111111, Equllpirneint IPuirchase Cost Project Total 1.511 $300,00000 $300,000.00 $300,000.00 $300,000.00 $300,000 00 Capital Cost for Budgeted Years 4D � quiprr�ent Flurchase Cu�.A (100%)$� ,500,o0o.o TOTAL $1,500,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 11 . quillpinent Ilau.uirchaso Co%t $300,000 $3()(),(xx) $300,000 $300,000 $300,000 $1,500,000 Totall $300,000 $19)0,000 $300,000 $300,000 $300,000 $1,500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 184 Funding Sources FY2025 Budget $300,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $1.5 IM $0 $801K $160K $240K 1111111111 020 dual stall Ilirm1piroveiment If und Funding Sources 020 Callikall hrnlpirovonicnu I1::wnd Totall Project Total $1.5 IM $300,000.00 $300,,000.00 $300,000.00 $300,00000 $30o,00w)o Funding Sources for Budgeted Years 9 020 Capit.al Irnprov rncnC i:: und {100%)$1 500,i TOTAL $1,500,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 185 Operational Costs FY2025 Budget Total Budget (all years) $75,000 $7 5 IK Operational Costs by Year REM $0 $20K Aninuall 01C eirationall Cost $401K $601K Project Total $7 5 IK $75,,00000 Operational Costs for Budgeted Years 9 Annual Operadoral Cost (100%� $'7S,000.00 TOTAL $75,000.00 Operational Costs FY2025 Total Aninuall 0113cii atlionall Cost $,75,000 $75,000 Totall $75,000 $75,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 186 Ov(,,irvk,,w Owilell, 11 sl.slail D'alr, 11 M. Coiririjjpletlo In 11 )a lc Delparta nell I pYjjpe 1hritervilew ilcmrns I Nail t Rvecdle, Doputy ClhkJ 01,10112027 12/31/2031, lollo� ("allpill'gall II ilill1proveiriloat ird [)c�scirijpfloii � p he pui-dhx;e and iinM.allal,lai i to ain audo and vhkr) Iroac oirdiq,,,,ysteirn for Lhe 8 lird eirvlew roornisoc,fl ed lin, Illnlva 14,,allJoins and 113odking. p 11 le Ipuu1 dhase wl1l hildhAdr, doud storape for. t he rrledla. I Ifttryuges P11", I ktadls 11111'0ed 11,11uln1ser 25 )ID 001 Accoui,A 11"Nluirinbeir (f)1,.6fp.9f),()(1,/09.66".7.099 11:111,oef, O 11ffe 2032 Sustaill lalbllil,y phe finavfew nfied[a wl1111 be,,Lored dlf.rNally lin the doud and I a,equlira Ila °,s ineed foir physic„all dirlves and US111"'i tostoire dhe 11111ledi') (At eqory 709 Noin A Aoriri(Aivo 11 spAlipinneN 11,111011rity 3 nijjpnrlan� S1ralleg1k, Goall thrall 4 11:'airdly 11::irlendly IIJclglhhoirhoods: SMC and 111vable 11 bir A1111 IN 11 li" Grall lt 11 uii lded" No Justification Locadoin Our auirrcnt inve5tiga4:loins, and Boolding, linl.erview rooirin -axoirdiirig systei-ri N Irr,aclhlini, the eild of its Opeimt1ol-KA11 Ilii o aind 41111 need ii oplacei[neint, A 11-11fghquall !I ty 'and W6111 fu If ldl(,:�Illirlg audlo all V4]QFj syAuin [01' rAA I!I l l fS Q[ !I Uca 11 -VCook coijill'y Sl,ak"F, AlA oni ey's Olirice ii maind,.H ; t hat11111 relarly aii iid juvoindc, N I or vi(wsillust heawfio and VkJeo l rcol-ded. 111111 addfldon, d 11 (" 1111 lvos� lg"Alve Sed iOin firequent ly liraalroelllcs hilk,1111 pir ofile videirlit cir limes or cases t 11 laa all e sens!H ive tel 011 le con-in,ni ii 0:y. A in eapar;lr arauadlo al ld Video recoll drA hfl erview k all 11 r""sentlall jji,�aii t d a Successliull arli-i'llind1l flu nvestigat On IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 187 Operating Budget Impact Af�o, the iiriidall jnardhax!, dhi„ cantrao, wflll Ibe foll 5yeai's. p hoolpeii a Hing, hu d gehmflll iiicirr�aso Itayr $75,000 per year Im thelHeart theconhrad. Inflationary Impact rids for Phis pirojerI WHII nolas; a%Jpended uinhll 0hn 2027budgn� year.We exlpecpdhe costof UNS prouect to Ii inrieaj.year own year untill the Stall tW the pirojCcL chrice Uhe piroet N ^:Aairted,wcwilll be Iloc ked hill t ) a set annuall suliscidpdoil cost that willl stay coinsktent over t1he 5 Y(aarsof [he contirarA. Capital Cost Total Budget (all years) $75 IK Capital Cost by Year 9M Project Total $75 IK $0 $201K $40K $601K IV r:::qu.uiilK.airxo int: IKbG.urc.lhuess Cost Capital Cost 11:quilpiircart Purcll iias(CoA TMkt all Capital Cost for Budgeted Years 1111111i E.IquipmenL Purcriase Cost (1009/,) $75,000.00 TOTAL $75,000.00 FY2027 Total $75,000 $75,000 $75,000 $75,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 188 Funding Sources Total Budget (all years) 7I Funding Sources by Year Project Total II $75,000.00 ^.baa $201; $400 un60IK 'N 0011 Ge nein 111 IFund Funding Sources 001 Ga:ncir<all I11::�u ind TotnaalV Funding Sources for Budgeted Years TOTAL $75,000.00 FY2027 Total $ 7`a,i"DW 75,000 $75,000 $ 75,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 189 Operational Costs Total Budget (all years) Project Total $1.501K $1.501K Operational Costs by Year Em KDW $0 $201K $40K $U)IK Aninuall 01peirationall Cost $'7S:,r)00 00 Operational Costs for Budgeted Years 9 Annual Operadonal Cost (100%� $150,000.00 TOTAL $150,000-00 Operational Costs FY2028 FY2029 Total Aninuall 0113cii atlionall Cost $75,000 $75,000 $150,000 Totall $75,000 $75,000 $150,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 190 IIIMdb!He iladllo Ov(,,irvlicw Owilell, 11 sl. CoinillpIkAloin 11 )a Ic Delpartinell I i 3Yjjpe I ,aii t Rvecdle, II oputy CIII 01/01/202 7 12/31/2027 lollo> Callpill"111 II ilill1proveirincint )cMscirijpfloii i he 111611(xnDelpairbrinellik 'nalinGAI Is u flect of 1A uI I used by sworin ,)o-sonnell ilia I.11c I forlinlance of 01171atu1r dufles and 'alre. of H kaAl lin U1 or. (fispal.dilling of sevocr: airld r.Irrlm gn Uro y call Is aild miller. c,"iellikiall rx)ITI rnurlir,aloins 11 1,y 202 7, flh(:. runrell It III mlbi 110. rad o", wi 1111 have, hr, clin 11 In as for irwarly fil H rrin ( V: 10 Years and wdll I Images Dctaik 11:11lojeci11,11urnbor 22 11:11) 003 Account ',Jwifil-ilrnir 020.60.90.00.1.709 668,00:3 11,11rojorl iffe in 2037 SuM AinablIfil'y Uheso 1-nobfloradloswflIll co III hiribule giready V,oL11he c I fer Live I airld ,crvlclii Ig of U1 le colininuinity by einsull hig dfoctive v,cjmi,nunlcdi bin capabdiLles aii 0 ii-nalintafined Category /09 '40111 A1,1WITIOUVC ::qlAljprfvnnt 11,11-iorhy 2 Vr,,iiy Il iinjj.,joirla1n4 Sballcqllc Goall (,Oall 1, 1 Village Govein rcn)ei It.Hinancially Sou.und Il A,f,,,jij4.iloiia11 Seirvlce k� I'llhis Graint 11:unr3r d? 1f) Justification LocalJoin Addii css: 911, Fasp KonvdngWin 111road o i onl1Y a re 9a ur I -no L -u i 11 aa ara d 10,--, rn a �r� 1111 i 11 h C; !111' -,u In d 1 (: 111 p a i a d e I - d rp311i13cr,plllra d a i 11 y f t1111 . 11 ni 0 111 i11 ra d i 0 ul n dol, V a 1r'Y !I n P airld (Wheir "i ress Faclors Irequill es Hie fleet ft) Ibe Irepllaaced With updaled IlrOds le 1-111lobile irrarfio IF, n crklcall asped of p I le Ileralhrr? 11 3ejjparhlrieiii S jl[jS,,10jj rfljjjOWIJIg fC)I,r 1,1rqpld dispatcl-liling of T.eirvk,e aii Id eilineirgency calkj. p lI iniodeii n ladlos aliko Iprrarrlide preater officell "allety by aiiell-hing GI's Is unalbIto; Io corn I nlu dcatt e ai ii tt 11 le ii adfo, A1111 INortlhlarrr,,t Calitil-all IID qljat 1: 11h c;ezlrrulrlruu1rn11tles will 11 bo relplad ii �g i I-Ich agh Ig ir"Idio fleci s and w, i 1111 Uraiivi t lai o P o t11 K 11 liewell rad k pu;. 3 11 Ils (�ajpi i all i rlveM in ell It wfll 11 eirialiblo, d w & paill bnri�'Int Lo rolp1l ace ol � I cull I fled r ff 1.6 rnolnfle rarfl(n� and nnalil]Mh I( oinjpal HPlIfiLy vAL11 o t Ih e IWrare.hwost ("einhirall 11 )k1pni dh Sy,,terri IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 191 Operating Budget Impact 1i he projed WHII Cos t a 1131111roxiinately $125,000.00 lo I' the pwircll I asp oi th(a radio Jillts, d0:adl lalble call'iroll hrash, ill v;i.alll a Hon kit arld installalion costs 1,o ii -c 1place 16 uiilt:. c.uui irellitlly^ lin Hic field, Inflationary Impact lo factai for prosslillnlle inrlatiolin cos(s, stair r akulatcda TA co,4 increasc, ior each yewr 1131riar W puilrdllase�, Capital Cost Total Budget (all years) $1.25'1K Capital Cost by Year Ill Project Total $1.251K $0 $301K 4)601K $901K $120K 1101 E.:clullorneint IPuirchase Cost Capital Cost .qu.ulill.aurirroen0Ilsu.uurchaso Cost Totall Capital Cost for Budgeted Years 0 E:qullwnent Purchase Cosa (100%) $12S,(-.)0Q.0C.) TOTAL $125,000.00 FY2027 Total $12�000 $125,000 $125,000 $125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 192 Funding Sources Total Budget (all years) $1.251K Funding Sources by Year Project Total $1.251K V25,000.00 $0 $301K $601K $901K $UOK 0 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Capitall Ilurnp iroveinient 11 wind Totall Funding Sources for Budgeted Years 9 020 Capit.al Irnprovr momt i::und (100%)$125,0C TOTAL $125,000.00 FY2027 $125,000 $125,000 Total $125,000 $125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 193 New I I odlker IIIZoa�'irlll ow"Irvkw kxqfu('d,f Owileir 11 si. Sf "1111 11 �)af C, 11 Si. Coirivillpletion Dale Delparfineii H fy1pe I raii l: fweedle, II ae>pu'dy ChkI 01/01/2025 07/01/2025 lollco ("allpill' all 111rlrolpraaveIrillelyd )eScirilpHolif f he dellwhineiril. i Ilookilillig 4 o I.aaaurdilair" 8, uunAl Ilodkell's ror the inein's Ilandkeir rwrn 'A [he jpcjllkx. s� akfoii ii. I inniages � )eGAIS 11,11 ojed "Wirldbor 25 1111) 003 Account 111uni 001-60 90,00, 1, /0&6 j,3,020 11,11rojefl. Aft, p he II ew acker'; 4111 AA fi)rflhe filfe olf the buildilllip, Category /06 innjpi-(W07101(. 0 lidbfic Biuddlings 11 111-foll-hy 2 Very 111111IIIpOld d1l lit Strategic Goall Goall 1, 11:: ffed.1ve, Vulllhage Govell-ini-nonL: 11 1-1"au"unia'olllly Smind, ll xceplJoinall Service IN flhi,, Cir,-,unt hunded? Vru LocAdoin 911, Las� 11<(,.nslnfjari 1,oad Justification f Ihue I'dice II1epranu brilleirit IIoa, added r1 11 luirikicil oll now ^amoii 1-1 orficell jjxrShJoil', ho 11 ccerlu Years, f IIw dq1jairtivicifl, leeds Lo adid llhese additioinal lockers lin oirdc�r to 111 -led, the dcrinalinu I [oil odkcirr, fair irrialle. sworin of ficers, Operating Budget Impact p the inew Ilockr^u ^, do not have aill oper'Wilig, ;OA and willl i lhnave ally fri-pad oir flhe 01pel[Aing Ilblaulrucl� IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 194 Inflationary Impact 111olle Capital Cost FY2025 Budget $22,500 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $22.51K $c $616 $121K $IBIK 111111111, Ex:jullpimeint IFluirchase Cost Project Total $22.51K $22,500 00 $D000 $.O000 $,0000 $.0000 Capital Cost for Budgeted Years 0 i: . cp..iprnent Purchase Cor.,�t (100%) $22,500DO TOTAL $22,500.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Fqu�lpnneint Puirclhaso Cost $22,500 $0 $ 0 110 $0 $22,11-M0 Totall $22,500 $0 $0 $0 $0 $22,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 195 Funding Sources FY2025 Budget $22,500 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $22.51K Project Total $22.51K $22,500.00 $D000 $D000 $.0000 $,0000 Funding Sources for Budgeted Years $0 $61K IUK $181K 001 I::Urwl (K)0%) $22,500.00 1111111111 0011 Genei[all If und TOTAL $22,500.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 001.E u7,ciralll11:uind $22,500 $0 $0 $0 $0 $22,500 Totall $22,500 $0 $0 $0 $0 $22,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 196 IIINe Slpecii4lllIIIRes�panse Fbarri Squad Car, 0v(,,irvk,w Owiliell, 11 <,Lslairf Dale 11 si. Coinillpletioll 1 )a ic Delpartinell I �Yjjpe 13a ii t Rvecdfe, Doputy 01/01/2025 12/31/2025 lollor Callpill"111 iiiii1proveirileint )c�scirijpfloii � I 111611(xa Delpall'briniellik !,,-, loolking, l'o llurdiaie (1) 1 sqii laid ("aii kw fll le SlIpe(Jall "Ims1poinisp. lbiirn. l hc,IDejjlmrbin�gnL fps hirdlheii Ilnsnlding Or; adid flils vdiln r. l.o lane vehos lo 11, raI-ALH,eirrinintsc I 7rxlule inlideir U le Vrdhidr! 11qp1a(,e1-(le1M III. I fliages I ktaik 111110tec9I'lluiriber 25 )ID 002 043.60.90,00A,/061.660D03 11:111,0�ef, � Lf feh ,vehideW1111 he Aded lo UwNdhk,le andvAll havea 5yeaii opeirai'lonall II' c,Iw,t (Ae�;ory 708 Vell ides/hAornio i ive Frjuiljjpireii ill, 1111110111LY 2) Very rrijlijorl,ani4 /,9:u ualeg1k' Goall Goall 4 11:�xlridy III F"Mr, and Livable 11 bir A1111 Is this Grant Funded? Wo Justification Locationi Address� 911, 11 �asIKon,Ingl,nn III ..... ......... l line 11 loll ii ce 11 k pa irtirile int's Sjpe(,J ',a 11Ilse qjp Oil la „arin !s Lm� I w L III the fnVe"t lgalJ oirli a rid su I foii i of A o 11 eii r0: c ir 1 rrle. � Ilhe Sli I all 11,� e�5 Do inse � ca i roculi^, oil Llirgd ing onforcel ncn� adlon oils vloh-:11 III, halbibiAlIl oll render^,, lune S111ueda11 Ilu,esjjl, oii mle aura Ilna , becin li!y;Illy dreAfve �Ural U1 ifn, 111-ilh'sfoll l, � Ihc Speciall 11"es1poll ise �cain W flizes awir[lii inarked Fquad caii O o roixhxt � hk enrorceinl(.11 0 ad vity. � 11 ic Sperfall 1Pqpon,;ek ol-11 ell 1� Y il'ifillill" a 11 C1 red fil oil] Uhl le jjxlk 1011 vellildc. l 1111,jt vellide I las a 1-1lgll u I lumbel, of lnruullos aii oa3 is lin i of rcjplaceinriein4 , Cure ell ill Ily, � I is SIx"dall Zes1poll sc? �eaill rjoes i havc a vellicle all 110c"Ited 9 oll. It'i au sr,;h o #I NVell lid e 11 1ojplareirneirfl: Il und, Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 197 i1he inwrcll I ase of 111he 111(^wsqu ad car foir UnrSpec i all Pespoinisc iQai-n w !11111 Il1 irn1iroiinrialll all ball'all budgO, 11-rqpar'L il-K' unQWMUad mar WI1111 bQ xJded to thevelticle ill 11 dinr.'Velinlde 11yqplaccrncnl: i Ill ldi1h is VA111 resull I, iiiii a n mldltioinall yearly irmyrnorn: to Uhr, i uind all ow lar ii e p acenneii It of i hr, ve h k:lo ill flw n egulail 5 ye all I - oll Idni le atilolllvelllIirlleopeiraiia:ruoralllliifecydkl p 11 loic vvilll I a inn inni nall oi-xm ani loi oll I iii ninaci aura thc lirs lblic Wall ksvc.l-ncle\&Innteiriaiicr,r Ii und For routhrie inin-annillen a i I levch ide, Inflationary Impact t 11 le wsl, of pu - r 11 io.� i rlp, 11 lew ve IN chn, 11 las i nicireased alipproxi in I a tely 30% slince 2020 . 11i I,, I Ix �d I.11 a(, V61 ide I - k,e, wflll colintill lue Ro lin( i I/Call, OW` yeall- of a higher than finlil-uUloiniairy llevell ale. Capital Cost FY2025 Budget Total Budget (all years) Project Total $64,000 $641K $641K Capital Cost by Year $0 $201K $401K $601K 1111111, E:quilpirrneint Puirchase Cost Capital Cost iiqullpim�t PlAirdl lasiCasi "N eat Capital Cost for Budgeted Years E.:qul�-.wrort Purc.,Ihase Cost (100%,) $64,000.00 TOTAL $64,000.00 FY2025 Total 4 ,�64,000 $64,000 $64,000 $64,0W IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 198 Funding Sources FY2025 Budget $64,000 Funding Sources by Year RM Total Budget (all years) 4I '�IIIIIIIIII� $0 $201K m m' 043 A:.sset seVZV. ire Fund Project Total 4IK $401K $601K Funding Sources for Budgeted Years 9 043 AsseL k>elrurs f::und (100%) ;}64,000.00 TOTAL $64,000.00 Funding Sources FY2025 Total 043 Assct Sel zu rca II'o,and $64,000 °'{;�6d,000 TotaalV $64,000 $64,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 199 IIINe S�peci�4�ty I ocdkers 0v(,,irvk,w Owinell, 11 =,LsIail DaIe 11 sI. CoinillpletIon II )a Ic Delparta nell I pYjjpe I Naii t RvecdIe, II oputy 01/01/2025 07/01/2025 loho> CalIA"111 111IIII1proveirincint )c�scirijpfloii � he 111611(xa Delpall'brinellik !,,-, Iloolldlrot, I Ipurcha'ie 6 ivw �,JpecLALY Raba Ilkeir^s. I lrmages DAIS 11,11roject "Winber 25 1111) 00d Account 111umbeir 001-60 90,00� L/0&6, 3,D20 11,11rojeU Il Aft, p the spechalty Inckers 4111 Il au t loo the IllHe M thir, bull(hing Category /06 Il inprovo,rion(. 0 liilbfic Bijlldlng,r, 1:111-foll1ty 3 lluaru11,1010,11111t Stil atepjk, Goall Goall 1, 11 ffecIve, V!1111,uge Gjoveinnrncnt::Inaincfflly Smind, II xcelpHanall Service Is flhN GiI 11 uaucellaaa't?'I Justification -(:quiir c t11 Ic Iii cor s to ii re add !it k wid1l equ il jjpiTN� ,^ ii i L, Ilauayoiil d 1A KJ I sLaii Wa and 1patii-oll equi pin Ieii It, Officers sture t1l oi5 add of o 11 cxju !I IDii I icii i Lh i tl-wlir "J,-)ecIalty ockei-, VVII ue ll 11 Iriot utflizing it 11111 the field Hhe Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 200 Inflationary Impact Moil ie Capital Cost FY2025 Budget $1.2,500 Capital Cost by Year 2025 2026 vam 2028 2029 Total Budget (all years) $1.2.5 IK Project Total $12.5 IK $o $31K $61K $9K $1121K 111111111 Ex:jufilpirwieint Purchase Cost $12,SOO 00 $xx)oo $D000 $D000 $D000 Capital Cost for Budgeted Years Purcl-sr TOTAL $12,500.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 11 . quillpi-inent I'luirchase Cost $12,500 $0 $0 $0 $0 $12,500 Totall $ 12,500 $0 $0 $0 $0 $12,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 201 Funding Sources FY2025 Budget $1.2,500 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $1.2.5 IK Project Total $12.5 IK $�2,500.00 $D000 $D000 $.0000 $,0000 Funding Sources for Budgeted Years $0 $31K $61K $9K $112 IK 9 001 (::Urwl (K)0%) $12,500.00 1111111111 0011 Genei[all If und TOTAL $12,500.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 001. tncirall 11:uind $12,500 $0 $0 $0 $0 $12,500 Totall $12,500 $0 $0 $0 $0 $12,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 202 mules" mm um uuml uuuumlu uml umi°uuu uuuuu uuuuu uu uuum uuuumul II a u° i, uuuuuuu uuuuuumumI IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 203 Uridergrotvrid 16III Sturage Fairilllk ace rrwnt Ov(,,irvlicw Owinell, Kevhri Della a, vehIde, IncrSupo r Intondont 11 sI. S� "1111 1i tap C, 0410112027 11 sI. CoinillpletIon II UaIc 12/01/2028 Delpartinell I lulbhc wol-11"s tYjjpe Cajj)Uall 111IIIIIpiroveirinefirst: )c�scirijpfloii I ",.ejpkxeiren[ of uindergir('A Ind fiA ,f�oiragc t�,aInlc,. UN', Indudes ex(,avauon of U1 le ourlircint fuell f ink'ss 20,000 U11 Aink and Lhe 12,000 gallon dle,;61 Well [aink, re,Maar x"ri-Iont (A �Vsnr rated)Ijphl,� sIlld 1,0,1111soirm, uscd h) nu)infloii the FJoirngc' taink.n. U Ih e I C0111101,-O.te k fidly irr"Mared and UpgradrA, * 202/1, un II Ir uln aaariiln;, * 2028 ConAinj((Ioin 11 uedl II llairur1 20,OOOT,,�.rlllloi[iu.ii,)Ilf.aded Und(ngirouind stoirage taink 12,000 gallon IDlei�,edl Undcq,,rouind Aoiragc tark, 11uell island 1700WCenhral11eUA11111W Dctaik; 11,11rojerl "Aull'Iber 24 ll>W 001015 Accounu11,kii-rd-wir 001,.80.90.00.1.706 64 9,020 11,11-olod, Ifo 35 W"n1l"S Cat cgory 706 in-Ilprovernei-d Vo lubhr, Buddlings 11,11-iol-ky 3 ii-inipoii Laird, StiraLogk: Goall Gmll 3 ojjp Oualli(yAllage infirwAinwhnro: 111flaii Icedand :Irnad ivp 1,o1-r11rrIIj1`1H Y IIinvi:sAilrlei-IL h, this ('1-111 -It 11uii Ided? I Locadoin nN Justification Hie UsU ,� earl eoll ogInzfll and weire lilri,,t illcd in 1985wW o a II He expectairm'y W 3OW40yearj, In 2028,flhe fuell lainkswH11 I onthelir 40 -year fitc cyde Sull I-OundIng sell aII Id pIlArig have ,Iginirlcaii III conrrx,ioii ii sind he conurde eirdbodded udfl y 11 de. aii e, also detuirioirated aii iid willll need 11 el"AxelArIend, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 204 Operating Budget Impact I the ineed W Ihirave ouir own ruelhiig,,U-aUain wit1h avallab1fity to purdhose Nell iii -ii Ibuallllt save , Ihe VfllaWc noiney. Additionally, 40yQors of service, of Uhc, curreld kiliks ha�; exror"Ind dh6i, hic oxlpertaincy. Inflationary Impact Inflation ofirinateiriall" and alpor W11111 4fe(A, 01he rwoalll rmcrmwcan prop(,.rt 11 s!rnflcs are II pias cd on dic c uiru enV i inaii pr1r.cofthe projei:� Capital Cost Total Budget (all years) Project Total $ I.. I. M $ 1.1 M Capital Cost by Year 2027 $ioo,000 oo 2028 $�,000,000oo $0 $2501K $500K $7501K $UM 11101, Construcfloin Cost 4k Des�gin Eing�ineeirling Capital Cost for Budgeted Years O construction cnsl- (Wwc$1,00o,C)00.00 Design Ergincorincj (9%) $10o,000.00 TOTAL $1,100,000.00 Capital Cost FY2027 FY2028 Total Desigin li ingincul-hiq $100,000 $100,000 Conshructloill Cosf$I,000,000 $1,000,000 Totall $100,000 $1,000,000 $1,100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 205 Funding Sources Total Budget (all years) Project Total $ 1. 1. 11\4 $ 1. 1. M Funding Sources by Year 2027■ $mo,000no $0 $2501K $500K $7501K $UM 0011 Genein all IFluirncd Funding Sources for Budgeted Years 9 001 Coneral I:::Urwl (K-)0%) $1,10o,o00.00 TOTAL $1,100,000.00 Funding Sources FY2027 FY2028 Total 001. Gencirall 11:,:u ind $ 100,000 $1,000,000 $1,1.00,00o Totall $100,000 $1,000,000 $1,100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 206 V'iI�lIlage III'°°°IIeet Clh�arg'�iing StatliQnls Oveirvk,w 22 1W OW94 11"'equosi Ovvilell, jx�oiri 11,611b, Il r¢eppua0ylDliredor olf lublicWark", 11 )ell pa - bil r i lulbllc work's lypo Calpif all filillpiroveirillellf [)c S C 11 i 11: i 0 In hrlsllallatfoin of C1111'arghl"g stitirrilir, at Vf1lape f.wlliIfos fear t the dharpjins of rderbi ic vd-Ildo'", illi 11,10, Vill kage flee L I innages IIIIIIIIIIIIN 11,11-0ject iquirdber 22 1W OW94 Account Numbeii 02(X80.90DO 1-106,649D20 11111-rjject Life 20years Category /06 inpiroveineilt I:r,) 111UL)Ific lei luflkiiiig� 11,11-1011-ity 31 Inl-mirtant stirategfc Coall (aoall 3 lop-Quall Ity Villageirfilrasbructure� 11"allairiced and 11 liroar1lve ('aii-Iii rluii iiIty 1111 veqAriveirt Is t1l if,, Graint ll Irn Ided? No Justification As ededrk,. w1h i desiwcoirrivava !III a L -4(j fol[ f I eM use, Ill-revillageas !111111 ki lhsu all 11 LIN -2 rccassa I, Y ill ]If raslirud,� I ire low1ppold deOri( volhides, f I a i w1:)1 -1r III (Jectiricall i-nochilwaLlon, a I. (he Villi agin'facllilfes to �,wjrrjport (he frl-,oll Ila lJoiri 0111 swell Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 207 Capital Cost Total Budget (all years) $1.001K Capital Cost by Year RM Project Total $1.001K $0 $2SIK $501K $751K $1001K Enquillpirnent IPa.uirc lhase Capital Cost 11 . (Jullpirincint 1131 irdl mse CoM Total) $i00,000.00 Capital Cost for Budgeted Years TOTAL $100,000.00 FY2026 Total $100,000 $ 100,000 $100,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 208 Funding Sources Total Budget (all years) ..A. IK Funding Sources by Year RM Project Total 1.IK $0 $251K $501K $7SIK $1001K 020 C ar itaal Il ir>rn;piroveiry" irrt: IF:aairnd Funding Sources 020 Caaplitaal hirnpiroveinient. I wind Tota ll $=,000 00 Funding Sources for Budgeted Years 9 020 C;::zapit:al Irnprov rncnC i::und (100%)$100,0( TOTAL $100,000.00 FY2026 $10 0,000 0 $100,000 Total $ 100,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 209 Operational Costs Total Budget (all years) Project Total $21K $21K Operational Costs by Year RM $0 $500 $UK 51K $2K AnInUall Olpeirafloifmll Cost $2,,000.00 Operational Costs for Budgeted Years 9 Annual Operadonal Cost (100%� $2,000.00 TOTAL $2,000.00 Operational Costs FY2026 Total Aninuall 0113 `ii atlionall Cost $2,000 $2,000 Totall $2,000 $2,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 210 SII Immp n.. um�m uuumuuu uuuuu uumm�l uum uuuumu uuu � Illu llll�l Iluuul u... um�i° III Illw.. um�m�0 uuuuu uuuuumm� Village of Mount Prospect I FY2025 Community Investment Program Requests Page 211 VIII ridlk,SldewaIIkMafinteinwl,ice ile io°ilwva �IIIIVlellll aiiurnuleiinlt 0v(,,irvk,w Owiliell, So"At Mrx,, shreeL,/113 I A(Allig Supe I, � I, itoldold 11 )ell �a - till[ wil S� I, eets & Bu ill difiril"S �Yjjw Ca; jjpil.,a11 II illipiroveirilicid [)CSciriptiolin F1'e1Ar1oVc,)11(f 11-oplace die Ilairifdksidewallka; lin wid airound 1.1he IfDowrltownarcm . I i 1113irldc qd(wflk 11 X�taik Category 1:111,forily Stirall.eglic Gmill IN 111 Ifs Girciirit 11 i1i'llinfled7 21 II1W 000/8 049,80.90.00 /0'),6/5.00/ 20 years /05 11/cswrfadii lglCluirlbs & Glu i'llers/Ndew"flIk", 2 Vory 111 iii1portaint Grmll 3 pojp-Qtlallty W111bge 1111 lfi,aSbri,ichjreIi,;"Al linced and Caii-iii-iiiii illy llii vc�d i H No Justification p 11 w Vfllagre",; If oi,pwinowin airra,,idvvwfllk�, aim p6nrlarfl(Ili sins»talllled oveir a decade ago ai 0 as Sudil ai,r � ill 1 11 lool aaf a kwger n,calo d rn'llinteirlidl-WC. Hie jjjirogirail[o ill die reliflovall mild lelplaceincri. o[ llanicks il lal, havedelerforated fu orlu the bot(orin -r, a i 4dilloilide use, illus causkig 11111 lev(N u walkill 118 Sull fxeandaii u urrlp1l fly ajjpjj�K�airarwc, * 2025 11 a,;t:,;fdc of 11�ii,iorsoii 11 firoll'.1 ljoirdhvve�,A F W( to Ceirif i * 2026 Noii tlhweM 11 W` firain 1111no116 Ceinbrall * 2012/" Wr,M.:Jde of 11 orrue irson fir 01 -in 113m, e to Coll lbroll * 2028 Korllbodlrfde�, 2029 11 aM:sldeaflGN 83firari Illwu,saalloCenb-d Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 212 AnIJ611lraLed cosil. savfirigs, du"^ to coliverAflig I roill-11 col-licircte biftk I'o day hired birld< i s exlpected UP I ha, !Ice as unig, givell I N's res !Is I'airwe W chloride. Capital Cost FY2025 Budget $250,000 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $1.251M $0 $60 1 $1201K $1801K $2401K 111111111 Constnxtloin Co.,t Project Total $1.2 5 IM $250,000.00 $250,000 00 $250,000 00 $250,000DO $250,000DO Capital Cost for Budgeted Years 0 Consti,ucLion Cost $1,21.30,000.00 TOTAL $1,250,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Coil �s tir [xiJoil 11 5r' $250,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 Totall $250,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 213 Funding Sources FY2025 Budget $250,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $1.251M Project Total $1.2 5 IM $250,000.00 $250,,000.00 $2SO,000.00 $250,000 00 $250,,000 00 $0 $60 IK V201K $1801K $2401K 0011 G: eneirall If und 40' 049 IProspe ct IMaailin 11 H:: Fund Funding Sources 001, Gencrall 11wind 049 Piro,,11pcct Mahn i 1111� IFuii ad Totall Funding Sources for Budgeted Years 9 001 Conera I I::: U ryl (20%) $250,000.00 411, 049 Pmspecl. Main 1111 L and (801k) $1,000,0M TOTAL $1,250,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $,4000 $50,000 $4000 $�)0,000 V10,000 $2�D0,000 $200,000 $ 200,000 $200,000 $200,0010 $200,000 $1,(xx),()00 $250,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 214 II""Ihre Sl'alikxn I I IIV° . IIIile p ace iiilrwie rit 0v(,,irvk,w Owiliell, 11 si. S� "1111 11 �)ap C, 11 si. Coinillpletion 1 )a ic Delpartifir'll I IYjjpe )c�scirijpfloii � ",.einlfflove fiidl rqjpl;Hx; the roor lifHirc, Sa� ffil ]I 1A. I I So"At MoeShred =,/Blulkh iig Superil'itell idell H 0510112029 06/29/2029 sh, e0s &, 111,11,01diling's ("allpiLd hilliproveirilleird SUAlon 11, Dctaik S4 )l loin 1,11 rool' 11111'0ted I'llumber 25 II)W 00002 11:111,0aef, � Iffe 2049 sist jalinc)Iblfil,y malillainhiligUlle -00l:,AaVl1k)greN lad1hyfS eirltiall hill keepling i1he of rellvAir a t r'g () 1-Y 706 in lubfir, I'mildlings 11,111011,fty 2 Very iniporl,anio 5,0 rallegrk, Goall GoJI 2, �ojp Qlmflly vlll,�)ge nfirashrud uire� 111allaniced and 111i[ oactive Conninnuinity invffsbrnenu IN d 11 li" Gir all It 11uii ided" 11,41) Slal,foin 11,irool[2 Locationi .... ...... P - Justification 1131'dding Ru(Jfirfdbgy coll I suhzu lit 5, 11111 C. (113 Q Ila,, jpa:rfoiri-ned,,ubu !III dhlr,,,onclosuim ;isse,�Silieii lit 0111 thc fere f ciiiced III !I IT a nd recommenrJ thattlic rjo[ I i lino 3 1r) ". ye"I I'S 'aS die i ui !I inv idwond of ods usefull 11 !1 [e. Operating Budget Impact ll,lanicaiuthis Urine. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 215 Capital Cost Total Budget (all years) Project Total $5251K $5251K Capital Cost by Year 9w $0 $i501K $3001K $4501K 111111111 C.,onsLructlan Cost AS IDesiigin Einqfiinociring Capital Cost DesginE11-11gr'llinpol-111118 Cont onstiructloin cos� Totall $525,00000 FY2029 $25,000 $`:woo,000 $525,000 Capital Cost for Budgeted Years 1111111, Consuuc�.Jon Cost (95%) 4�)0 1)es~ gin I nginee6ng (SlYo) TOTAL Total $25000 $500,000 $525,000 $50c),000 00 $7,""000.00 $525,000.00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 216 Funding Sources Total Budget (all years) Project Total $5251K $5251K Funding Sources by Year INIM $0 $�SCIK $3001K $4501K 0 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Callikall hrnlpirovonicnu I1::wnd Toulli $525,,000.00 Funding Sources for Budgeted Years 9 020 Capit.al rnprovorncnC i:: und (100%) $525,0( TOTAL $525,000.00 FY2029 $525,000 $525,000 Total $525,000 $525,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 217 VIII ihre Staflkxarm it IIIIEIIlathiroanri Oveirvk,w Arroepoar> p, Owner 11 )ell a r tilliell a Y11 w [)CScrilpfloin 111, r,, ifir ii or] ell il i, og o f Nf ii u ir P. x i I ii ii b';I a [ h i, o o ni, I innages 11:'Ire Y:aPloin 1.2. 1131a� hiroorin 111,eniodd1 Cqjpil-a11 kinpiroveirinent Locadoin Justification 11:1111esMtlon 12 a,.Aien,m,drflr.NJ 40003�iind,glvein the heavyuseafflie h(TI(les, LheyxeinowM LhceiidrA Lhdii useliull fives As I L11 le lennoddl wflll !I nr.dude ncw hxhire,i1boi-, Ili f,,I I U! ing, o tc, 2027 20281 Operating Budget Impact Norio ,fl: Hik Hiroo. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 218 111110ted 11"'Ilumber 19 II)W 0006d Accoui,A 11,11wrinbeir ,roec�II fre 20 Ye,,)irs ("c tegary /06 Il irinprovernent W 11)idblk, 111,ijildlings 11:111,foirfly is llivjjpoidun� StiraLeg1k, Goall GoAl 3 1011p Q13,4111 uy V!11,mu 11111,11'a'All wbuirr",: Mlaiwedl ;.-md 11111,0,"adlvp. 11F, lI GraiN I Yes Locadoin Justification 11:1111esMtlon 12 a,.Aien,m,drflr.NJ 40003�iind,glvein the heavyuseafflie h(TI(les, LheyxeinowM LhceiidrA Lhdii useliull fives As I L11 le lennoddl wflll !I nr.dude ncw hxhire,i1boi-, Ili f,,I I U! ing, o tc, 2027 20281 Operating Budget Impact Norio ,fl: Hik Hiroo. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 218 Capital Cost Total Budget (all years) Project Total $1.501K $1.501K Capital Cost by Year $0 $201K $40K $60 IK CcnstrLJCT101fCO t: Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� $15C),C)00.00 TOTAL $150,000-00 Capital Cost FY2027 FY2028 Total coinshrur"11101111 Cost $75,000 $75,000 $1.50,000 Totall $75,000 $75,000 $150,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 219 Funding Sources Total Budget (all years) Project Total $1.501K $1.501K Funding Sources by Year Em 2028 $0 $201K $40K $U)IK 020 Calpitall 11 irnlpiroveiry"int IFLAnd $7S,000 00 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovcrncnC i::und (100%)$150,OC TOTAL $150,000-00 Funding Sources FY2027 FY2028 Total 020 Callikall hrnlpirovonicnu 11::wnd $75,000 $75,000 $1.50,0oo Totall $75,000 $75,000 $150,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 220 II iiihreSl'alikxn 1 2 Gerwrator ite ace iir'ilw nt� 0v(,,irvk,w Owiliell, )ell pa - til 11 wil pYjjw )CSciriptiolin F"elplace Ohe gen ueusuOxanr il, 11 fire St sidoini 12, I inniages 11Ire Station 12 Geirier,,fl ar So"At Mrx,� shreeL,/113 I A(Allig Supe I, n I, itoldold S1 I, eets & Bu ill dii-il"S Cajjpil.,a11 hillipiroveirilicid 11 X,taik 111110 l, 23 II)W 00; Accoui,A111wri-illbeir 020.80 90,00,1,/06.648,020 11111'0ed IIffe 20yeains SluT,[all1s111bilily 1lee 1pIx ,ing 1,11 le .,e.A irlei,�oir WfIll re"11a1H iun fewell rcjxails and fin creass reliabililly, C,fl egory 706 innijjpi-OMI]Cllitio 11aulblic 113iAldings 1:1111011rity "', 1111'njparl,,'11111� sb%rope gk: Go�jll Goall 3 Rq) Cjua F uy Vii lageIliad rastrudiiiie: 11141anced ,,Ind lromive Col-11111i'lli.A1111HY inivestivolill, 11 dlhis Cir;,nnr 11ljinidled1 III Locadoin Justification p It e ,31: IIre St,Aicn 12 w;�us hi stallkd in 2003 ai d 11 a.,,; renis l led 1:11 le eii HI oli It:,, i neliull lfcr, Operating Budget Impact 1140111le <fl: this tillile, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 221 Inflationary Impact matell1all cr)�,ts condinw, Uosc, As such, dhp bijidgr�t Ihas, been hincii omed Iiby 5W, Capital Cost Total Budget (all years) $78.751K Capital Cost by Year Project Total 78.75 IK $78,750 00 $0 $20K $40 IK $60K CMWRJCTJ01[1 COSt Capital Cost Coll -VAI[ lwdoin COM Totall Capital Cost for Budgeted Years 111111111 ConstructJon Coct (1010,11o) $78,750.00 TOTAL $78,750.00 FY2028 Total $78,750 $78,750 $78,750 $78,750 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 222 Funding Sources Total Budget (all years) $78.751K Funding Sources by Year Project Total m IK $78,750.00 0.00 'N 020 Caalpita 111 llir>rnl irov€ irrrn€ int: IF aiiirnd Funding Sources 020CallukalllIlurnpairovn°utucnu II:'u.uund 1VoullV Funding Sources for Budgeted Years 9 020 C;:apit:al Irnprov rncnC i::und (100%)$78,7` ( TOTAL $78,750.00 FY2028 $7a3,750 $78,750 Total 78,750 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 223 II iiihreSl'alikxn 1 2 itIIIIV°leIIIIVIIIace irwi e rit Ove,irvkw kx'cpjos0Owiliell, So"At Mrx"i shreels/113 I A(Allig Supe I, roto oalm;;^u"o4 11 )ell a - till[ wil SI, eets & Bu ill dii-il"S pYjjw Cajjpil-11 hillipiroveirilicid [)CSciriptiolin selArlove')II11d 11-oplace die spa LI-00fgar lHirc SLAlon N12, Melpiroposed in In 202o ra, cr,,,rvddci,,�Alclin in 202P, I i 11:11,eSta1loin 12 l NA41S lirojed 11"'lluiriber 20 II)W 0005d Accoui,A 11",11wiri-lbeir 020.80.90.00.1.706 646,001, lliojodLife, 20)(caiis Ce ,)� gory 706 innjp-0V(T1CI11t0 11)ulblic Duildings 11:1111oirill'y "', rnjpoirl,,"ull� 5 i Gm; ll Goal 3 pbjjp Quallily Village infirash Ild ure: Frdanced and 11111rfvld ive Coli'llili'lli.A1111HY inivestirr[olill, IN flfli Gil 11:�iAnd(xP No LocalJoin 41. V11 ­ Justification 11 lire Station # 1.2 was ast minodded lin 2CW, IindicaLill q; the iHe W fll le 11 oofwi1111inieet/exreed ut.° useliull ife in 2024, Rejjpk-iciii - of U1 le ii rx4 is e,,sr;^l 0&0 to Ilrmre 1p the fticility hi it good i ej',wlr� Operating Budget Impact 114oii(s sl: U1111is, i'llille IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 224 Inflationary Impact Materiall and Illsslbor costs have iiincireased signffwainfly,As lrpa it hu1dlinj, iria4fleinaiicc coiw;uh a rik, 11 -nor rqplaceinwin aveirage$$,15 Ix it squaire rom. r he ii oo I For statioin 12 Is aplpii axInwkely 9000 oi, ain estimalled cost of $405,000 Capital Cost Total Budget (all years) $4251K Capital Cost by Year RM Project Total $4251K $4�2.5,000 00 $0 $W1K $2401K $360K Constructloin Cost 4C."onstructlon IE inglineeirling Capital Cost C I onsbrucholin Cost Totall Capital Cost for Budgeted Years Constl`ucLion E.�nqhnooring (5%) $20,000.00 TOTAL $425,000.00 FY2028 Total $20,000 $20,000 $4Q),000 $405,000 $425,000 $425,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 225 Funding Sources Total Budget (all years) $4251K Funding Sources by Year Project Total $4251K $1'a.5,000.00 $0 $�201K $2401K $360K 0 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Callikall hrnlpirovonicnu I1::wnd Toulli Funding Sources for Budgeted Years 9 020 Capit.al IrnprovorncnC i::und (100%)$425,0 TOTAL $425,000.00 FY2028 $425,000 $425,000 Total $425,000 $4,25,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 226 II"°Ihre Slalikxn1 3 A�p�paratus 0v1,,irvk,w kxqiueOwner 11 )ell aa r til 11 wil pYjjw [)CSciriptiolin F"erlinisIl I Ohe -I jjpjpa)11',�Hw; floo I, a L H of skaUai 1, 13, I inniages 11lre St 13 All rlrx)ii- Scott Moe�si,qpc I, lintelindeld SI, eets & Bu ill dlings Cajjpil.,a11 kinpiroveirincid 11 X�taik 11111'0ao d, 25 II)W 00005 Af,counF: 111wrinbeir 020A0 90DU 1,/0&6!A001 11111'0aed Iffe 2044 Category /06 W 11)idblic 1131ijildlings Feu -forfly 3IT11113010',Nd StiraLeg1k, Gmill (.1oAl 3 pojp Qi.,alliuy Allage Illnllraanpu inctuire: 11 ;akiii wed and II liraad ive CoirnirnuinHy II invesbilneilL 11 s dhN Gir,,3int hundled? 111,110 Justification p he �aJpjjpargltus flooll, N st�l I, UIV, O,o [aail, roquhrhng ut M llbr, Irefini,r Ihed Operating Budget Impact Nai e A 1:11 iil,, tinne, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 227 Capital Cost Total Budget (all years) $1.501K Capital Cost by Year INIM Project Total $1.501K $0 $401K $8(DIK $1201K 0 CcnstrLJCT101fCO t: Capital Cost coinshrur"11101111 Cost Total) $1S0,000.00 FY2029 $150,000 $150,000 Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� TOTAL Total $150,000 $150,000 $1�ic),C)00.00 $150,000-00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 228 Funding Sources Total Budget (all years) ..A. IK Funding Sources by Year Project Total 1.IK $11S0,000.00 $0 $401c $80 IK $iretlK 'N 020 Caalraita 111 llir>rnl irov€ irrrn€ int: IF aiiirnd Funding Sources 020 Caaptlitaall Ilurnp iroveinient. II wind TottalV Funding Sources for Budgeted Years 9 020 C;::zapit:al Irnprov rncnC i::und (100%) 150,OC. TOTAL $150,000.00 FY2029 150,000 Total $150,000 $150,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 229 IIIICIIIII Slalikxn 1 4, IIIIII Area Paiintfing 0v(,,irvk,w kxqiueal Owineir 11 )ell pa r til 11 wil pYjjw DcSorilpfloin 11 lire Statlion 1Aajj')jw1'ab.is 'Irmir wall 11 jaalnUing. I inniages 11:'lre Station a1ppaira4:u'I'; flooir Wall ll l NA41S Scott Moe, Si"qperlintelindeld SI, eets & IBa.0ddling's Callpitall II ouop:proveiruoaau"d 11,11rojed 11"Iluinber 22 II)W 00092 Accoui,A 11"Iluirialbe1r 020.80.90.00.1.706 648,020 lliojodIffe, 15 "(cail s ca�egory 706 inajp,OV011011t� 0 11)ulbfic Duddlings 1:1111oll1LY ', 1111'njpoi'Lailp 51 raLeyjc Goal Goall 3 pbjjp QualHy Vlllage infirashi ud ure: Frdanced and 11111rfvld ive Con[lilr[ILAInHy 111nvesbrr[oll IN flfli Grain11:�und(xP No Justification 11 lire Station 14 was caliristii uct(A i ii 1120 10 a ind J! rurea 11luaruii 111e.al;alralradllIsflbol, Wa 1111k, 11 uavr, ii u�(A lx.(.ii n pai ii fted A', r;[ x:11 111 �c vv, 4115 are 11 rk 11 Ic'ed A� l p fng to 11 ralaelptIhe"t:rr,trtuare lilI a *'Ke of go(A 11-op"d r Operating Budget Impact 114ll)1111(� �A Uills Llinle IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 230 Inflationary Impact Mage riall co^,ts contlinw, W rkc, A,, such, U1 ae Iluisi,4,,rt has been incii oa,,ed Ilby 25%. Ill oowin quaidfl,y 1based oin prlCai n?, irecoivrT,A 11:111 C, Sdfl lon 11, which is fornpall all sIle in slze Capital Cost Total Budget (all years) Project Total $43.351K $43.351K Capital Cost by Year RM $0 $�21< $24K $361K 111111111 Constructloin Cost Capital Cost Coirv-&rucdoin Cost $4,3,3!..;0 00 Capital Cost for Budgeted Years 111��Jii CorsLruc:tion TOTAL $43,350.00 FY2026 Total $43,350 $43,350 $43,350 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 231 Funding Sources Total Budget (all years) Project Total $43.351K 4ml Funding Sources by Year RM ^eta $¶21K $244 $361K 'N 020 Caalraita 111 llir>rnl irov€ irrrn€ int: IF aiiirnd Funding Sources 020 Caaptlitaal hirnpiroveinient. I wind TottalV Funding Sources for Budgeted Years 9 020 C;::zapit:al IrnprovcrncnC i::und (100%) $43,35( TOTAL $43,350.00 FY2026 Total $43,350 $413,350 $43,350 $43,350 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 232 Illll ihre Staflkxiri 4 IlllElINAClller IIIIIIII ilii VIII iiiii iiu I VIII ilii iiur I iiu l iiu I Oveirvk,w kx'cpjor dOwileir So"At Mrx,, shreeL,/113 I A(Allig Supe I, ii I, itoldold 11 )ell a - billell 5 I, ects & 11 ,Ili ill dlilj,S pYjjw Callpil'all Iluuup iroaveiruua=u'ut [)CScriptiolin exierior I I innages 11:Ire Station 1.4 IBuuder 11 Aiddill III Aalii Itell ance I NA41S lrojod 1114urril.,x.�r 20 W 00WA Accouiql: 1114wirlibeir 020.80.90.00.1.706 648,020 llirijodIffe, 20 `(caii s C a e ;0 ry 706 ifingpraavntnn0int 4o IliAblic BiAlldlny,', 111111011rity :3 rnjpoilain� 5tI Goall Goall 3 pbjjp Quallily Village infirashi tld ilre: Fajbjiiced and 11111roadive Col-11111`1111LAInHy inivrSbrineilli k, dhis Glrailnt 11Ijill&d? No Justification IVa !In tahilling i'lle Vill age's �acflltie5 in a state F'A good i cjjp,dir is III ib i I iAlinfi, airid/fii ci4eindfingthe !I I � wx�full 11i Ile, leirfol-111-11 !III Ig 111-liscollancousrepahis a Ind I I. he,,bnv.L I'll -¢:Willl I - event lon. Operating Budget Impact None al� t hills Liiine. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 233 Inflationary Impact i'llho ro"t o irpnaUrdals Iia,, increased. Asxlh, 5% 1111w, Ilan,vin added Hca dho budgrL Capital Cost FY2025 Budget Total Budget (all years) $28,875 $ 2 8.87 5 IK Capital Cost by Year 2025 $0 $81K Construcbion Cost Capital Cost ('oinsbl u(1 !I oin clos� Totall $MK $24,K Project Total $ 2 8.87 5 IK $28,875 00 Capital Cost for Budgeted Years 1111111111 ConstrucLion CoSL (10/0'W") $281,87S.00 TOTAL $28,875.00 FY2025 Total $28,875 $28,875 $28,875 $28,875 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 234 Funding Sources FY2025 Budget $28,875 Funding Sources by Year REM Total Budget (all years) $ 28. 5I $0 $81K $MIK 020 Calpitall irnlpiroveiry"int FLAnd $24K Project Total $ 2 8.87 5 IK $28,87500 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovorncnC i:: und (100%) $28,87 TOTAL $28,875.00 Funding Sources FY2025 Total 020 Capitall hirnpiroveinient 11 wind $28,,875 $28,875 Totall $28,875 $28,875 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 235 Illll ihreStatlkxurm�i 4 IIIIExterllar Pa'iIinCling Oveirvk,w Owilell, scq"ilAMrx,, shreeL,/113 I A(Allig Supe I, � I, ltxnldod 11 )ell aa - billell 5 I, ects & 11 ,Ili ill dlilj,S aYjjw Callpil'all Il ilillpiroveirillent )CScriptiolin :Ialnu alll exterior surtimes o11:'Ire St at ions 14 dllalalre noll, Ibriick. I innages 11:�Ire St:aPaIan 1.4 II xl.erior 11:1alinding �1 )(AaHs 11111'ruga d 11"'Ilhilriber 20 II)W 00060 Accoui,A 111wrilillbeir 020.80 90,00,1,/06.648,020 au oec� II ire 10 Years ("ategary /06 Ilinrolprovernoit W Iiaii.tlhlliia 111,ijildlings 1:111,forily 3 llinngtarrrlain� Stirall.eg1k, Goall Goall 3 aOjjp Q13,4111 iY V11111al"u 11111,11'a'All wbuirr",: takmicedand 11F, llh!�, GraiN 11I,inded? Ill Locadoin Justification rair -Tlairltaiiflii,; U1 le sl,ii udin c ill n a sl:,fl e of good a elialraild hellFr, t:o1jileveirit lorrat icilaild, He(Abhe Operating Budget Impact 11,01111cat I1111if, tiline, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 236 I IIhe cwA of rriaU,,�1,11,311s has ui ir,ieas,,dAs sawlh,b% II as Ilroo n addQd W U ic Iruadc,O, Capital Cost FY2025 Budget Total Budget (all years) Project Total $46,200 $46.21K $46.21K Capital Cost by Year $0 "$12K $241K $,%.K 11111111, CoTrost rW.1101r) COSt Capital Cost for Budgeted Years 9 Construction (100% $4(,,,200.00 TOTAL $46,200.00 Capital Cost FY2025 Total ("Onsbructiol-11 Cost $46,200 $46,200 Totall $46,200 $46,200 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 237 Funding Sources FY2025 Budget $46,200 Funding Sources by Year RM Total Budget (all years) $46.21K $0 $12K $241K 020Caa raita:nl 11 ir>rn irov€irrrn€int: IFaii irnd Project Total $46.21K $46,200.00 Funding Sources for Budgeted Years 9 020 C;::zapit:al Irnprov rncnC i::und (100%)$46,20 TOTAL $46,200.00 Funding Sources FY2025 Total 020Caaptlitaal hirnpiroveinient.I wind $46,200 "46,2.00 1potaalV $46,200 $46,200 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 238 VIII°°°°11111 ilii iiur ilii lull Society Canriqpus Ove,irvkw kxqiue, Owner 11 )ell aa r til 11 wil pYjjw � )CScirilpfloin Scott Moe� shre(l ='/11"Iuflkhii 11g, Si"qpel1intell odeii d SI, eets & 1134,61161ing's Calpitall II uuop:olroveiruoaau"d Pie 11 ls[orllrall 3 thok'Ae aireiin ineed MM * 2025 Sd1 iiooll II Now&Wo� * 2026 Ilraflaur,eunn g,nn� * 2097 Musminn fJdkit,-, o 20281 IYAlu.uscu,alrlruskHrip a 2028 II 1,bg,1ksi'nH.11r1 Sholip IiwR )of 116 Museurn � )Ct'Als Schooll 11 bu'e lrojerl '4urnbo.ir 21; NV 00003 Ar:rounp',,hjirrflbeir 001,80.90.00.1.706 651.001 11111rojorl Life 2045 SuMahnabdfity Ity provli6ng in,flink.�naincpwoii k 011r, lnjdkflilgc, will Lw kepil hill a �A:atc ogood 11 n1pall- a l egf 1-Y 7061hnjpr0V01'101'fl 111111011-hy 2 Voryhinpoii Qain� St ra[r.,gk Goall Goal 3 4(,7j1j Qualk(yAllage 11 tallaii �ced and liraadive Coirrinnuirdty 11 nveA Ineii 0 Grall �t :u11 �&(J? Nh) 11,11ad'sinnWhi Shrip Location Justification Uhipoing,ofing irnainter a liced the facflfidc�� !Is(S',eirfl,Aall hiri IlDir eve n0nrAflheiin firaii[ii find heir dek,,da, atA ai� Operating Budget Impact Nlane at t his Horne IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 239 Capital Cost FY2025 Budget $30,000 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $1.,501K Project Total $1501K $30,00000 $30,00000 $30,000 00 $30,,00000 $30,00000 Capital Cost for Budgeted Years $0 $81K $i61K $241K o11111111 consUucLion co'.: (100%) $ISO,1)00.00 111111111 constructioncost TOTAL $150,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total coinstiru(1 �oiri Cost $"3o,000 $130,000 s3o,000 $3(),000 $130,000 $150,000 Totill $30,000 $30,000 $30,000 $30,000 $30,000 $150,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 240 Funding Sources FY2025 Budget $30,000 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget ((all years) $1.501K Project Total $1501K $30,000.00 $30,,000.00 $30,000.00 $30,00000 $3o,00w)o Funding Sources for Budgeted Years $0 $81K $GIK $241K 001 Gei'ieral f::Urwl (ID0%) $Iso,000.00 1111111111 0011 Genei[all If und TOTAL $150,000.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 001. Gencirall 11:u ind $30,000 $30,000 $30,000 $30,000 $30,000 $150,000 Total) $30,000 $30,000 $30,000 $30,000 $30,000 $150,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 241 Operational Costs FY2025 Budget Total Budget (all years) $7,500 $ 37.5 IK Operational Costs by Year 2025 2026 NOON 2028 2029 $0 $2 IK $41K $616 1111111111 Aninuall Olpeiiafloinall Cost Project Total $ 37.5 IK $7,500.00 $7,500.00 $7,500.00 $7,S00 00 $7,500DO Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $37,500.00 TOTAL $37,500-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Clos% $7,500 $7,500 $7,500 $7,500 $7,500 $37,500 Totall $7,500 $7,500 $7,500 $7,500 $7,500 $37,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 242 IIC�)�rogrann 0v1,,irvk,w 11"'equosf Owinell, )ell a r tiniol lypo )CScrilpfloin Fl,elplaceincii H of 11 WAC unks, w, ineeded, I nages WA IIre1jalkxornoi 0,lirogr�,wn So"At Ir oe� Shred s/1131A(Aii iig sujperfrotxn odoi H 5 I, ects & 111,11jildfil q�,,s Cajjpil-11 kinpiroveirincid Justification Locadoin ex poa;u re, c) 11 ouI ve 11 oti 'A 110111, a 1-11611- Ili fc (..Xl xr, tanry is 5 11 ii teii due k' 11 oin ru oll operatlon aii 0 11 oan ,A o cinvil, 01'11111c.^nts * 2025 * 2026 11 OC holler Fystoin * 202/ A N I * 2028 * 2029 11 OCchilleir Operating Budget Impact Nolle "fl: Rhis Hi rle INVillage of Mount Prospect I FY2025 Community Investment Program Requests Page 243 11 11111'0�o,d, 21, II)W 00066 Accoui,A111uirirflbeir 020.80 90,0(),1,/06.6!)1 0110 ,roaecf II fre 2( Ye,,)irs Category /06 W 11)idblic 1131ijildlings 11:111,foirfly 3 finjpoidsinn StiraLeglic Goall GoAl 3 iolp Qimll uy V!11,mu infirash ucbjre� 11 ;akiii wed and II lroad ive CoirnirnuinHy II invesbilneilL 11F, lI GraiN III I Justification Locadoin ex poa;u re, c) 11 ouI ve 11 oti 'A 110111, a 1-11611- Ili fc (..Xl xr, tanry is 5 11 ii teii due k' 11 oin ru oll operatlon aii 0 11 oan ,A o cinvil, 01'11111c.^nts * 2025 * 2026 11 OC holler Fystoin * 202/ A N I * 2028 * 2029 11 OCchilleir Operating Budget Impact Nolle "fl: Rhis Hi rle INVillage of Mount Prospect I FY2025 Community Investment Program Requests Page 243 11 Capital Cost FY2025 Budget $69,300 Capital Cost by Year 202S 2026 Now 2028 2029 Total Budget (all years) $360.41K Project Total $360.41K $69,300.00 $69,300 00 $69,30000 $82,S0000 $'70,000.00 Capital Cost for Budgeted Years $0 $201K $401K $601K $80 IK 9 ConsUuuhun Cos� (100%) $360,40000 Consltructloin Cost TOTAL $360,400.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Coll �shrl wboll 11 Cost $69,300 $69,300 $69,31010 1"32,500 $70,000 $3160,400 Totall $69,300 $69,300 $69,300 $82,500 $70,000 $360,400 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 244 Funding Sources FY2025 Budget $69,300 Funding Sources by Year 2025 2026 vzwm 2028 2029 Total Budget (all years) $360.41K Project Total $360.41K $0 $201K $401K $601K $80 IK 1111111111 020 Calpitall Il improveiment IFuaind $69:4}4.1.00 $69,300 00 $69,30000 $82,50000 $70,000DO Funding Sources for Budgeted Years 9 020 Capit.al Irrprovemomt i::und (100%):'[,360,4� TOTAL $360,400.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 020 Capitall Ilunp iroveinient 11 wind $69,"300 $69,300 $,69,300 $82,500 $ 70,000 $360,400 Totall $69,300 $69,300 $69,300 $82,500 $70,000 $360,400 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 245 VIII IIIII'II III2edestri�ani1111riklges 0v(,,irvk,w Owilell, )ell pa - til 11 wil pYjjw So"At Mrx,, shreeL,/113 I A(Allig Supe I, � I, itoldold S1 I, eets & 311 ill dhil"S Cajjpil.,n11 ilillpiroveirillreld )CSciriptiolin irv;1ped, -ejp1w,e der kilig, -,All ('11 peli loinill �,t,edl sbra I( buire 11 qpalirs or tl-w pe(lestirian Ni idges In Keinsingtolli hjsfilnts Cenhir I l KBC lledeLir hnin 111'ridge 11 Xaik 11111'0a cl, 1'1lhiIN,-)u1' 22 II)W 00082 Accoui,A111wrilillbeir 020.80 90,00,1,/04.6/8,019 11111'0ted IIIfar 30yeains Category /04 sb[ed ,,(A,0111sbrixbon 1:111,forily 3 Illnnllpprrlrliinn Stirall.eg1k, Gmill CIoAl 3 pojp Qii�flliy Allage infirash inctuire: 11 ialkiii iced and lroad ive Coirnirnuinlily invesbinenill. 11F, llh!�, GraiN 11I,inded? Ill Locadoin Justification l 11 le jjjedes� i, laii obii idges in 11<11',C well CA ill is(allcd ill 11 'he em Y 90's. l 11 le I'm idge,, all e due for 0 11 uchn all ii l,,jx0Acjiri, wood l relplaceincii Ili aii Id geileirallrelpair,, ,iild dealihing Ql` the ,*xdI A I �Ix,i Ili re, p hcirewe 3, biridges awililElil," ill aongth oll' app r oxhinately /13', Operating Budget Impact 11401111("'AtIllf, tiline, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 246 y'lhez wsL o I bu !I kfiin, irirodArrlals ire in aur v, ,,11girI Hir. a 11-10,11y hip,1111011- Uh a In 111 a vIrev !I ow, yeairr Capital Cost Total Budget (all years) Project Total $731K $731K Capital Cost by Year mm $0 $201K $401K $601K 11j111 ConsLructloin Cost Capital Cost for Budgeted Years 0 Construction (100%� $73,000.00 TOTAL $73,000.00 Capital Cost FY2026 Total consbrucdoill Cost $73,000 $73,000 Totall $73,000 $73,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 247 Funding Sources Total Budget (all years) 7I Funding Sources by Year Project Total 31K $731 Cl00.00 $0 ^#anal $401 $601K 020 Carpita:nl ir>rnpirov€ irrrneirrt. Fund Funding Sources 020CallukalllIhrnlpirova°utiucnu II:'u.uund 1V 4Dtall Funding Sources for Budgeted Years 9 020 C;:apit:al Irnprov rncnC i::und (100%)$'73,00 TOTAL $73,000.00 FY2026 $73,000 $ 73,000 Total $73,000 $73,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 248 VIIIeve7W4I1IIMaifintenance ow"I[VicW kxqiue,,pOwilell, 11 sl.slaid IiDale 11 SI. Coirivillpletloin Dale DelparfineiH pYjjpe Scott Moe, si,qpc I, III 05/01/2028 05/31/2028 SLI, eets6" 113,11iddlings ("alpflIall 111II-Ilpiroveirl-wint )eScirilpHolin ".einriovfifq, all llalIrrsltpllading, U1 Ile u61114 ,ealoralong Ulhe q,onurcte wall ll oF Levee 3/. I innages Levee 37 walll I )CUAIS 11111-0aed 111undber 2S II)W 00001, Accounl: 'Nluirnlbeir 024.80 90,00� 1,/0Z6//D()3 p IIffe 2048 SustalinalblIfity malintall-1111 iig U1 le evee W,511111 ell ��mre,, flood proted.Aoin 'al adacenll, ncAglhboirhoo&s. Category 702 11 lood Canb,dl nunnd lordated Flrop xA�I� 11:111-ini,Uy 2 Very hinpoii ainu Sbrall.egllr. Go, -,fl Goall 3 pojp Qim1fIyV11agu Balnncr^rl aaInd 11,11road Ve ("olminnuinHy inve"bin-Irmill, ll,, d 11 fls Clrl rnII 11Ijii orledl I 11"Af) Justification Locadoin ry 11 evrm 37II cmpilires roi fthi le lirisjjxa+Iiclii ii -,n id uln a !I F I (A li,III (P L0 01-11 U IC L11 a I, a111 fac ets or 1,11 le Systell-11 or e fil n & A d wrm kling cond4lon p 11 lisindiudes puirillp Stations, gate systrei'irru ai id the concirete, wall. p 11 le walll r,,�xtcin& N oii � a p1p I, oxhiriately 11:: 1x1h d Ave to Sei,inlrole, � I �e wall 11 hm arifiroll llohnts cvei[y 20' Lhal, aire.gealed wldh a "u()Int" -,ealcir. Shice Lhvwalll was I uiufll. fin 2008, 111(: VA in t�,eakn h 'I-, Ilaegu I' o to al"IcR ai'VJI !Is u,I Iowlilngsgins off allull 0 pus l evell I Ilin u n d I'll-11"Ay dd orkpil a don of U1 le cal ciretc, ureiil Kwiling aindl ii oplad ng L11 w JIA I -It se"do, k ne,,Nary. Operating Budget Impact Nonr,aA thilri Lhn(a IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 249 Capital Cost Total Budget (all years) $1.251K Capital Cost by Year 2028 Project Total $1.251K $() $301K $601K $9011K $120K 11111111, Constl,W.1101r) COSt Capital Cost Coll lsbructloill cost Totall V25,000 00 FY2028 $125,000 $125,000 Capital Cost for Budgeted Years 4D Const.ruc6on Co-sL (1001X,) TOTAL Total $125,000 $125,000 $125,OMOO $125,000.00 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 250 Funding Sources Total Budget (all years) $1.251K Funding Sources by Year Project Total $1.251K V25,000.00 $0 $301K $601K $901K $UOK 0 024 Flood Control ConstrLACTIO... Funding Sources 024 11::11ood Cointii oll CoinsLi[ uuction 11uind Total) Funding Sources for Budgeted Years 9 024 I::Iood Cont.rcfl Construction f::und (100%)$ TOTAL $125,000.00 FY2028 $125,000 $125,000 Total $125,000 $125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 251 OC[°ilerIII26Wic 1113WH4iii ngs 0v(,,irvk,w Owilell, )ell aa - til 11 wil pYjjw [)Csorilpfloin 11 rill1provelirleirds lo vfllagrc owined Ilauuilluilirmgs. I nages 111,11111ldlini" 1111-1,[11)11 rwolleiils� 11 X�taik 11111'0ed IIffe Category 11:111,foirfly Stirall.eg1k, Gmill IN 111 Ifs Girciirit 11 11,111111ded? Cajjpil.,a11 II ilillpiroveirillreld 21, 1W 00065 020,80.90.00 1./06,651.001, 11 nuin& w11111 Ibe iro. qwsled 111 lil lil ul 11 Y rol, oilgall ing aind oalfi. (Wes W theAllage 106 inproveinod lx,�a�"Nblk, 131011(hings 3 11 inportaint: GOaJ 3 pojp-Quallty W111bge 1111 lfi,aSbri,ichjreIi,;"Al linced and liramdfvr Caii-iii-iiiii fly llii vc�d ilreii H No Justification U, alinfing iroouoarro, eauoil sldlng full oul'sldc garages Ilow refill isll es/i ol Aace" cal-11jetill lg, Ole K coo annkfloors as needed, ckslks, coirl[eireii we l,alblrn and h �1 11 l cl 11' -x ng , ilt 11 1W a trueeded, Operating Budget Impact 11401111("'AtIllf, fline, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 252 Capital Cost FY2025 Budget $1.65,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $8251K $0 $401K $801K V201K $i601K 1111111111 ConrAruction Cost Project Total $8251K $ifas'000.00 $165,,000.00 $iE;5,000.00 $1I65,000„00 $i65,00w)o Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� $82S,000.00 TOTAL $825,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total coinshrur"11101111 Cost $165,000 $165,000 $165,000 $165,000 $165,000 4825,000 Totall $165,000 $165,000 $165,000 $165,000 $165,000 $825,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 253 Funding Sources FY2025 Budget $1.65,000 Funding Sources by Year 2025 2026 vzwm 2028 2029 Total Budget (all years) $8251K $0 $401K $801K $W1K $�601K 1111111111 020 Calpitall Il in')1piroveiment IFu and Funding Sources 020 Capitall Ilurnpiroveinient 11 wind Totall Project Total $8251K $�65,,000 00 $�65,,000 00 $�E;S,000 00 $�65,000 00 $65'ooaoo Funding Sources for Budgeted Years 9 020 Capit.al IrnprovF momt i::und (100%j;}6;32 S,D TOTAL $825,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $1.65,000 1),165,000 $165,000 $1.65,000 $165,000 $825,000 $165,000 $165,000 $165,000 $165,000 $165,000 $825,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 254 VIII �)arlkfirilg1)edkIII ainteriance Ov(,,irvk,w Owilell, )ell ba - til 11 wil pYjjw So"At Mrx,� surae L,/113 I A(Allig Supe I, � I, ltoldod SI, eets & Bu ill dling's Callpitall II ilillpiroveirillreld )CSciriptiolin Staff re(iii esl,cd a (�ai diticiii ii ass�essrnoi iL be laor-farmeal In 2023 to rhAcirlinill le If f 11 le ci,iinrcrd innailill.cin,uiv,e sdhcdulk� vvankeelpling, I WIL11 0 U1 le ralc or ddeirlraratiori f hc rq,,Part amar, kiliallized includiling'a 5 ye�31'- u:r'Ijjplhll plan 1:1[oll, cnsurem, fll lat O 11 le '0 l ur h,lrc VW111 be in:Anil r'ihrled lin a M,all,o ol good relpaiii I l lau klilg II beck Pmalrlteilarr:,� I Garage 11,11rojed 11"'Iluirlber 21, II)W 00068 Accoui,A 11",11wiri-lbe1r (61-80.90.00.0.706 679,021, 11:111ojed Life, f 11his i an a11111111,111 jjpilouod ..rategory 706 innjp-OVOTC'llt� 0 11)ulblic Biuddlings 11:111'loir11ll'y "', 1111'njpoirtaill� 5all,eyjc Goall Goall 3 fbjja Quallily Vllflag e infirash tld ure: Frdanced and 11111r�vld ive Col'11111`1111LA1111HY investi,r[olill, IN flfli Gil 11:�lAnd(xP No Justification 111,,,fr,erj budgM of$150,000 ani �ually I for the aInlrafiu1G.ra1 iall urns of !Lcrrr+like, floolir S1, -)a11, a,mfllk and floor llohllts, watell pil oofilrig "Ali riceded, exq,-)an,�Ion Gohnl, replkweinneirit, and otheii rrl!,,cdlaineowu arqjalrs a�, I'leeded diuc Lo nal,uirdll agfing all wear arld Lear f he rqjoirtdeifldlrle. IinjpiroveilirwinL, hn 2025 fad:oirfing, Iiin cur rell 0. cw,t,, arld,;�"Aar 11 l, a hr, ('11 1gli-worling hin'ri 1 OCOflrnirwii idain iInflal,ioii lary ill lorease lo I parr, At] 11 l cot �, lor i-rohnitalinh ig, bodl o Vlllag(:r parlding ArluaLuirm, ain IMallple Stir(^.cq au id I'mcm sai o 5b, ect * 20251eeo tee johi H <walan( llhh,Il~Mllarvr k, 3, and 4 * 2026 feeto tee jolint se�,flaiit IlWH Ilnva ls 2 and3 * 2027 * 2028 "R i, to p ce jrA int ,Ila n u I-t&lt evell �; lh&ai ry nu aii id A. * 2029 Jolint Irmtpa,aiu at 'Aalple Sbreet 11'all-11ding, 11 )edk IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 255 Operating Budget Impact None M tlhk,,� fline, Capital Cost FY2025 Budget Total Budget (all years) Project Total $1.1.1,000 $9331K $9331K Capital Cost by Year 2025 2026 2027 2028 2029 $0 $801K $160K $240K ConsLruction Cost $ I ii'oco oo $132,000 00 $163,,000 00 $227,000 00 $300,000.00 Capital Cost for Budgeted Years 111111111 ConsUucLion $,,�;i�"()00.00 TOTAL $933,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Coinshrur boll -11 Cost $111,000 $1,232,000 $163,000 $22/,000 $300,000 $933,000 Totall $111,000 $132,000 $163,000 $227,000 $300,000 $933,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 256 Funding Sources FY2025 Budget Total Budget (all years) $1.11,000 $9331K Funding Sources by Year 2025 2026 2027 2028 2029 $0 $801K $160 K $240K 1111111111 05Village Parking Systeim Fiu— Project Total $9331K $m'000no $M,000.00 $�63,000.00 $227,000 00 $30o,00w)o Funding Sources for Budgeted Years 9 OSI Wlagc, Parking Sysorn i::und (100%)$933,( TOTAL $933,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 05INHIage �Iaii ding Systarn 11::�uind $111,000 $132,000 $1.63,000 $227,000 $1-00,000 $933,000 Totall $111,000 $132,000 $163,000 $227,000 $300,000 $933,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 257 VIII �)dk�lceStatiilii itoof IIV°t. IIIIpIIIIIace rill e nit Oveirvk,w Owner 11 )ell a - tilliell pY11 w [)CScrilpfloin 1:1611ce SLItion 11 mf replIC0111101110'. I innages 11,11) 11rwff �I )(AaHs 11111'0ted 11"'lluirlber 22 II)W 00091, Accoui,A 11,11wrillbeir 020.80.90,00,1,706.64 7,020 au mfrs II ire 20 }resat; ("c egary A06Ilinrolabreomearnenf W 11)idblk, 111,ijildlings 1:111,forily 3ivjjpoirlunn Stirall.eglic Goall GoAl 3 1011p Q13,4111 uy V!11,mu 11111,11'a'All wbuirr",: Mlaiwedl 11 F, d lh!�, GraiN 11vinded? Ill Justification Locadoin L an adaliplheircuseula 30 year old buildlill, 111clerlovaliollor (he LHAII&I 11g, ill ndhjded 'hele 11j,"'coll allexiAillgroof �,y,,,Lcnn ajpjpi-ox1im)te1y 11, yeaiii ,, old, whichi lipoii o 1,11 a(,. cornirnksloniii r, artIl le bi u111(flng, W;�Is iound to hzwe1-i'lultiple ezflks, umsli �g fll ie uiueae df au pat(A rojp':A-'�, a lhie roo 11 eal.a:sfur S wo - e co r1ril Ileeted by tlha roo il I og o .Oin l, — c l,011' L 111,rt W,l 5 bcoll it 11"a rAed to t hr., ge ii e ira 11 r;o in t ri,ro to rko inr l, - u c l, io in uTM 1-1�a9C` ` kff ill s1pedluirl confurinned tapir. hi llti<dl h ls1pectlaii o 1Chat ii oof i loods to IIoe -ejp1kicvd wlfl llin five year s, Operating Budget Impact Noll lrz <fl: dhils tilinx, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 258 Inflationary Impact ithe cos�o I irttn,flei1als Ihas increascd.N^,urlh, 5% has Iberrn "uhled bo U'le budgd- Capital Cost Total Budget (all years) Project Total $3.5961M $3.5961M Capital Cost by Year 2028 $3,595,700 00 $0 $1M $2M $31M 111111111 construction Cost 4�W� CainstirucdoinIE: ingineeiring Capital Cost FY2028 ConM ruO iol-11 IFinginrnn ing $200,0W Construction C;ost $3,395,700 Totall $3,595,700 Capital Cost for Budgeted Years 1111111111 ConstrucLion CoSL (941y()) $3,395,700.00 4111 Curst.rucLiun E.�nyim.h.niny (6%) $200,00(100 TOTAL $3,595,700.00 Total $200,000 $3,395,700 $3,595,700 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 259 Funding Sources Total Budget (all years) of Funding Sources by Year Project Total oll $3,59S,700 11 $1M $2M 020 Car itaal Il ir>rn;piroveiry" irrt: IF:aairnd Funding Sources 020 Caaplitaal hirnpiroveinient 11 wind Tota 11 Funding Sources for Budgeted Years 9 020 C;:.zapit.al Irr provemomt i::und (17I0'/r)$: S9 S; TOTAL $3,595,700.00 FY2028 $3,595,700 $3,595,700 Total $ x,5°75„'700 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 260 II')UWHk Warikiir°Illlhillea III1)oar 0v(,,irvk,w Owiliell, So"At Mrx,, shreeL,/113 I A(Allig Supe I, Fl I, itoldold 11 )ell �a - till[ wil S� I, eets & Bu ill dii-il"S �Yjjw Callpitall hillipiroveirilicid [)CSciriptiolin F"elplace Oh 11:11 hlk:wark�, rad F i.yovelillead drmir*,, Ilocall.ed fin Lhe inalin galage a nd ille velildc n, laintellialwe ga I' I inni ages 11,fl1„1l1:: woirll Oveirhcad D�lplw Zelplaculnuill, I NA41S )1rojed 11"'Iluiriber 22 II)W 0O('Du 5 Accoui,A 11",11wiri-lbeir 020.80.90.00. 1.706 64 9,020 11:1111ojed II ife, 30 "(ca i s category 706 innp0 liuildings j-V(T1C1l1t0 11)ulbc D 11:111'loirill'y "', 1111'njpoirl,,aill� 5 i Goall Goal 3 pbjjp Quallily Village infirash ud ure: Frdanced and 11111rfvld ive Coli'llili'lli.A1111HY 11 inivesti,r[olill, IN flfli Gil 11iAnd(xP No Justification LocalJoin p 11 le 'UlbliU Wwlk.,,, lacJllty was wted lira 19 18, p he oveirl u.ad dooirs aii id oporators aire an igh all to U1 ie Ilsi.alilldi111i11y, aii id are re, c I iiii ig U1 le eii id of Ll"Aruscrid ifea H a Lhirr,c Ycsou' 4iumlaanrai'll-le, o 2026 * 202/ rqjpjja(�f^ I e,V(.qrj-,(,ad dooi[ s fin ill t(,, vell ft 11c, 1[ rlaiinel wime gal[ age * 2028 'e gairawe * 20217... rr�prllsaieuArlvr�rhortaaapapa;rr,;alrl�iuu0.11�o°vowllr'ia:,llr°Irlrlrauurpa,,,ra,alnlu<„sara;,la�a. Operating Budget Impact I "fl: R his ifirle IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 261 Inflationary Impact ilheco,A r,4 irnatciJallru lliiaj uric asecL Asswlh, °j% II as Ihaeen idled flea the budget Capital Cost Total Budget (all years) Project Total FY2026 $1.,94.041K 41K FY2028 Capital Cost by Year Total 2026 $48,510 00 20217 $48,5iODO 2028 $194,040 2029 $485MDO $0 :'112K $241K $361K $481K 0 Construc.floin Cost Capital Cost for Budgeted Years 0 Corst.n.jc6on Cost (100%� $194,04000 TOTAL $194,040.00 Capital Cost FY2026 FY2027 FY2028 FY2029 Total Clonsbru(Goiri Cost $48510 $48,1,10 $48"Oo $194,040 Totall $48,510 $48,510$48,510 $48,510 $194,040 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 262 Funding Sources Total Budget (all years) $1.94.041K Funding Sources by Year 2026 2027 2028 2029 Project Total $1.94.041K $0 $112 K $241K $361K $4+81K 111111111, 020 Calpitall llirrrpiroverneint Fund $48,5K).00 $48,5p0 00 $48,5M.00 $48,5M 00 Funding Sources for Budgeted Years 9 020 Capital Irrprovornent. i::und (100%) $194,0, TOTAL $194,040.00 Funding Sources FY2026 FY2027 FY2028 FY2029 Total 020 Cap itall hinprowinicint 11::uind $48,510 $48,51.0 $48,510 $48,51.0 $1.94,040 Totall $48,510 $48,510 $48,510 $48,510 $194,040 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 263 II')UWHk Wariks itPZ 0v(,,irvk,w kxqiue°,9Owner Scott Moe, .fl ,qpc I, ill Dell aartillaifil SI, eets & Bu ill dii-il"S �Yjjw Cajjpil.,a11 hillipiroveirilicid [)CSciriptiolin Fl,el/Iliac e flaw? device a�iLhe I'lublicW011 ('s I inni ages W fl)7 11 Xaik 11111'0a cl, 25 II)W 0000d Af,counl� 111wri-ilbeir 020A0 90DU 1, /0&64 9D20 11111'0ed Iffe 2%4 Sinta !Ill I s111) !III H Y 11a,11'Z 'inw,,l. I Ile W jj,-ms�, !I in"peciliolill Losafegu a ird U1 le Vill II rgw, wat�oSY�Aern. C,fl egory 706 innijjpi-OMI]Cllit0 11pulblic 113iAldings 1:1111011rity 2 Very II rnjparl,anid sb%Aegk: Go�jll Goall 3 Rq) Cjua F uy Vii llaag IIIIafrastrudiiiie: 11�41anced Y.°Ind Ilplrerrld ive Col-11111i'lli.A1111HY inivestivolill, 11 his Gir;,nnr 11ljinidledl III Justification p he Iback ilcwdrwic<� can no llonger jjpas; (he aau iiiijall hislIxc.A.ion a i id il,, hii need of ii v1placon-lont, Operating Budget Impact I if, sfl: dhis tillix" IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 264 Capital Cost FY2025 Budget Total Budget (all years) Project Total $40,000 $401K $401K Capital Cost by Year 2025 $40,000DO $0 $101K $201K $30K $401K CcnstrLJCT101fn COSt Capital Cost for Budgeted Years 9 Const.ruc6on Cost (100%� $/,C),C)00.00 TOTAL $40,000.00 Capital Cost FY2025 Total CoirrAirucboin Cost V0,000 jm,000 Totall $40,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 265 Funding Sources FY2025 Budget p 40,0ag Funding Sources by Year RM Total Budget (all years) 4 $0 $1101K $201K 020Caa raita:nl 11 ir>rn irov€irrrn€int: IFaii irnd Project Total $401K $30K $401K Funding Sources for Budgeted Years 9 020 C;::zapit:al Irnprov rncnC i::und (100%)$40,00 TOTAL $40,000.00 Funding Sources FY2025 Total 020Caaptlitaal hirnpiroveinient. I wind $40,000 $40,000 TotaalV $ 0,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 266 1)oor ��Ie ace rne rit 0v(,,irvk,w kxqiue° Owner Scott Moe�si,qpc I, ill Dell aa - till[ ia it SI, eets & Bu ill dii-il"S �Yjjw Ca; jjpil.,a11 II illipiroveirilicid [)CSciriptiolin F"el/Iliac e and a l. the Ilea lblhworl<FFf"wility, I i 1W 11 xLeriol, Door 1pejp1,'icr1'1-lrl-lt: Xaik 11111'0l cl, 20 II)W 00062 Af,counl� 111wri-ilbeir 020A0 90DU 1, /0&64 9D20 11111'0ted IIffe 30yeains Category /06 W 11)idblic 1131ijildlings Fru -forily 3 IT1111301i'l',Nd Stirall.eglic Gmill (.1oAl 3 pojp Qi.l,illi y Village 11 inifirash inctuire: 11 ;akiii wed andlroad ive CoirnirnuinHy inivesbilnenill. Is flhN Gir,,3int 11 iijindled? 111,110 Lpa cationi p Justification p"Ihon; lubfic Works 1,acilltywls rmirisfirud ed lin 19W3 ')1l a,> "ix1h, t1he exi,ell1al dooi,and firnillies 11 lave o detell-if)II'M,12 F C) SIA11 al'I 0Xtrll-i[ Uh,'A Aaceirricii it is cs.,,oltlall W illizlill tall -11 U1 11(� StINICAIA11-0 ill 11 .r ,JA,c ofg^xA rqp�ilr aii id fuiftll leir i tlI le N¢dllty sc.�r, ure, Operating Budget Impact 11401111("'AtIllf, tiline, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 267 ihewsk)[ rnakrlab, Ihutrv� uncreas,,:d. AsswJh, 5% Ilhas Ilar,en added W Uic, '�)wlwA Capital Cost FY2025 Budget Total Budget (all years) $52,500 $1.31.251K Capital Cost by Year 2025 2026 2027 2028 $0 VSK $3011 $451K 111111111 ContAruction Cost Project Total $131251K $52,S00.00 $26,2SO.00 $26,250 00 $26,250DO Capital Cost for Budgeted Years 0 Construction (100%� $131,250.00 TOTAL $131,250.00 Capital Cost FY2025 FY2026 FY2027 FY2028 Total consbrucdoill Cost $52,500 $126,250 $26,250 $26,250 $1131,250 Totall $52,500 $26,250 $261250 $26,250 $131,250 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 268 Funding Sources FY2025 Budget $52,500 Funding Sources by Year 2025 2026 2027 2028 Total Budget (all years) $1.31.251K $() V51K $301K $451K 111111111, 020 Calpiia ll Ilirrrpiroverneint IFund Project Total $131251K $26,2S0.00 $26,250.00 $26,2SO00 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovorncnC i:: und (100%) $131,25o TOTAL $131,250-00 Funding Sources FY2025 FY2026 FY2027 FY2028 Total 0200 aputaall lhirnp iroveiniient 11 wind $52,500 $26,250 $26,250 $26,250 $1.31,250 Totall $52,500 $26,250 $26,250 $26,250 $131,250 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 269 I VIII llh°°°11IVAC Vari4WIe AiHr VdIunne cm Oveirvk,w Owilell, So"At Mrx,� shreeL,/113 I A(Allig Supe I, il I, itoldold 11 )ell aa - billell 5 I, ects & 11 ,Ili ill dlillp's NYjjw Cqjpil-a11 II ilillpiroveirillent [)CScriptiolin 111opkice Ii IIVAC vairiable�ihr volurne (VAVJ l Ilocated au lidblic Worlo, I::arllily. I innages 1W 11 IIVAaC VAV box relpl'ice'rinvint �I )(AaHs 11111'0aed 11"'Ilhilriber 22 II)W 0008d Accoui,A111wrilillbeir 020.80 90,0(),1,/06.6!)1 0110 ,roec� II fre 30 Ye,,)irs (", tegary /06 Il irriprovernoit W Iflii.tlhlliiu, 111,ijildlings 1:111,forily 3 llinngturrrliinn Stirall.eg1k, Goall GoAl 3 aOjjp Q13,4111 iY V!11,mu 11111,11'a'All wbuirr",: Mlaiwedl ;.-md 11111,0,"udlvp. 11F, llh!�, GraiN 11I,inded? Ill Locadoin Justification Hle II1W 11 NA(WAVIlboxesexis(hr (he buildingarld have adlieved Hlelir useliull II ife,A1111 Operating Budget Impact ll,loii le,'jt 1:11 il,> tinne, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 270 i Ilhue cwAu far Inall sufactuiring, "31111 C01-11111porients a Ind ava1 a "All i ('y rA inn a Led! all s willl wnil,i inue, W i rlcircaser As, surh, a in iriirroase of 5W, I ms lkeni adckx] to U w budge l. Capital Cost Total Budget (all years) Project Total $86.6251K $86.6251K Capital Cost by Year i $0 $25K $501K $751K Capital Cost C . onstirliclJoin cos� Totall $86,6,25 00 Capital Cost for Budgeted Years 0 Construction CosL 1100%) $86,625.00 TOTAL $86,625-00 FY2026 Total $86,625 $86,625 $86,625 $86,625 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 271 Funding Sources Total Budget (all years) Project Total $86.6251K $86.6251K Funding Sources by Year RM $0 $25K $501K $7SIK 0 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Capitall Ilurnp iroveinient 11 wind Totall $86,625.00 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovcrncnC i:: und (100%) $86,62! TOTAL $86,625.00 FY2026 Total $86,625 $86,625 $86,625 $86,625 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 272 VIII flllhliiiii lllll III ailii ntenanice Shqp Oveirvk,w Owilell, )ell aa - billell aYjjw [)CScriptiolin tho, irlicirio I, ordlevell i ide inaill i IP111,H]lKe 'I holp. I innages 111WWA-lide Shop 111alintling So"At Ir oe� shreeL,/113 I A(Allig Supe I, I, itoldold 5� I, eet�� & 11 ,Ili ill dlilj�,,S Callpil'all Il ilillpiroveirillent �I )(AaHs 11111'0ed 11"'Ilhilriber 20 II)W 00061, Accoui,A111wrilillbeir 020.80 c/41.00,1,/06.64 9,020 ,roaecp II fre 25yea,�, ("ategary /06 Il irriprovernoit W 11)idblk, 111,ijildlings 1:111,fori9y 3 llinngtarnrlain� Stirall.eg1k, Goall Goall 3 aOjjp Q13,4111 iY V11111al"u 11111,11'a'All wbuirr",: lialkiiicedand 11F, llh!�, GraiN 11I,inded? Ill Locadoin Justification Hle lulblicwoilks radlitywas I-Aid(in 1,989 all Id, Gr, such, Hlelirdeiioii wa111 xildcoilling"u1i faces requIrc palinhillig 'o (ouji "ood ruliadr,asweIll aircl, Operating Budget Impact 11401111cat I1111if, tiline, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 273 I IIhe cwA of rriaU,,�1,11,311s has ui ir,ieas,,dAs sawlh,b% II as Ilroo n addQd W U ic Iruadc,O, Capital Cost FY2025 Budget Total Budget (all years) Project Total $46,200 $46.21K $46.21K Capital Cost by Year $0 $12K $241K $36K 1111ill, ConsLructloin Cost Capital Cost for Budgeted Years 0 Construction (100% $4(,,,200.00 TOTAL $46,200.00 Capital Cost FY2025 Total ("Onsbructiol-11 Cost $46,200 $46,200 Totall $46,200 $46,200 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 274 Funding Sources FY2025 Budget $46,200 Funding Sources by Year REM Total Budget (all years) $46.21K $0 $'12K $241K 020 C ar itaal ir>rn;piroveiry"irrt: F:aairnd $36K Project Total $46.21K Funding Sources for Budgeted Years 9 020 C;::zapit:al Irnprov rncnC i::und (100%)$46,20 TOTAL $46,200.00 Funding Sources FY2025 Total 020Caaplitaal hirnpiroveinient.I wind $46,200 "46,2.00 1potaalV $46,200 $46,200 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 275 IIIIC° rafitVIII' W Veflhilii dleIII afirwtenanceIIIIC igIl°lftiii ng to I 0v(,,irvk,w kxqiueOwner Scott Moe� si,qpc I, ill Dell pa - till[ wil SI, eets & IBu ill dii-il"S �Yjjw Callpitall hillipiroveirilicid [)CSciriptiolin F"(All-ofill, exlsfJiigoneirgy ill highLing in, lulblhWorl<. , Vehicle riliallill,on"ll'iCC „rali u<,u Ilii,ding Lo 11.11 11), I i 1W Vehicle 11"lah-lienairice if"1111611 g l NAAHS 11,11rojed11"'lluiriber 22 II)W 00W7 Account 11",11wiri-lbeir 020.80.90.00. 1.706 64 9,020 ire 310 yeairas cat egory 706 innjp-0V(T1C1l1t� 0 11)ulblic Duildings 11:111'loirill'y ', 1111'njpoirl,,aill� Sbrall,egku Goall Goall 3 pbjjp Qualfiy Village nfirashnwbi Ile: Frdanced and 11111rfvld ive Coli'lliloll i.A1111HY II inivesti,r[olill, IN flfli Gil 11iAnd(xP No Locatioin Justification le 11 g ,110,11118 in L11 le 11 lldblk� Worlka, vell licle rinahnik.,.ii uainc.e col v�dkA,� aA onor,,;Y h 110fi(Jell it 5 fixturcs, p he lsflinlg fixtin es, ^Aai-Lor^, 111 Id i require fireq, mil lit ch"ll-ligill iig all id 1131-ovide q,ibsl.airidard lighl'illig lin 11 "r�lhojp, INN"Alronittill 11g, flll(� iglht, to 11111) tYl)(,llIg41111 lIT11,311 OVC,' ObJell-KY and Ilight: qualfLy, 11'0^Addirlg ill 11 caul fill-1111pirowd wol-1/firig roindidon. Operating Budget Impact "'ch ofitifing the exkdnq; fixhlireas willl 11-(,�,uh in lowor I'll-lairift'llial we (�osk roir iniatellialk and 11,111boll'. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 276 Inflationary Impact i1heroot of m aur riklls ha,� increas,,dl. Asq,wlh, 5% has Ilan,e is added k„ Uhc ')udgeL Capital Cost Total Budget (all years) $48.5 1. IK Capital Cost by Year 2026 Project Total $48.5 1. IK $0 $112 K $241K $361K $4,81K 111111111 Construction Cost $48,510 00 Capital Cost for Budgeted Years 0 ConstrucLion CosL (100%� $4,0,S10.00 TOTAL $48,510.00 Capital Cost FY2026 Total Consbrucdoin cosp$48,510 $118,51.0 Totall $48,510 $48,5-10 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 277 Funding Sources Total Budget (all years) Project Total $48.5 1. IK $48.5 1. IK Funding Sources by Year RM $0 $1112K $241K $361K $481K 0 020 Calpitall llir>rnl iroveirnint: IFUnd $48,SM.00 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovcrncnC i:: und (100%) $48,S1( TOTAL $48,510-00 Funding Sources FY2026 Total 020 Capitall IIurnp iroveinient 11 wind $481,510 $481,51.0 Totall $48,5 10 $48,510 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 278 VilllIageIhniteriar 111Paiiiiiiiintiiiiiilng of Areas 0v(,,irvk,w kxqiuesOwner 11 )ell pa r til 11 wil pYjjw [)c S C - i P 1: i 0 In a.�ununp, orwilligre 11 L)IIII I inniages Scott Moe, si,qpci1nteindeid S1 I, eets As. 1134,61161ing's Cajjpi[,a11 kinpiroveirincid Locadoin 111111 ojed 11"'lluirdber A Vdlkige 11 Eilll IIIntorliaplrIi1au nuncr or )c1partinoH, Aii ex, Scott Moe, si,qpci1nteindeid S1 I, eets As. 1134,61161ing's Cajjpi[,a11 kinpiroveirincid Locadoin 111111 ojed 11"'lluirdber 22 II)W 00(W Accoui,A 11",11wirinbeir 020.80.90.00.1.706 651.001 ire 10llarsalrra C,)tegory V1011t0 11 c D)ulbfiud6ngs 706 innjp,O01 1:1111oll1LY ', 1111'njpoil,"ul� Go"311 Goal 3 bjjp Qualfiy Vdlage nfirashnwbi ii,e: Frdanced and 11111rfvld ive Con[lilr[ILAInHy invesbrr[oll 11 s d his Girrnn� 11undkxll No Justification p 11 oe delpa, tinneii oL ciirciis CA U1 oQ V11111agc 11 we�iro aspah Led h 112,016, As suc I i, pah �thi q,, W fll oppw 1 111111 be xq.essairy to lecelp 1,11 e bulldh q7 in ¢i good of irc"Ip"d I'. Operating Budget Impact 114oii(s�A Uhl�s Llinle IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 279 Inflationary Impact Capital Cost Total Budget (all years) $46.21K Capital Cost by Year Sm Project Total $46.21K $0 $ 21K $2411, $361K Construcflon Enghneering Capital Cost Coll -VAI[ lwdoin Totall $46,200 00 Capital Cost for Budgeted Years 1111111111 ConstrucLion Enghrvucring (100%) $/,(,200.00 TOTAL $46,200.00 FY2026 Total 1,46,200 $46,200 $46,200 $46,200 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 280 Funding Sources Total Budget (all years) $46.21K Funding Sources by Year RM Project Total 4my1 $0 $¶21K $241K $361K 'N 020 Caalpita 111 llir>rnl irov€ irrrn€ int: IF aiiirnd Funding Sources 020CallukalllIlurnpairovn°utucnu II:'u.uund 1V otalV Funding Sources for Budgeted Years 9 020 C;:apit:al Irnprov rncnC i::und (100%)$46,20 TOTAL $46,200.00 FY2026 $46,200 $4 6,200 Total $46,200 $46,200 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 281 VilllIage I igl[�uItfing UIpgrade ow"Irvkw kxqiue,,gOwiliell, Dell yartii 11 it gYjjx' [)c S C - i 11: � 0 In F"(All-ofill, exlsfJiig' ill aicIFlaar li7;Ilkiiilg oveir Lo 11.11 11), I i V11 11 ink'111011, lightling" i Scott Moe, si'qpc I, ill SI, eets & Bu ill dii-il"S ('"allpikAl II Irlropiroveirilielit D(A�41S 11111'0l cl' 22 II)W 00086 Af,counl� 111wri-ilbeir 020A0 90DU 1,/0&6!A001 11111'0ed IIffe 20yeairs category /06 uo 11)iflblic 113liull(fings Feu -forily 3 1T1jjXA`l',Nd Stirall.eg1k, Gmill Cio,fll 3 �ojp Qi.l,illi y Village ll inifirash inctuire: 1131al,iii wed and Illlroaa aive Coirni-nijinity inivesbinenill. Is flhN Gir,'3int 11 ijiiidled? 111,110 Locadoin Justification g he vllla„e 1111,11111 hriteirior ligd-liting 11 iias Ibe cirl ('Xin;IJI-1q," uur Lhe buildling dince 2003, ghe Hght" coll Kill lue l'o uroquiro significnird urgealr, lirldkAfiirl�,, IhaIIllasi. �iild Lxflbs, N, siAcJh, !it !is I, Q(xminivielided to I[ chrorit UKexisll'lns" Illi glills to a imne o11r'1q',Y drlck�ii u4, Ilenng(:^11 la',sdiig 11,11 11) type d Ili f; I L Operating Budget Impact 114AIrrifitting the existing fixtures WI1111 resuilt hn a reductiari of ii-rialinteinance costs foir i lzds and aljor. Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 282 I IIhe cwA of rraU,,�1,11,311s has ui ir,ieas,,dAs sawlh,b% II as Ilroo n addQd W U ic Iruare3c,O, Capital Cost Total Budget (all years) Project Total $34.651K $34.651K Capital Cost by Year mm $0 1111ill' ConsLructloin Cost VOK $201K $30K $34,6�.SO 00 Capital Cost for Budgeted Years 0 Construction (100%� $3,/�,&.xxoo TOTAL $34,650.00 Capital Cost FY2026 Total ("Onsbructiol-11 Cost $34,650 $34,650 Totall $34,650 $34,650 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 283 Funding Sources Total Budget (all years) Project Total $34.651K $34.651K Funding Sources by Year 020 Carpita:nl ir>rnpirov€ irrrneirrt. Fund Funding Sources 020CallukalllIhrnlpirova°utiucnu II:'u.uund 1V otalV Funding Sources for Budgeted Years 9 020 C;:apit:al IrnprovcrncnC i::und (100%)k'34,65( TOTAL $34,650.00 FY2026 Total $34,650 $34,650 $34,650 $34,650 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 284 umilu� uuuuuum um ml uuuuuum uuup uuuuuuu uuuuuuu uuul�uuuuu um umilu� umu a uum°u mp uuuum uuuum �i uuuuuum uuuuuum ouu �, uuuuuuu II uuuuuuu �mVum �i Village of Mount Prospect I FY2025 Community Investment Program Requests Page 285 VIII oa�rd iloolu°iri ScIreori iteIIII VIII ellluirie ni'll. 0v(,,irvk,w Owiliell, 11 lowaird <IrAiw' telin, Dilrecio - ofcoirairauirllr:„fl I011 I 11 )ell �a - till[ wil V Sell -vire” �Yjjw Cajjpil.,a11 hillipiroveirilicid [)CScirilpfloin dwo -noL01`li7Cd SU'CCIT; wiflii is &1.9-,i7eda;jjpect i to irr,rlpllace I'lle Challigc t.11ar Ilo nse� ; an the rAirionll.vidloo jjproucd:ois to i'[1111 the iri(w soman 11-11 ^,izef, I I X�taik 111110aed IIffe Category 1:111,forily Stirall.eglic Gmill IN 111 Ifs Girciirit II:11,111111fled? Justification 24 � V 003 020,20.90.00 1. /09,66 `.).008 2040 /091',k)n 2 Vcry Ili iii1portaint GOrJ 1 11 d fective V!1111,sge Govell-11 III ricill l: 11 Lxurajptianall Sairvice No he aurreint ,creorylino the village Board 'yraraira mire o111,,in,111 eq611prineini, and a ro 20 years old. d heyweire ill uStalleld duiring, Lho i9,,o and =»ttand I A inoirdeii i to f` L t11 le -1Q1,l/Q1-11sa11 IliunroiitsJuiir n,,�, 111 le inew ,Crccin^.i 41111 brj M a I n opor" v,,Jjpe(A, raniirp ibir 111111 ) video and the ira ,,ij1Lh p wI1111 larf,,,or, Operating Budget Impact d he'll c" �,Ihouldl be corp iii lijp;x,A an U'le olperading, Ilaiaallget. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 286 Capital Cost FY2025 Budget Total Budget (all years) Project Total $40,000 $401K $401K Capital Cost by Year $0 $101K $201K $30K $401K E.qullpirnent Purchase Cost Capital Cost for Budgeted Years E.�quiprnci,ir. Purch,a,,.,o CbsL (100%) $40,0MOO TOTAL $40,000.00 Capital Cost FY2025 Total 11q�Alpirneint Purchase Cost $40,000 $40,000 Totall $40,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 287 Funding Sources FY2025 Budget $40,000 Funding Sources by Year REM Total Budget (all years) 4 $0 $1101K $201K 020 C alr itaall 11 ir>rnl airoveiry"i rt: IF aairnd Project Total $401K Funding Sources for Budgeted Years 9 020 C;:apit:al Irnprovr momt i::und (I00%)$40,00 TOTAL $40,000.00 Funding Sources FY2025 Total 020Caaplitaal hirnpiroveinient. I wind $40,000 $40,000 TotnaalV $ 0,000 $40,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 288 VIII iroa Illi ix Switd[iier 0v(,,irvk,w Owiliell, 11 lowaird <IrAiw' telin, Dilrecio - ofcoirairauirllr�,�fl inil I 11 )ell aa - till[ wil V Sell -vire", 1Yjjw Callpitall IIuuop iroveirilicid [)CScirilpfloin F"elplaceinoH seflkrhar kn i1he 1131iroadcas tIlk, Mica in the Nscrvke'scanlxoll 1 IF lybrld <;Y< ternlwfl.h '13 II",dMworlk 11 4 SIDII inputs rhall-irld"'4 0/111',s, Iv1evVllUllu.uo. I If 1AX IF lylbrld Sedt�, her �l)ctaik 11,11 ojecil, IIAauiliber 24: U V 0002 Arxxwna Aw-ribeir 020,10.90.00 1, 709 665.008 1111rojed Life 2032 egrvy 709 Noin AuLoirrlot ive 11 :qulj,aii m iU 11,111oll'Ay 2 Ve ry 11 rin i - ha n P S1 ai Goall Goall 1 11 Ufnr:Paivr VdIngr, Goveril lrneill0 " 11:11111alvJally Sould, II saes, loiniall Sell vir,e IN flfli ,ramal 11iAnd(xP jr) Justification Jjj,-jprarl(:,�; 11 n Ledl oInoll ogy all 11 ow � 11 lis swil t(A inii Lo l�ii icor por ate ii letwor ked soi n ces h uroall U irrie, Operating Budget Impact 11111,;,, lteilr� wi1111 Il <w no kn1pactain the n1peirating ,, lbi idgeC IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 289 Capital Cost FY2025 Budget Total Budget (all years) Project Total $30,000 $301K $301K Capital Cost by Year $0 $81K $MK $241K E.qullpirnent Purchase Cost Capital Cost for Budgeted Years $K),000.00 TOTAL $30,000-00 Capital Cost FY2025 Total 11(Jullpirncirlt 11311airdmse Cost $30,000 V30,000 Totall $30,000 $30,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 290 Funding Sources FY2025 Budget p $30,000 Funding Sources by Year RM Total Budget (all years) 3I 020Caa raita:nl 11 ir>rn irov€irrrn€int: IFaii irnd Project Total 3IK Funding Sources for Budgeted Years 9 020 C;:apit:al Irnprov rncnt i::und (100%)4;30,00 TOTAL $30,000.00 Funding Sources FY2025 Total 020CallukallIhrnlairovn°unicnII:'u.uund "ii30,000 $30,000 1V otaalV $30,000 $30,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 291 (1-1111vics Shill III° IIIIIaceiiirnle nt Oveirvk,w Arronpuuc> p, Owner 11 lowaird Klohn,;telirl, Direclor 11) ll aa - tilliell V Seirvice,; �Yjjw Callpil'all hillipiroveirilielit [)CScrilpfloin 111'elplaceino-H for 11w, eAMlirigci)Jc�; I'Vent Sign. Nvii)WAR.'11 111:111flFlbinind inessag,r. urlfl^, WIF11.1.111,1111) 11:111"d(1111,11G. 1o4GXVII 1Z1'1L11 SSvArll,1111:1' 011.SIGIN IDcjta plain H,Jrlduido, IlG IN11 H 011:1XIblaild and I irni'aples (ivlu Fvcrlts sigln NA41S lrojod 1114urrllor,'r Accouiql: 1114wirribeir I'llojed IIffe C a t e� ;0 l'Y 11,1110111ty 51 ai Goall 241 V 001, 020.20.90.00.1.709 617,001, 2035 709 INai i Awtonlm6vv 11 quipirnent �3 rnjpoilainr Goall 211 nilhi,.-wiclng ',AwiM 111irosper.A. C11 ainrri/(IharwAer11 himorling, 11 fis9,011 Y, 11 Nri­!H agre, And 11 iiveirsiLy, 11 quityand 11 nclusloin 11,11(j Justification U1lecA,,fling igilll is 10yeaii m, old a ind Nbegh-1111-11ling blowirli plxel,�. 111I[ aactive lelp1l ace i wdll allow u'3 k) i the w -A al, a Llrne(A ouir dhoo^, !I -wWLI-imit thesign LwN4g down [oil- "A LNue, Operating Budget Impact � he r,ign "11 i(Add 11 lavo, i hrijpnjct on, U1 le ojpuraling biAgrl. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 292 Capital Cost FY2025 Budget Total Budget (all years) Project Total $55,000 $551K $551K Capital Cost by Year 2025 $��,00000 $0 $�51K $301K $451K Enquillpirnent IPa.uirc lhase Capital Cost for Budgeted Years $55,000.00 TOTAL $55,000-00 Capital Cost FY2025 Total 11(Jullpirncirlt 11311airdmse Cost $55,000 $55,000 Totall $55,000 $55,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 293 Funding Sources FY2025 Budget p $55,000 Funding Sources by Year RM Total Budget (all years) 551 "j0 $ 51K $301K 020Caa raita:nl 11 ir>rn irov€irrrn€int: IFaii irnd Project Total 55IK Funding Sources for Budgeted Years 9 020 C;:apit:al Irnprov rncnt i::und (100%)$°'5,00 TOTAL $55,000.00 Funding Sources FY2025 Total 020CallulkallIhrnlalrovn°utiucnu II:'u.uund "w'a55,000 "j;55,000 TotaalV $55,000 $55,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 294 uuummu WIC uuuuuuu uuuuu m IVu uuuuuum uuuvl U m m mllluuv uuuuu uuuuu uuuuuuu uuuuuuu IIUu uuuuuuu uuuuuuu "VIII umm uuuuuum umuu ummllluoi IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 295 II''°°°IhreVfflhidle Ove,iryicw kxqiu('dnf Owner 11 )ell aa - til 11 wil fy1po [)CScirilpfloin Kovilin II ellucaa,Vellloiiellr;IIIIIIteinanc(Supo I, Intendant vell-ilde kdallitelial-we Callpitall II ilillpirovelilleld F"elplaceinol I � offile II elpall' biniOnt velhlide,,3and equillpinionll. Anil I jall Vehi 11r711r ase laaayuinielits a Ill, ('alcull a lcd Ila, eadh volhidlu Iba,,ed on Mlle llffe ol Adne vidlIde, calrnjl,ited inleircrif all lid the vell ]I We arrc::oIIil7itllPrall,airor,e Flnevelilde emp, jjmynlranln r11'0, rc(:alollaterf a n nmdly pa',cd ora arluall ar:nru -III �, f 1-ic followill g, are L;dhiediuled to Ill u elp1l a c ed: * 2026II 1D# 500 11ord 11 x1ploi-eir $58,000 * 209& II11 11 501, 11oirrf 11 x1i Lloii eir $58,000 * 202 1111 M 5(1') 11riird 'Ickwip$581,000 * 202 1111 M 5OJ II calrct I11 scalpe IL Nylbidd $46,000 * 2028 1111A 503 G-wvy falhoo $69,000 * 2028 1 11 524 11 hii I Aline) * 2029Illltff 525 II imight1lileir 11 $475,000 * 202911111)6'06 Licighthilei-11 * 2029 1111 M 5V. , 111 f e ii, c; u 1i 11 re 11 . ng ince 1; 11 , 2 0, 000 (C A A ii- - Q I Y, a 4 yeah- ii- I I ILA f 11 nI I, I Inn a 1111 Ow a 11 11 .1 11 a in in ed A, o o ira 11 e 1, 11n 2 02 1) 11 OIRID 11 X11111,011RIARAIDIMIN Dctaik 11)11rojed rAunqber lac counu lftauinnlhe it 11111rojed, IIAfe (: at ogo ry 11111- i o 11, f Ly stiral,cgki Goall Justification firelDelpt, 11 relght hileii Airindbulanco 21, :1W 00071 061.70.90.00 1, 708 660.005 Aii ii-q-)ILH.cinneirit jjpolhr.y 708,Vchili: ns,/Al.jt()1TI()hV2 11 quillpirnent 1, Crkkall G,oall 1 11 'xcr.,ptionall Seirvine 1\10 H !!:11:11 le poll !icy oft he Vill of I n t li-aspITt I jafca toolk notorIzed equillpineint a soul stanUall finandall ExAlah or th(Ndlag(,aInd I toll)(diandkx] in Uh(^Inliostr ecorloir�ilicnall nnailliwir 11n thelir a I o d fun i ii in ax ii ii irii ii riiro1, � 1-1 c i 11' d i Ipo u, a 11 va 11 a A e. 11 3 c 1111 ve 11111 r• 11 e d 11n1 d/o I I il c r' e rat r= q L I ii ) ir I c n � � 1, o a S a I, I u A I]- I b c - o f 11 f ve . 11 t 11 o a a ; e 1( V e 11 w1l ii i C 1111 is 0 1h (" a I-ir o ('A A rot" t IF hirneawdilde aindsafeseivir,eIt Ilona leclinologdcall Ire'vVIhich rejprcsf�inls 1:11)n to inevvell riodds, 1114(a5tilrl(olpf)lrtalnitlly,fitllo;ISallo(�Lfuii-or,ilrofi�, Ife'vVIhich is Uic eingthor OWI-Ifffall lj[a CGI^A fS,'A a unu1uDioramauaro. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 296 Operating Budget Impact I Inflationary Impact C 11 le I III � "I [Uhf co,As (11 �gh 111 ng, decals, rad kislhavu dou INI c (J. Capital Cost Total Budget (all years) $2.9641M Capital Cost by Year 2026 2027 2020 9w Project Total $2.9641M $0 $6001K $i,21A $1 Sim E:qullpirneint IPuifclhase Cost $p 16,C)C.}ODO $104,000 00 $54,4,00(100 Capital Cost for Budgeted Years 111111i E.:quipmei it Purchaso Cos,,C. (1001/,,) $2,964,000.0 TOTAL $2,964,000.00 Capital Cost FY2026 FY2027 FY2028 FY2029 Total Fquilpiina.int 11"inchase CoM $116,000 Ju 104,000 $544,000 $2,200,000 $2,964,000 Totall $11.11.6,000 $104,000 $544,000 $2,200,000 $2,964,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 297 Funding Sources Total Budget (all years) $2.9641M Funding Sources by Year 2026 2027 2028 RM Project Total $2.9641M $0 $6001K $L21M $1 81M 111111111, W Vehicle Replacement IFund VO4,000.00 1544,000.00 $2,200,000 00 Funding Sources for Budgeted Years 0 061 'Vehicle, IP: cplacci ncW. I:::und (100%) $2,964,¢ TOTAL $2,964,000.00 Funding Sources FY2026 FY2027 FY2028 FY2029 Total 061Vc117kJc ,cplacci-rwintll jind $116,000 $104,000 $544,000 $2,200,000 $2,964,000 Totall $1 16,000 04 $1,000 $544,000 , , 52,200,000 $2,964,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 298 II VIII ce Whid ove'rvkw kxqiuedf Owiliell, Dell Iall-til 11 wil fyllI(' Kevfin Ddlucal, Vell-ildr, I III tenanc(supo I, friteiridell-it vell-lide kdallitelial-we Cajjpil-11 IIuuop iroveirilicilit [)c S C - i 11: f 0 111 Ielplaceinol I � of ldfcc Do I Unci'A vdhilde�� a ind equillpirwint. f he a I-inu -III Vdilde lew;e jpayiineiiil.<; a irc calcubAed far eadh wNcle lb,)Sed on d I,( ife ('If U1 ]I( vell I ide, calrmlnll,ed inleiresi, rill uJporvklo I ]I fccs, 11 ereived, and Lhevchkle ar�r:rm in, dm11611-we f I vc I le xIY1`1`101 ]Ik', aire irr!r.�.dr.I.AlkikA )n in uJIlly lb,-nm,od oin ridunll arcirual,�, in 2025, d ]e followlingvelik e^Aquilipin-loint nii c sr ledded to I I * 1111M 111 11, 11:'ard I I11H y IL Nylhrid $64,000 * 1111)# 111 1'E 11:oird 11 scape $49,000 1111711 111 19 11 ord Utility 11 Nybirid $64,000 11 D# 111 20 11 aird p killity IL Nylbii fd $64,000 1111 M 111 21, 11 oird Udllky IL Nylbrid $64,000 1111M 111 39 11:'ord UdIlly 11 Nyhii A $64,000 11 D 8 111 40 IFaasii d Utility li Nylbii A $64,000 11 D# 23 birdl UL11111 y Ih Ilyl1birld $62,000 1111"p# S 31 bird II Aplorvii Adiii-ilin $62,000 f he 16111owfing vehides(nave Ibea,.rn carrkd ovor fil t1he 2024 to the 2025 Lou idgeL a-, 1,11hey Wore wriavallable roir pluirchw,le hiroin Gerri-all IAoLaalra fin 2023 iind uMgflin fin 2024 * 1111 W III I Chevy fahoe $69,000 * 1111N� 111 2 Chevy fahoo $69,000 :1011w 11 ritell"cel-Aar 11:;:Xjjploror 11:"oi, d FSCl 30 111 13 ("SO 11 ,(,ajI �� )CtaHs 11111'0tecf I'lluinher Accountl 11"Niumbeir 11111-0jecf II A, sustalin,)1bifil'y Chevy hilhoe Dodge Xiiiango 21, ll -W 000/0 061.60k 9000 1/08,660D03 U,cjpladillg IL Ilylkolrlid 11::Xjjplorear shant rlwll savill-if"S0140%or hlglheip Wfilh less d1eirlininfI14" bale'llind 708 11 qijijjpinneirlt: IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 299 priorl'y I Ckwall Suawgil Goall Goall 1 11 [fective V111agQ GaVC11,11-1111no-11L 11 fil arld,311HYSOU11 id, 11 NCUjl)tk)1llla11 SQIWIC�� NINUMMAMM? No Justification It K the polky of TeVOge of MounU4oqpcxt GqmnAdesF;0vA I h he todh nomled to palmin thichr dnlxilila uinrf safe numWnhomw dw MON 412% Umm aUWAMWH &kWh my now sun Md molmom aulpmard w=alkl homW KwAnadch0whad of Me VINge an& wM to behatAfed On to mooll ma nmkd i rommHn Hdr plmhah, Wmatlon wd A mminksing THAQwA ukta EM vAWe v&Mr Onm 5 c1donmt As a mabn of Set R hos a smWe HN, whkh Is Lhe amounAlf lfrne -avelilde tscajpableail safeseivice. IIt has a Lechnolog"lCall Iliffe,aAdhklh urcjpresons HN= rdallive tlhr.ull lit aS C01[`11)a1,r.q1to avniver. ir7rawry ds n4oA li-inilpoirLwdy A hw an mmmandlearch K N Hon hyb Of AwAw wxMe AW wMdr,'i CM1`101-ShIllp COSt iv tairiroion0iivunro. Operating Budget Impact dle cull reirlif 11rvd(ik avaflability of Vfdilides IlKvcaiusrM us o exllund Mcllife usalgQ i'k uur c"'a lent vdlldcl his resulk hn del-g^r rnafnkmnai ve (osLs Cairo domume of vokos Rmwe MMM. W Ms, O mphlrs. Inflationary Impact no qoo A@ unts 0QNKg dmal% Wks, waly have aved mally IN Village of Mount Prospect I FYA25 Community Investment Program Requests Page 300 Capital Cost FY2025 Budget $695,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $2.2861M $0 $200K $4001K $6001K 1111111111 E..�qullpirneint Puifclhase Cost Project Total $2.2861M $695,000.00 $442,,000.00 $385,000.00 $448,00000 $3116,00w)o Capital Cost for Budgeted Years TOTAL $2,286,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 11(Jullpirncirlt 11311uirdmse Cost $695,000 $4,12,000 $385,000 $448,000 $3116,000 $2,286,000 Totall $695,000 $442,000 $385,000 $448,000 $316,000 $2,286,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 301 Funding Sources FY2025 Budget $695,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $2.2861M $0 $200K $4001K $6001K 111111111, 0EA VelhIcle Replacement Fund Funding Sources 061.VclhkIle 11�ciplacci-nant 11wnd Total) Project Total $2.2861M $695,000.00 $442,,000.00 $385,000.00 $448,00000 $3116,00w)o Funding Sources for Budgeted Years 9 061'\Iehiclo, f:::und (100%)$2,28G,( TOTAL $2,286,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $695,000 $442,000 $385,000 $448,000 $31.6,000 $2,286,000 $695,000 $442,000 $385,000 $448,000 $316,000 $2,286,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 302 OveirView lcroepuuc> p, Owner 11 )ell aa - tilliell pYjjw [)c S C 11 � i P 1: i 0 In Kevhn Dekxa, vellide NlaliriteilancrSuj�,wri n oiridq!lrit Vehicle 114111111telural" we Callpil'all hillipiroveirilielit 111elplaceino-H of I vehide,, and equijjpinliieilll, Arl I -mall ve hlldrl Ileaso PaY1aI01,1LS III -r calculaied fm each velikle lbased oin U110, Hie or iillereM, and thievehilde acumint halalv:e. rhe vellide case payrnnints are reralrAflated annually has(ql on, arAuall accrimls phis iollowiilp_, alre s( leddcd to Ikea relplaced: * Il,ti.ua ret Year 2025 1111 )# 305 Vain V Scrvkr,�s) $55,00r) * Bludgd: Year 2025 1111 )# 303 11 'ord , cajpe (Corninnurally 11 )evell,I)Ipinnont) $46,000 * Ihtnluil,rA Year 2026 1111:9# 300 (Ahevy hhoc (Village Adirdii lisration) $ a8,000 * IBudgrA Year 202/ 1111 )# 324 11 ord 11 =,e„aluc (Clorni-ni.inlLy 1Developi,nent) $46,000 * 111,udgrA Yrn-nr 2028 1D# 31A, 11:'ord Fscijplp, $4(,,wo I irn a ges 11 Ord 1::SCaj:)(_, 1110oll 11),oind. i4lurnbor Account i4i.ji-ribrq 11,11rojod Life ( a t egry F111 ioll hy St lraLcgk. Goall 11% t11iis Grairit iiuirlded? Justification Chevyval t W IN 2021.0hevy 'ahoe VIIA vellhicle :'19..11`"W 00072 061.219 901:'t0 1, 7011 660.011,061.20 °11d,00 1, 708.660 012, 001, 40 90.00.1.708 660.01A 11:10011 a anirin on a 10 Year leplaceineii t schedulle 708 Ihiu Ihcs,/Autonn(A live 11 quipirricirit 3 111-11111pollard Goall 1 11 [fective vfllage Govell-1111111ol-11L 11:°hri a I all 11ySould, xCeptill)II-lallseirvke llp o 11t k; t11 le policy oft he Vill age of IAruaun4 I lirospect ii,i[iairui,ue.i,.Aiinoiiigtill i(u tool N helphi ll"°t thell-1-11 ,K„Co1­njp1N1h thnlilrtrasl(,, vire, III vrdlldcand Inrur,AOrflzed equilpincint sulbr,tvnlJall rinaridall riveFU1,1[leiril. oil 11 lxdl lalf oil ("a onarlicall all of i mr? a wd-ilde k capable of rol-I&I-ing `11-1 efficienil and safsnrvirx111hrasaspauti°:II`oiraerllogiirnlllliife,vrlhiiialhire,^Ilnrese,uopst11le,ire,Il;ap:uvealprearlraeiMHYeUer-ealiurle of t fil ne the aver age totall Vehicle's owrle1 IlnljpcccIe cat ,'oumfiuofiunuuau"ire. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 303 Operating Budget Impact Norio, Inflationary Impact veell(ia,lleprllr,esarerwi:illl11vollaUllernriI:PIIIIIInruuCaaa,tatraafillal iIIGt, and'1lll1aaallllallller::rinbrTur,tprlir.Iling, Capital Cost FY2025 Budget 1. 1,000 Capital Cost by Year 202" 2026 2027 2028 2029 Total Budget (all years) $251.1K IK G:::a Ullplrrrment IP ulrclhmase Cost Project Total $251.1K $'58,00c o')o 46,000DO Capital Cost for Budgeted Years IV I::::cyt.sir;:rnric°rYC Pc.arc.P}sisc., C:.:cx:;t (IC'iCY%} $2,:>1,000.00 TOTAL $251,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total quII ;YIf"Ifllc int Puir4::lhast C4:D,:'t $1,c)1,000 °'ia,".)8,oP. o iV'A4.6,000 $46,000 $0 $ ,.!,');1.,000 TotalV $10,000 $58,000 $46,000 $46,000 $0 $251,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 304 Funding Sources FY2025 Budget $1.01,000 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $25 1. IK $0 $251K $50 K $'751K $1001K 111111111, 0EA VeNcle Replacement Fund Project Total $251.1K $�m'000no $S8,000.00 $46,000.00 $46,00000 $,0000 Funding Sources for Budgeted Years 9 061'\Iehiclo, f:::und (100%)$251,00 TOTAL $251,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 061.W17ik1c 11�ci4:lacci-nont 11::�wnd $101,000 $58,000 $46,000 $46,000 $0 $251,000 Total) $101,000 $58,000 $46,000 $46,000 $0 $251,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 305 I�)UlWlic Warlks Veflhi(dleIIID Ow"Irvkw kxqiue,,dOwiliell, Kevfin Deluca, Vell-ildr,I III tenanc(supo I, inteiridel-it 11 )e1partil 11 lell vell-iiia Ile Ikdallitellairice dYjjx' ('"allpil'all II iiiii1piroveiriiielit [)c5clipt iOin F1,ejFAa(,e1noH of vIdhlde.,Anniiall vel-ilde easse payllne'llik ror on the lleofdhe Ulawh Ig aire sliedulled (a lxr ii ojplac`,ed� * 1111 ) # 71533 Nirco Leaf vaoinnin F rafleir $175,000 * 1111 )# 45 38, Klaijr^ir Sinow 11111(wvnir sll,ir) m $1.9o,000 * 1111) # 4A 3 dowiinAA.eir h-aileir. $20,000 * 1111) # 4 548 E raddle-," 114 d $1,90,000 * 11 IID # 4553 )ropDieck flr,-dl(�ir $25,000 * 1111) # 455d 11:�nrd 450 HIN g,: e. St alke L -Indy 1,11 UHL $95,000 * 11 limn # 4558111iroWcOlLoadeir Fuck, $28("J,000 I �c lollowill lig vell Idle relplac einneii Ks ,airs: caii I ied oveir firm n d Unna 2024 IkauuaVgd lo dhic 202'i Ilyu.ucllgO as t 11 icy weii c not ava111ra1ble Iloi I wase !!I 12024, * 1111D#272d Ili turiOlonall 11:1,Albcd Aft GM,c firuck $1,60,000 * II Ila # 2/38 WCt011 flLU5hQ1`b` MR $33(),OCK,� * II Ila # 2/40 * 1111) # �52/ ii-Aeniationall dul-11111p bruck4x.2 V Sjpir(-�adeir, Scirajjlxsir 11111ow 11 Irani, I'llow, AI1111111-), $2^.400() * II Ila add4528, 1111ow. $280,000 4"'a2/ Sall h t ruck uindeirlbody plaw,wdl � and bidine saJpreado-;� and w udeir body liallaaw, j all L aind 11-.wlinc, sjpireadnr^u, 2124 2738 2740 Durrip Lirudk firont JrAOW, Andleirbody top 452d IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 306 4533 1" H CO II MY V,:KUUIrQ A533 flaucir Sino Blower /id Mchirnnot SINO GO 4543 PnAn-insfor Hlk, firailo( 4546 hamns Ill f 4558 RMN WaHr DoWs 11111-0�ec[ l AccrmnL Iylli.anrmlbeir 40>1 We catogwy ITOMY SU Ad" GoAl ku"Quuwndw? Justification 450 Ewwaw Upkir 455/1 larrIll 35011.flftgate timck 21..11':"W e311069 061,8,0�90.00.1/08 661b.CM6 Pu vnhkk rqAwanwnt pdky /08 Ve1h1doVA.0anmHve hqApwrfh I CANI God I h AcAe VMMe GoveiriniTieinM11 filan(Jally Soull id, 11Yu,ejptlarwll seirvke "lo 11 t " t1l le pallcy of d he vfllage of Anjin t llirosjjpr,d lo l staff wN,11 i O he toolk, needed to pcirforin u helir dolbs 'ini a jprolr,sa,k)if o all, connl-y,-'I�eint and �,afc manrwn Awwd; Om tools WQQ Hwm ammAMW And WK mT W w vAHn W moWAnd eMomm, h wdlHonj&W wmwqwmoW a ,au MAKU &wwW KwArnenk on KIWI H a VaNgn wn?wwd to bMlmdW In Sm "WommakA mmmu WANOWNW& qmQbin W In rn&mWVKdMNWW vAn QW6 Ode andAr plince of eqWpment hws a rwmberaHKeT R Ins a smvke h0whkh N the amcwkW [One avehldc lsc'Alpable of wt wKWHm a Wdmabgk;0 Hkqwhkl-[ rej,areset 14s thc rdallfve Ohe usu H, w;(,annipared to anmm,,i-i-nrxJrfls. 11\4wt firnpark0y R hw an mrnomule & anal 5& am IWMT d UmMln wwMe &W whWe's IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 307 Operating Budget Impact f he cul, I-( �Irit ac k iti avad a �,Aiiy of Vehicle,; ia,� i is keep ourrent Vehicles ol-11 the road o1q,"cli. f he"o volhicles a im ex x �11 ioncing highell, rilleAgr! airid hirmv�, of I uSe, wh c 11 ]1 callI i u n 11 lighei, innohnier a ince cosils aind downtlinne for exLerisfve allid possilplf� coslly repaill `, Inflationary Impact Oil k1le ccsfof ainid ariet essairy qpfittingcosks IIndvesignificanfilly lt(ron i over tlhielaM:year" i llle and telir, Capital Cost FY2025 Budget $2,225,000 Capital Cost by Year 2.025 2026 2027 wi Total Budget (all years) $5.8241M 2029 $0 $6001K $11,21M $Izilo Enquilpirnent. Purchase Cost Capital Cost 11:quflAran inl PiuirdhascCoM Tota ll Project Total $5.8241M $2,225,000 00 $872,000 00 $�)3131'000 o $1,574,000 00 $220,000 00 Capital Cost for Budgeted Years 11@11 E.:quipiTwN,ir. Purcha,,o Cost (1C)()w,)$5,S24,000 C TOTAL $5,824,000.00 FY2025 FY2026 FY2027 FY2028 $2,225,000 $872,000 $91113,000 $1,574,000 $2,225,000 $872,000 $93,000 $ 1,5 74,000 FY2029 Total $220,000 $5,824,000 $220,000 $5,824,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 308 Funding Sources FY2025 Budget $2,225,000 Funding Sources by Year 2025 2026 2027 2028 Total Budget (all years) $5.8241M Project Total $5.82411\4 $2,225,,000 00 $872,000 00 $11,5 74,000 00 2029 $220,000DO $0 $6001K $11,21M $l1.(; IA 11111111111 0EA WhIcle IRe1placeiment If und Funding Sources 06].1/c1lhkIle 11�ciplacci-nantll lwi d Toulli Funding Sources for Budgeted Years 9 061'\Iehiclo, f:::und (100%)$$,824,( TOTAL $5,824,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $2,225,000 $872,000 $933,000 $1,574,000 $220,000 $5,824,000 $2,,225,000 $872,000 $933,000 $1,574,000 $220,000 $5,824,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 309 uuu uuuu uuuuuuu uuuuuum uuuuuum luuumuuu uma .m�m mum uuvuuuuu uuuuuu uuuu uuuum mu uuuum 111111 uuuuuu uuuuuu .uuuu m IIII II .uuuum .uuuum uuuu i. uuuuuuu h uuuuuuu IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 310 VilllIlage III iiinager's Office Conference IIIIoann cNavow RNWM omwil, I w"WHOW !MXW"UWWwc Qpwhnen H Qpe AnriAt nilaiiiir, )ircctoror ii:fiiance 01/01/2025 1w31/zn5 VwMemauvwsomm ("alpiA,111 II lill1provenrleint AsApthn WWI UwWyc MmuWA C)Mce had to conved'soar. or 1,11he cesHing coinferenro rooms &Loan of Yarn Npon Am mmo AW "MAm RwMbgre MmRw"s 010m As 6 wed ch a mduence mmm ho"wAN mmknp IIIe exis(III ip ecwk rcan can be InWvnxwd and u54 d as a canirwr e nxwx Ws pin:nllc,ctwllll conveiI thlevault al -ca Anto a r,eanreirenrun;en ooin oin the Ohli-d fllbi:,i-. I iFnages Dchik 1`p 11 NwAwr 25 VMO U1, Account ',Jwinnlrair 020.80.90.00.0.706 645,020 1:111r bled 11.1fr, 11"llo Cafle,gory 706 nnjA-w0V0111Cllt� 0 113dbfic 113liddlings 11,111011rhy 2 Very innjpoi,Aainu sbrategAr, Goall Goall I I Ad Ne Wmp Gwernmmd; RwxWO Sound, 11 Xcejplfvninlall Sell vico 11 s fll lis Cii-ant II ljinldrW Wo Justification Rum WY Or VMage Ma11 ozWT4 OMKOwd to m wuWw & U w eAdh q value Ke mono Mu a; mMm Vase A� a wwy added "Atban, i lhuce Vl1lage Mainagell's Ohilcv-,is ill 11 riccd of ,[ coirdereince ircKn n Moir varlous i-nectlings. L he rrktlii 1F, Ire cvni[ r1 I, oUr[ri C"A111 be 11-cloAA11-posed aind used as a conro I, rince Ill 1[11. I h !I s Irp11 OR:rcwflll (onveirk 11-11eva I All t Blare a Unto a conreire'linx., vorsin al 11 Lhe hIll !I ird floo I', Operating Budget Impact Nme. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 311 Inflationary Impact Noire, Capital Cost FY2025 Budget Total Budget (all years) Project Total $1.00,000 $1001K $1.001K Capital Cost by Year 2025 $i00,0MOO $0 $251K 5; 501K $751K $1001K 0 CO: rISUIJCT!10111 COSt Capital Cost for Budgeted Years 1111111111 ConstrucLion CosL (10/0`/0 $10(.),(.,1o0.ao TOTAL $100,000.00 Capital Cost FY2025 Total Cons, bi uctloin Cc0 $100,000 $100,000 Totall $100,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 312 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year RM Total Budget (all years) $1001K $0 $251K $501K 020 Calpitall llir>rnl iroveirnint: IFUnd Funding Sources 020 Callikall hrnlpirovonicn41wnd Totall Project Total $1.001K $m0,000.00 Funding Sources for Budgeted Years 9 020 Capit.al IrnprovorncnC i::und (100%)$100,0( TOTAL $100,000.00 FY2025 $100,000 $100,000 Total $ 1 oo,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 313 uuuuu r i uuu uuumu uuumu a uuuum�u m I uuuuuuu uuuuu uuuuu uNl� u„I IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 314 Booster IVIG umnlp Statian Illi iiillmwgIII cNavow Requem Omer (.a,;r�y 11150 Sinperildoindelifl, lubfir wodks,' !kPmMifl sun my Amni, "w CAAWHmWownnfl DcsadpHon Wntmmmy mW ;WWWon of Me VTUgpWvmNHnWAgh wKe nmmps, Wages I hgh SaNky lkw,drr Pwnl,.) D(A41S 11111'0t cl, 21. II)W 00009 Accoui,A 111uirinlbeir 050.80 90,0(),1,/00.66!Y,05),1 11111'0tecl Iffe 15 20'Yeair,, Category /0()Wate1[ SY'Aol'i owly wwry h"Mr! allin Sbral.egk, Goall Clocll 3 pojc Q1.m1fiy Vfllage lllnldranpu inctuire: I Wuxiwd WaQ Ne CoirnirnuinHy investinneinin. Is flhN Graint 11 ijincled? 111,110 Justification f he vfflaeOhive (5) boosteir OMAn Krum W%m ('V5) h1h myKe pwmps Waka;Ve 0 Am hym 15 HP W IM)hp An mWe amlts=r am Wo N qmcU moat kwo en h wmp W rxDmmend overhoWs IKared on WN 0 j wMannams wzWo"wWd WWW jouhqwlil knclude�� Ll ic rc.nncwfll of each pm np and WcAlk m= pmp dhowmby W nqnAr mWw testin, ; epair Wwpkwonenlrwcanbo and re fin-AallalJoini Ileo geii aora 11, 1-cIp"oll, r, 11 ave beeii i uraino j i g firorin $25,000 Lo $50,000 Dci, assei nll)ly: All 11 'notoir rejja11 aron nr,.i o�, 44111 u,e a pireirinfuirn el fidont 91 Ile Iniurat:a�rlr. flienxjjpcled use=Aor a h"hsxvkMWmpwW nwhaNs 20yems. Operating Budget Impact AIto al WMawma wst, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 315 Capital Cost FY2025 Budget $225,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $1.1251M $0 $601K $1201K 10801K 1111111111 Construction Cost Project Total $1.1251M $225,000.00 $225,,000.00 $225,000.00 $225,00000 $225,000DO Capital Cost for Budgeted Years 9 Const.ruc6on Cost (100%� $1,125,000.00 TOTAL $1,125,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Cora Airucboin Cost $225,000 $225,000 $225,000 $225,000 $225,000 $1,125,000 Totall $225,000 $22.5,000 $225,000 $225,000 $225,000 $1,125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 316 Funding Sources FY2025 Budget $225,000 Funding Sources by Year 2025 2026 vzwm 2028 2029 Total Budget (all years) $1.1251M Project Total $1.1251M $225,,000 00 $225,,000 00 $225,000 00 $225,000 00 $225,000DO Funding Sources for Budgeted Years $0 $601K $1201K $W1K 050 Wat.cr and Sewn- Fund (100%)$1,125,000C 1111111111 050 Water and Seweir Fiund TOTAL $1,125,000.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 050 Water and Seweii 11 und $225,000 $225,000 $225,000 $225,000 $225,000 $1,125,000 Totall $225,000 $225,000 $225,000 $225,000 $225,000 $1,125,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 317 Operational Costs FY2025 Budget Total Budget (all years) Project Total $2,000 $1.01K $101K Operational Costs by Year 2026 $2,,000.00 2026 $2,000.00 1111111111 ninu.aaall Olpeiiafloivaall Cost Operational Costs for Budgeted Years 9 4nriraal C:Ypcmi or7al Cost (100%} $10,000.00 TOTAL $10,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aniirnu! aIll 013cii atlionall Cost $2,000 $2,000 $2,000 $2,000 (;2,000 $1o,000 TotCalV $2,,000 $2,000 $2,000 $2,000 $2,000 $10,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 318 CaInImbiii ned Sewer cNavow RNWM Omwir 11150 Sulpo'hilloil](joill, lubfir woi(ks,' Delp"whillelifl AWWWAMor "w CAAWHmWownnfl AsApHoit WqW WK mMmo. inilin Ilivalc °;evvur„, a1llrjm';oC!'Ae(j rhi urhAlles fin colinIL)h1le(I Sewer ^xmrvlr'e all, I moges szwlltary Sewell- 51130, 1ejplaciincin� of old dkiysanfl airy xwver Withl FWWSIDIR, 26 WC 11JI11)0 x...1 cadoIrV lrojod '4urnbor 16 :1W 00027 Account 11",11wirrilbeir 11:111rojed IIffe Annually Cjai P'°gory 701, S,-unk,wy 1:11110111ty 1 O'HR'�ill 1a1rateg.Ir, Go"�11 Go�fl 3 I bjp Cjl,mlily Vlll,Ie infirash ud urc: 11141ance(t ;,Inrt lrnrld ive Col-11111`1111LA1111HY investivolill, fll fl'i Gir;�nnt II:Ilj11lflfx1? Ill Justification 111 o 2015, 111 le AIll<ige roii ldlx.tcd;u cainrilblirierl 5,oweir 5p= m An& U a m oysts h Wed U ic QW9 g oksmUmd wwe"4WmAmWAy 201000 IQ WM I ms W beun R4 WIRMW ad jKmMW a wWWm awamn I AH md" wWnmU moral gNm a cmdWa "Whg rMh 5 befiw,' the vwx'M'311 id 1, Ibeling 11 lear ljerfed, jj")'ljpe. O 11-K, An WhAdw mpT mer a 15 jwqxiKdJn 2024, I qWm wlH W HMUW W Ww,s mkWry 3 mAn NAw ll,, T"mmNl owNs MM MW hw Km mhWlltated� a 5 100%cmYAWUV11S 15011) o 4 100%cmnAKkPMY148 W! H) * 3 94% carnplele (4 1,818 0wall J:) * 2 80% coinplele(19,528 116usfl 11.1) 1, Seven 1111pe segirincints Irpi^I ImInkg to cmnoete (2A34 fWaH I 0 10W, c,ani-ple[c (":0,638 116L -fl 11,111) IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 319 Operating Budget Impact Annuall ffl�A7P0l,)HCC COSL Capital Cost FY2025 Budget $800,000 Capital Cost by Year 2025 2026 VAGM 2028 2029 Total Budget (all years) $41M $0 $2001K $4001K $6001K $80— C(w.)struction Cost Project Total $41M 00 $804 D,000.00 $800'00000 $800'00000 $800,000 00 Capital Cost for Budgeted Years 1111111111 ConstrucLion CoSL (10/0"X") $4,000,()00.00 TOTAL $4,000,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Coinsb[ [J(1 1101in COM $ia $800,00 $00000 8, $8 00,000 s'l'000,000 Total) $t';010,0()() $800,000 $800,000 $800mo $800,000 $4,000,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 320 Funding Sources FY2025 Budget $800,000 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $41M Project Total $41M $aoo'000no $800,000.00 $800,000.00 $800,00000 $80o'oow)o Funding Sources for Budgeted Years $0 $2001K $4001K $6001K $80- 050 Water and Sewoi- Fund (100%)`h4,000,000 1111111111 050 Water and Seweir Fiund TOTAL $4,000,000.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 050 Water and Seweii 11 und vmo'000 $800,0oo $800,000 $800,000 $800,000 $4'000'000 Totall Jwo'000 $800,000 $800,000 $800,000 $800,000 $4,000,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 321 Operational Costs FY2025 Budget Total Budget (all years) Project Total $1.0,000 $411K $4 1. IK Operational Costs by Year 2025 2026 NOON 2028 2029 $0 $2,51K $51K $751K MIK 11111111111 Aninuall Olpeiiafloinall Cost $m"C;0o.00 $m,000.00 $T0,000.00 $ 0,000 00 $T,Oow)o Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $41,000.00 TOTAL $41,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Cos� $1.0,000 .$1.0,000 $1.(),()00 $10,000 $1,000 $41,000 Total) $10,000 $10,000 $10,000 $10,000 $1,000 $41,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 322 II eqp W6I1II WdIlII #1 6 cNavow RNWM Omni' DcsadpHon MMrOmmmy mW I moges (,".asr�y 11150 Sinporildoindelifl, lubfir wods sun my Amni, CAAWHmKownnid INAAS Locatioin 11,11roject lquinber 16 1111 00OU Aecount Numbeii 11,11roject Il Aff, 20 yezan Category /00 W,'Bteir SY'Acrin 11111-loi1ty 3 inilljoid,aint stirategk Coall Goall 3 �ojp Qijali(y Allage 11 n4 rashructuire: Balbinced and IN difsGraint 11 i'llinded? 11,110 Justification I 11 w Vfllagre's [wo (5) deelp wells worr �X'j, rr;l ialbill imiWd In am 19%Ys and the hAmUy mawwnAvd AMA N 20 yeary F he rduNAMbin ploce"'s 1 nJudes Indliling Or deejawelll cohninin assuirrilb wd NmQwmhAjdwhbMm d NnpecWq Um ampm mks and mowl I wTepaMrg ainydefi(ininLul d0ectivf.pwty I hiscHoOrAH Nwo% one O)deq)weHewTyuU-nTyeu1DcaKk We when H my A ham !men dNxkaL I he RAllowhig, k a dk-a.ii fijpflon estffl-le W011 Ile:: * Mobillize, 11HdIl pulinip and hn,,JjjeaA * Rome WAH-Mle Annemwe, dwn M 0 hqwd U -n P=111) vo 140 air Drhwir � est "nid rcj.",Air est,rjo(AL 11"elplace esL 1,00 II r. (olunnin as<�aaibly 11"("InMall, C11 doir al"fle, dernotAlze, -'alln1pling, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 323 Operating Budget Impact 11101111e Capital Cost FY2025 Budget Total Budget ((all years) Project Total $535,000 $53511 5351K Capital Cost by Year $0 $1501K $300K $4,50 K ConsLrucfloin Cost 4�1� ConstrucHoin Eingineeiri'ng 41P E)esign Engineering Capital Cost for Budgeted Years Consuuc:Lion Ccx.,L PTX,} $S(:x),0o(:x(:4o ConsLrucW.m F_nymeennc.3 (4%) $ 0,000 0o DcsIgn E.:nginccrlrsg 3'X,) $15,(.)00.a0 TOTAL $535,000.00 Capital Cost FY2025 Total in 11Ingfinccirfirlg $15,000 $15,(xx) Coinsbrucboin Finiqdnec,11,11111,g $20,000 jy20,000 Coimbrucboiri Cost $500,000 $5()(),()0() Totall $535,000 $535,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 324 Funding Sources FY2025 Budget $535,000 Funding Sources by Year INME Total Budget (all years) $53511 $0 $1501K OSO Water and Seweir i::: und Funding Sources 055Watcii aunt Sewcirl::�und Totall $300K $450K Project Total $5351K $s.T15,000.00 Funding Sources for Budgeted Years 9 OSO Wat.ens and Sower IFund (100%)$53S,000 0( TOTAL $535,000.00 FY2025 $535,000 $535,000 Total $535,000 $535,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 325 andIIPafintfirlg ow"Irvkw kxqiue, Owiliell, Delpartil 11 lell 1Yjjx' C:i,,sl��yIISar teirinain,Waleir/Soweir SulperfillendeliM, klblkwodks ftfl �,r airid Sowni, ('"allpikAl II Irlr'oII',alrurveiruoa^II"ot )c5ciriptiolin 11 irv;1pedJai ii, I a,ind coaa fii ig, of inteirliai und exteiJoii sul, Nwes of 1,11 ip (devated waf eir stoirage Ginilk, kxa ed rut 2(Kf11 wi( gir(i�in Ave. I inniages 11,11roject lquirdbor 25 ll 1W W006 Aacount llaUuinnllbeii 050A(190,00,1,/00A/1,008 11,11 Ojed Aff" 15 YII:A116 categoi,y 100W"Itell. SYAorn 11,111ol-hy 2 Vell Y 1111-1-111poll Laint Strategic Q�;oNl ("icall 3 lojp Qil ali(y Village inifirash uctuire: 111,al6nced,ind IlVeStllllell lit IN this Grairit 11uiided? 11,110 Justification MaInLeinarce d "VaLer "rLoiragp Lairilk", llw, fle(xuss,,iiry to innalirll,aln anifl,airy ,x)indldawand pirew"Irve "Ailuduirall III Aeprll,y. 11 X1SlJng Water Stol-ago ca1mcky N III to sn(Asfy 1111FIFIAmi id JAWA roqo lrornord!7 airld 1 50 hilic I'Mill W"Al'or ta+rlks arr hlllrJjpecl[�A airld oin a r(Aadil If, LuwAi, 1his I eseirvchi was la,, l rell Fflbflhllated and 1-palinted in 2,015, Operating Budget Impact Aninuzill ii-nahMenunce co,,As, Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 326 Coinsbruc,Hoin co�ks haw!I if oCii,eased 30% lintl-w as I: yea ir. Capital Cost Total Budget (all years) Project Total $81.01K $8101K Capital Cost by Year NM W0,000 00 $0 $2001K $4001K $6001K $8001K constructloin cost 41 CoirlStiru(AlOirl IE inglir*eiring 4@111, E)esigin Engineering Capital Cost for Budgeted Years 0 Const.rucLion Cor:,L (86%) $700,000.00 4W Consl.rucUon E:n9meering $7,15,000.Oo l DcsIgn E.:ngincc6ng $35,000.00 TOTAL $810,000.00 Capital Cost FY2029 Total Dcs�gin $,-35,000 $35,000 Coinsbru(boiri II nginccilinqg $75,000 $75,000 Cloinshnuhon Clost 11, /00,00o $1oo,000 Totall $810,000 $810,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 327 Funding Sources Total Budget (all years) $81.01K Funding Sources by Year INIM Project Total $8101K $0 $2001K $4001K $6001K $8001K 0 oso water and Sow eir i::: und Funding Sources 050 Water and Seweii II nand Totall Funding Sources for Budgeted Years 9 050 Wat.cr and Sewoi- IFund (100%)$,810,000 0( TOTAL $810,000.00 FY2029 $810,000 $810,ow Total $81.0,000 $810,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 328 Operational Costs FY2025 Budget Total Budget (all years) Project Total $1,000 $51K $51K Operational Costs by Year 2026 $¶,000.00 2027 $ ,000.00 2028 $000 00 2029 $¶,Oow)o $0 $250 $500 $750 $UK 1111111111 Aninuall Olpeiiafloinall Cost Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $S,000.00 TOTAL $5,000-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 013cii atlionall Cost $1,000 $1,000 $1,000 $1,000 $1,000 $ 5,00o Totall $1,000 $1,000 $1,000 $1,000 $1,000 $5,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 329 IIIIC°°° will rvlew ''Aar ns Ovedlhmad Sewer,IIC�)�rogrann Oveirvk,,w kx'cpjo�d Owiliell, Cl".,i,;r�y 11150 Sulporild oil Idell I I, kiblir wodks, 11 )ell a - tilliell ftfl r�r all lid Sower lypo Cqjpil-a11 II illipiroveirilielit )CScrilpfloin p"'heConverr,ionorIpropnrtirdIles,IlaaraoDedillIifle 11alhrvinvv Gardeirv, subdivision lfoIwwo, su"'ported direft fooking, Ole coni-Kxtlonr M Lhe vlllag,cs' s,�nllfl ally "ewell, hw� r:o1rill,11 L)W inry cle,11-m,fl ('11' lo I'lic 11:'nflrvlcw 11 lh Sil"Mion, I Irni'aples �I )(AaHs 111110ted 11"'lluiriber 23 II)W 004 Accoui,A 111wri-illbeir 050.80 90,00,1,/01.6/2,001 ,ro�ec� fre AiiiluGilly ("c tegary /01&ulltarysy�Aorn 1:111,fori9y 2 Very iinijj.-joirinn� Stirall.eglic Goall GoAl 3 iolp Qimll uy V!11,mu nifiraAii ucbjre,: 11 lakiii wed and lroad ive CoirnirnuinHy inivesbilnenill. I^; d Ill GraiN 11vinided? III Locadoin Justification 11wa �r t 11 la L d kdl ar � �es ill � Lo 11, l -v a Vill 11 apas' sa rd I'all Y vnvai ill I oll dar t o III[ leet I'l e Mehropoll iLaii o Wa Ler wakn iftSt;)ticiri. Operating Budget Impact p,educed puirnping c MmAffort1ha¢IlfIN sG.Alori. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 330 Capital Cost FY2025 Budget $470,000 Capital Cost by Year 202S 2026 2027 2028 Total Budget (all years) $1.881M $() $1201K $2401K $3601K 111111111, ConsItruction Engineering Project Total $1.881M $470,00:307.00 $470,000.00 $470,00000 Capital Cost for Budgeted Years C.onst.rucLion E.:nginooring (100%)$1,880,0000( TOTAL $1,880,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 Total coirrAirur"Ibloill 11 : 16111' I'll C011 11111�, $470,000 $4 70,000 $4 70,000 $,l 70,000 $1,8f,; O,Ooo Totall $4,70,000 $4,70,000 $470,000 $470,000 $1,880,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 331 Funding Sources FY2025 Budget $470,000 Funding Sources by Year 202S 2026 2027 2028 Total Budget (all years) $1.881M $() $1201K $2401K $3601K 111111111, 050 Watpr and Sewei� i:: und Project Total $1.881M $470,000 00 $470,000.00 $470,00000 Funding Sources for Budgeted Years 9 OSO Wat.cr and Scwor If und (100%)$1,880,0,00.� TOTAL $1,880,000.00 Funding Sources FY2025 FY2026 FY2027 FY2028 Total 050 Water and St ward 11 und $470,000 $470,000 $,470,000 $470,000 $1,880,000 Totall $4,70,000 $4,70,000 $470,000 $4,70,000 $1,880,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 332 VIIIead Wateir, Service I firile couvow RNWM omwir jx�oiri 11,611b, lublicWark", Departinnonr AWWWAMor "w Calpirall II uuoIpiroveiruoa=int AsApHoin ReQuinaw Whad wauTwOm IWWW25 and 2021 therwoRmtkallocaNd $100p714 raadgeav For had smWelAw mahmmmonlAwe WMm. Shirdingri,0027, flicallocaflaill k flhecostto rejnlarx� 10% or 70) peryoar I moges DUAS lrojorA 1114urnbr'i, Accouiq9: 1114win-flimir 11:11lojec9Iffe ca�egory whrhy Slahjc G&I 11 F, flh!�, GraiN 11vinded? Justification 2211)W 00093 04 D.M047.1MAAM.672.008 I'll/p, 7001MWSp=i 2 Very 11 rinlura rtaint Goall 3 1111011'risbrii chjre. 11 S,nainced,nnd Iii oxu flvc Corninminity investrincii H. ',4o n w SWW W HK wN k 6 d w Immms at rwvsimob. d ow,L.vaar4 Sm We Lhe 1W)bammA m W N"NAW"W, and iclli 4111 requh e wateii WrIhies O,o 11-uplace had watell sor vicc Wn h om dw main W H a waWr meWr, H a Wqawd WH Mdmw pWal BW M w MAmmmM wMS only reAxe ke Why wated Ode or a WoWe We Wing h0unownwN Air wat I he Village N cunwlly mnobikq Urm pman oHnwWging MI ead wi'vicc fil ow, 4o date, (1-w Village has iinv(�i)Wirko.l apWox&mUAy 74.14;91h and wivice Hms. Operating Budget Impact No hidga inn1par � IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 333 Inflationary Impact Coinsb, ud ioiri costs have i Increased 30% oveir [he Ilrstyear. Capital Cost FY2025 Budget $1.00,000 Capital Cost by Year 2.025 2026 vam ISM Em Total Budget (all years) $2.451M $0 $2001K $4001K $6001K CorlsLruoilcan Cost Project Total $2.451M $i0o,o0o oo $ioo,000 00 $750,000DDD $750,000DO $750,000DO Capital Cost for Budgeted Years 0 ConstrucLion CosL (100%� $2,450,000.00 TOTAL $2,450,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total (�cxnsbrucdoin cos� $1.00,000 $100,000 $750,000 $750,000 $750,000 $2,450,000 Totall 000,000 $100,000 $750,000 $750,000 $750,000 $2,450,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 334 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year 2025 2026 KDON sm Total Budget (all years) $2.451M $0 $2001K $4001K $6001K 111111111, 050 Water and Seweir Fiund Project Total $2.451M $mo,000no $m0,000.00 $750,000.00 $750,000 00 $750,000DO Funding Sources for Budgeted Years 9 OSO Water and Sower IFund (100%)$2,4,.30,000. TOTAL $2,450,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 050WMciraindScwai 11::�ijnd $ 100,000 $1.00,0()() $750,000 $750,000 $750,000 $2,450,000 Totall $100,000 $100,000 $750,000 $750,000 $750,000 $2,450,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 335 eIII IIII )etectiani and I ftflNly ocatilii ng ow"Irvkw 11xqiies9 Owner Dell iartil 11 it GYjjw Cla,,(^y 11 50 teirinain,Waleir/Soweir Sulperfillendelli, klbli(wodks ftfl �,I, arld S(,Wrl, Callpil'all hillipiroveirilicid [)c S C - i 11: � 0 In call, srinird'aU)II's, wall,e Ile alk. deted,lon devire"; all ('1111 liew Ili IA Ili � y kwa LA rig axj u ii I �n L. F 11 lese pi irr, hases A 1111 (:C)1111011111,11eko hi(All) u till 11 t Y st aff ideint I fy t 1111(, a% acl hear at irill of awa i oil Staff 1plkair, Lo P1111-chwe: 0 S 30 II ealk Si Ilrveyri,,; jaft I,- 11,1,11) 7200 Dllgfl.all 11 fighi Iivr irle,arn�rnionre Utility II ocall.oro Ilant puirdhaspil lin 2016 )&,Als I'llojed "JurnIx"i, 23 1W 00001, Ar:counuINJuirrilbeir 050 80.90.00.1.709 665,025 11,11rojorl 11 iN" 6 ,-wrru­irri,A11CC. Category 709 *mn Autoirinoke 11 cliAlisinneN 11111 ioirky 3 llunapaui lainit irairn,, ,,k Goall Gr211 Y Gojjp Oijallily villacr infirnshrud ijire� 113allainced and 11111 oadive Conninniiinity IluntrksfinneviA IN ill i,� Grairit 11 inrided? "Jo Justification Location Ift1placei'lleirill, Or "I"Jing Ilea Ill, col-rell a ksrs a,, si riirc^ hoiranl, ifstoning duvices as va(,111 a i at,hl lig iltilliY locaUing equipi-ne in L G I tu uquilarrienil. goiner all lly h,n a 6 8, Year Aaresilxin airls,i tile LIM dilric I I ulp1­n(,nl:ww, laauui,dhae rd was !I in 2018� Operating Budget Impact ZedilrAinin III Maass. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 336 Inflationary Impact 11 (JiAprnent ws "oline up irl piriceand Ilvarl Jillnes have itInriroaw, d. Capital Cost FY2025 Budget Total Budget (all years) Project Total $80,000 $801K $801K Capital Cost by Year $0 $201K $401K $E,01K $801K 111111111, EnqkJlpimont Puirchase Cost Capital Cost 11qullpirncinII'luirdhase Cos1 Total Capital Cost for Budgeted Years 111111111 E.:quprncnt Purcrsa,e cos : (100%) $810,()00.00 TOTAL $80,000.00 FY2025 Total $80,000 $80,000 $80,000 $80,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 337 Funding Sources FY2025 Budget $80,000 Funding Sources by Year RM Total Budget (all years) Baa 8201K 050 Water and '' ew eir i::: iwurnd Project Total $801K $401K $601K $801K Funding Sources for Budgeted Years 9 050 Wager and Sewoi- Fund (100%)$80,000.00 TOTAL $80,000.00 Funding Sources FY2025 Total 050 Water and Se weii I11 and ')u80,000 W,000 TotaalV $80,000 $80,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 338 04Iktan WaterSysterril ow"Ira,kw kxqiu('";f Owner Dell rartii 11 it fYll)(' kr,oiii 11.611b, kiblfcWark's ftfla,r arld S(,Wrl, ('"allpitall II Irlr'vpiroveirilielit Dcscirijpfloin irv;tallaUon of inewwater aialf-isaind X�sxxfat�ed fil I inewlyannexed ain�w; flhiafdo iniot� I i )(AaHs 11,11rojed lquirdbor 24 II1W 00106 Acourrt Numbeii 11,11 ojed Aff" /5`A a S Category /00 Water SYA orin 11111-loir[ty 2 Voi y llii rillirrii i. alert Sbrategic f;oall (krall 3 fojp Qi Village inifirash uctui-r,: 111,albii rced and 111ir-o4cAW ('1011UT111JIdLY 1111 W�SUINA Ill IN this Grairit II u1i deed? 11,110 Justification loirdoirr,, o[ i all HIMaLlUIS Tr(f)W 'Alalx�r fill a pi1vate utdity ar 'ar VHte wellk. In aill effoll: Lo 11111rovide 11 dgjh quahl,y wal'or al, affol-dable raf,e�� All -rd fincrease wa(cr i rues, (hr' Village W111 hrini,alll new wator 111-rahns, Ihvydrairits, Valves all uat cr(heir 'Inces""Ary corrljnol wnl,'3. f II vi, i would hivolve the rnstallatkwi of a11-rpiroxinwrtely2 ON) llillileasr ferl 0a 12'' wateir inialin exteildling fironri UlcAllagd,,,� a,�xi.,llhngvvatxn syskrn M LexingLoin Dirfvu,,.nind 0,,A(toni Strf:d- [ 11 le 11 liew watell 'nalin would I no art wee doing Oalklon St Ihre,taauea heading Iruorth milli 113,adgeir Drive axiiriiriee, Ling, to Ll le vlllagc"� ex'I'AJIng, WaLell ill "A teirrrrlii all 11 )11,11v(-a1lu1113adger 11)1-11VQ. 0 2024 C0111-1111pled:e 11 11-1;6e1111 r, leilgill eingh m h Ig foir 11 rr,y wa Lei- 11 n fir asti, uctuii c� foir aininexed air eas sout h ran Oak Loi uRoad, a 2021S Operating Budget Impact Requfi-c"t; Ihydirain0.11eak detrqAirrini, 11 ydirainirflusl ling, inallin brealk"', Inlvrrlr.0 11 cadlinp, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 339 Capital Cost FY2025 Budget Total Budget (all years) Project Total $750,000 $7501K $7501K Capital Cost by Year $0 $2001K $4001K $6001K CcnstrLJCT101fn COSt Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� $750,000.00 TOTAL $750,000-00 Capital Cost FY2025 Total CoirrAirucboin Cost $750,000 $750,000 Totall $750,000 $750,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 340 Funding Sources FY2025 Budget 7502000 Funding Sources by Year RM Total Budget (all years) $0 $2001K 037 SMP 1111 i::: iFUlr,d $4001K $6001K Project Total 7IK $750,000.00 Funding Sources for Budgeted Years 37 SIM P..riiF i::::raru:i (100i) $750,000.00 TOTAL $750,000.00 Funding Sources FY2025 Total 007"ILII i IIID II'° a ill $750,000 0,000 "l 750,O00 Total) $750,000 $750,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 341 Operational Costs Total Budget (all years) Project Total $201K $201K Operational Costs by Year 2026 2027 2028 2029 $0 $1121K $2 41K $3. 6 IK $4+ 81K 111111111, Aninuall 01peiratiohall COSL $5,000 00 $5,000.00 $S,00000 Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $20,000.00 TOTAL $20,000.00 Operational Costs FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Cos $5,000 $ 5,000 $5,000 $5,000 $20,000 Totall $5,000 $5,000 $5,000 $5,000 $20,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 342 Ovedhead Sewer IIIIRrograrwii cNavow RNWM Omni' Ikimmminr "w (,".asr�y 1115of Sinporildoindelifl, kflblir Wo Oks sun my Amni, CAAWAwWownnfl DwadpHon An mMwA wWWywmi"sK-n k%WrA to WeninisanlWywask fl-011TI MOWIng Itradkirt'o tho llowe,whidh CNrli aaa;v.;nuir for dlffferonr reasons one of therin I'scillg, I mlin (woi Its wheire Hilo &sillllare's r,ol'N"Aned soweir utasiunin go Wkd 0 cafmay An owkwA smA my warAn"kk dw Nome An Wh Me W=&Mn, Im &M)s W aw pkh"mAtaT wnmWA ad wwu nut, lairtkip-,flIon nuillbers to(L-fle� * 2024 `i * 2093 3 * 2022 4 * 2021 10 Avomp 151wrywir Wages Chedwad So= RAW II cuMW XTI DwAs 11,11 ojock, 1 21, 1W 00022 Acci: wint f1wrinbeir 050,80,90,001,702 672,001, 11111-ojr4 p II ife Annually (wamy /11211 IIru'.uc1 (3n0.ro11 and Rdawd rneds 11,111 is KY 2 Veii y Ilinnillaoii Laii K Stirafcglc Goall Ge313 iolp 0,na Ili (y Vi 1111 age 1111 fra,,4 ii ujd uAii c: No I ncadoin 14 Justification install,adoin or publIcsectoii Unnipmvenneds ahnn cmmd pwAde I he swne Owd of WAAWy agAnq sadUry bmAup as hnsiallal Wn or pWo scctoi' bardoulp sonbrol, IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 343 Operating Budget Impact Oheirc w11111 Ibe no Ibudg(q uinglusac. a:� the sy^Aein would Il e owned aincl rna'iifl,alnee 1,-)y hoim-"Owincirs Capital Cost FY2025 Budget $1.00,000 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget ((all years) $5001K $0 $251K $501K $751K $1001K 1111111111 Cc' nsLrucfloin Cost Project Total $5001K $i0o,o0o 00 $ioo,000 oo M0,000 00 M0,000 00 $ioo,00000 Capital Cost for Budgeted Years 11111111 Consuuc..Lion $,.00,00(:x(:Po TOTAL $500,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total constinxboll-11 Clos0 $100,000 $1 010,00:0$,0 $100,000 $100,000 $100,000 $500,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 344 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 1111111111 050 Water and Seweir Fiund Project Total $5001K $mo,000no $m0,000.00 "$ 0,000.00 $M0,000 00 $mo,00w)o Funding Sources for Budgeted Years 9 OSO Wat.cr and Scwor IFund (100%)$S00,000 0 TOTAL $500,000-00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 050WMciraindScwcii 11::,ijnd $1.00,0()0 $1.00,0oo $1.(K),()00 $1.00,000 $1.00,000 $"5oo,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 345 SewerMlafiri 0v(,,irvk,w Owiliell, )ell aa - til 11 wil i lypo [)Csorilpfloin S(.Wcr inaill I iii-ling'spot i and i ill ide I inniages (.a,;r�y 11150 Sulporild oil Idell I l, kiblir wodks,' ftfl �,I, arld S(,Wrl, Callpitall hillipiroveirilicid Locationi 11,110.`Aject lquiriber 21, 1W WOV� AB'count \kiiii-ilbeii 11,11 oject Aff, Aiiiiijally Category /01. Sail lt"wy SyMellin 11111-ioi1ty "IL..criticall Strategic Coall Goall 3 lop Qualli(y Village 11ln4rarshru ctuire: 111,albinced a nd IN 111ifsGrairit II i'llinded? 11,110 Justification maintailin 011 le Mxucl.uraiil,, argirli.y or seweir i t,orm)vo ex�:ess iii-irill uratioin aii id inirlow i.f.) ill iiiiiiii 1[11u/v basel nord: back Ajpr� and Sowell- smircl iall-ge", 11 1[ 0llects will 11 buv,dl o( t (A ba,,ed ol � nccd 011,iii- gab,111 N to inaIhalA itat e apIx wd 11 faF,a k,dy 1Y, Or thU 5Y�AOITI �11 HILW11 Y, Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 346 Capital Cost FY2025 Budget $1,000,000 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $51M $0 $250 K ��.600K $'750K $UM 1111111111 Construction Engineering Capital Cost CoirrAirur'bDrain 11:1ingincell Ing Totall Project Total $51M $i'(:&Oc'000 0o $i'o00'000 00 $i,000,000 00 $i,wo,000 00 $i,000,0004 00 Capital Cost for Budgeted Years Const.ruc6on E.:nginccring (100%)$5,000,OOOC TOTAL $5,000,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $1,000,000 $1,000,000 1,000,000 1,000,000 $1,000,000 $5,000,6;DQ:0 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $5,000,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 347 Funding Sources FY2025 Budget $1,000,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $51M $0 $250K $500K $'750K UM 1111111111 050 Water and Seweir Fiund Funding Sources 050 Water and Seweii II und Totall Project Total $51M $ 000,00o.00 $ ,000,000.00 $ 000,000.00 $�,000,000 00 $�,Ooo,00w)o Funding Sources for Budgeted Years 9 050 Wager and Sewoi- IFrund (100%)$5,000,000 TOTAL $5,000,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $ 1,000,000 $ 1,000,000 $1,000,000 $1.,000,ow $ 1,000,000 $5,000,000 $1,0()0,000 $1,000,000 $1,000,000 $1,000,ow $1,000,000 $1Woo,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 348 Operational Costs FY2025 Budget Total Budget (all years) Project Total $1.0,000 $501K $501K Operational Costs by Year 2025 $m"C;0o.00 2026 $m,000.00 2027 $0,000.00 2028 $(0,000 00 2029 $m,00w)o $0 $2,51K $51K $751K MIK 1111111111 Aninuall Olpeiiafloinall Cost Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $50,000.00 TOTAL $50,000-00 Operational Costs FY2025 FY2026 FY2027 FY2„02,8„ FY2029 Total Aninuall ()Ipcii atlionall Cost $10900 $1.0,000 $1.0,000 $ I (),(xx) $1.0,000 $50,(XK) Totall $ 10,000 $10,000 $10,000 $10,000 $10,000 $50,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 349 actreel: hiliglllh VIII)Iscariiiriect Cabfiriet 0v(,,irvk,w kxqiue°, Owner Cla,,ey 50 teirinain,Wfleir/Soweir Sulperfidendell I u, kflblkodks Dell artii 11 it ftfl:a,I, arld S(,Wrl, QYjjw Calpitall kinpiroveirincid [)c S C - i P 1: i 0 In painddmir;, I mages Stlrr r p IlJiu Iht confiroll Calbilinet Justification KAI HjpleAirc�ct figll utiuilg dkcarilriCd Ila in, aire oveir 20 ycair<, old and are di lr7 faalr an uppi ada Q the upp, ade,, allow f011- TKKO OFICTt Y CffidU-IA equfjjpinnenQ. and w11111 u1rief.,O ii ia^7w code rep,fladoiw, foir AIK Hash Oine of Lhcujjpgiradea , firicludes 11 Avill g U1 ur 11 ainu] off dutou ,wfkdhe, MarcakA on Llw o1W :Jde or t 11 w cabhnd fin a lodkod (�ont alli 1111 api-1111'. Q 11 o11,; allowkn non All,C flashed OraVirwd indl to afxx;S flhew, svOtdl w�,. Qh", 1311'0130VA budUet wflll alloAr frau 2 ca[And: implaceinell 111,5, ,au d 10 pr)111 nrwun� ed replacui ncr� ,, per ye�ir. Operating Budget Impact AininG.<j ll I n a11rntenance cast. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 350 )11 ojed, Aumber 19 :1W 00034 Accourfl Auirinheir 020 80 90 00 1 7015 676.001 1111rojed Life 30 Y(Ij 11' (,:rflegrvy 705 111111or11'Qy 3 rrijpoilan� SIraLogrlr: Goal Goall 3 Qbjp Qil nlHy W111age infrashu( i ure: Balanced and 111iroadive Conninnuinity inv:ashnnein 11 i tlfl^, (,Irant 11 uilded? bla Justification KAI HjpleAirc�ct figll utiuilg dkcarilriCd Ila in, aire oveir 20 ycair<, old and are di lr7 faalr an uppi ada Q the upp, ade,, allow f011- TKKO OFICTt Y CffidU-IA equfjjpinnenQ. and w11111 u1rief.,O ii ia^7w code rep,fladoiw, foir AIK Hash Oine of Lhcujjpgiradea , firicludes 11 Avill g U1 ur 11 ainu] off dutou ,wfkdhe, MarcakA on Llw o1W :Jde or t 11 w cabhnd fin a lodkod (�ont alli 1111 api-1111'. Q 11 o11,; allowkn non All,C flashed OraVirwd indl to afxx;S flhew, svOtdl w�,. Qh", 1311'0130VA budUet wflll alloAr frau 2 ca[And: implaceinell 111,5, ,au d 10 pr)111 nrwun� ed replacui ncr� ,, per ye�ir. Operating Budget Impact AininG.<j ll I n a11rntenance cast. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 350 Capital Cost FY2025 Budget $1.00,000 Capital Cost by Year 2025 2026 mom 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 1111111111 ConrAruction Cost Project Total $5001K $i00,00o.00 $i00,000.00 $i00,000.00 $100,000 00 $i0o,00w)0 Capital Cost for Budgeted Years 9 C.onst.rucLion CosL (100%� $S0C),000.00 TOTAL $500,000-00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total coinshrur"11101111 Cost $100,000 $ 1 oo,000 $100,000 $ I oo,000 $100,000 $500,000 Totall $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 351 Funding Sources FY2025 Budget $1.00,000 Funding Sources by Year 2025 2026 NOON 2028 2029 Total Budget (all years) $5001K $0 $251K $501K $751K $1001K 1111111111 020 dual halal Ilirm1piroveiment If und Funding Sources 020 Callikall hrnlpirovonicnu I1::wnd Totall Project Total $5001K $mo,000no $m0,000.00 $mo,000.00 $M0,000 00 $mo,00w)o Funding Sources for Budgeted Years 9 020 Capit.al Irrprovornent. i::und (100%)$S00,0 TOTAL $500,000-00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $1.00,00() $100,000 $100,000 $1.00,000 $100,000 $:5oo,000 $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 352 Operational Costs FY2025 Budget Total Budget (all years) Project Total $1,000 $51K $51K Operational Costs by Year 2026 $¶,000.00 2027 $ ,000.00 2028 $000 00 2029 $¶,Oow)o $0 $250 $500 $750 $UK 1111111111 Aninuall Olpeiiafloinall Cost Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $S,000.00 TOTAL $5,000-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011 of abonall Cos $1,000 $1,000 ,�,bI,000 $1.,000 $1,000 $ �5,000 Totall $1,000 $1,000 $1,000 $1,000 $1,000 $5,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 353 iletrofits 0v(,,irvk,w Owileir 11150 Sulporild oil Idell I I, lubfir wodks, 11 )ell a - tinnell ftfl r�r al id Sower �Yjjw Cajjpi[,a11 hillipiroveirilicid [)CScrilpfloin W�edhnology, All 11 sbireefl ig,11 As w 1111 Il1 coil veir Led Lo 11.11:::: 11) at u 1110 eind 012024 with, thie. ex(: oll or L11 w 111 lairl, pairlk Ill lig Ilot 11 igh '3. o Silaffcall-dirnfid t lie exis0 u I'll; I I Stired IIfght pole I )c ta i I S 11111-0aed Nuirdber 21. II)W 0004 6 Accwnl: 111undbeir 020.80.90,001,10bAI&O01 11t IIffe Aii iiii luAlly clntegory /05II" Csijil f,xill P/0311 S, Gut tei-s/,Sldr,,wd1(s 11 111-foll1ty 3 11 iTillpoirlaini St1Ial1eP,lcG(,')d11 Goall 3 tojjp 113,flancedand 11 lrurwl 1 ve C q j in inn u in!! ty 11 inw-, tinno. in 1, 11 h i:, i,, n in t 11 ij ii odled? "k) Justification Locadoin ilmlnpahis 1,10(kheeLlights, fl-111'seffoll.w11111 IbeairiijlU year WILIFIDicbrofits Bawdoiri oinlr exjpci'lon(xwithi flic" Conversion of ajpp1-0x!1-1-lrd:e1Y 100,11-cctllfflhtT3 to II 11:JD, III ie staH u s exped I ii ii,,, to see a ret u I in o in 11 nvest inn c int of L; 6yeai,s, All 11 st red fiM 110 pr, 4ks will 11 L -w conveirted Iby 4 11 le oind of 2024 thodowintown aire;Ao 11,11 11), flliseffoiru willl alsolbea I !I ye)Ir I Operating Budget Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 354 Possible reductfari in electirfcN,y Capital Cost FY2025 Budget $50,000 Capital Cost by Year 2025 2026 2027 2028 2029 Total Budget (all years) $1.301K Project Total $1301K $0 $Q1K $241K $361K $4,81K 111111111, G::.qkjililpirrieiritlF)uirclh)ase C<)st $,,.�0,000 oo $20,00000 $20,000 00 $20,000DO $20,000DO Capital Cost for Budgeted Years Purl tat cc�sL (100%) $13c),C)oo.00 TOTAL $130,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total 11cpfllsirncnt Puirdhasc Cost $50,000 $20,000 $2Q000 $20,000 $120,000 $1,30,000 Totall $50,()()() $20,000 $20,000 $20,000 $20,000 $no,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 355 Funding Sources FY2025 Budget $50,000 Funding Sources by Year 2025 2026 vzwm 2028 2029 Total Budget (all years) $1.301K Project Total 1 3 $01K $0 $�21K $241K $361K $4,81K 1111111111 020 Calpitall Il arra proveiment IFu and $5c"000 0o $20,,00000 $20,00000 $20,000.00 $20, 000.00 Funding Sources for Budgeted Years 9 020 Capit.al Irrprovemomt i::und (100%)$130,OC TOTAL $130,000.00 Funding Sources FY2025 FY2026 FY2027 FY2028 FY2029 Total 020 Capitall Ilurnpiroveinient 11wind vjo,000 $20,000 $,20,000 $20,000 $20,000 $ 1. 30,000 Totall $50,000 $20,000 $20,000 $20,000 $20,000 $n0,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 356 Operational Costs FY2025 Budget Total Budget (all years) Project Total $500 $ 2.5 IK $ 2.5 IK Operational Costs by Year 2025 2026 2027 2028 2029 $4,80 1111111111 Annuall Olpeiiafloinall Cost $Soo 0o $50000 $50000 $50000 $500DO Operational Costs for Budgeted Years 9 Annual Operadonal Cost (100%� $2,500.00 TOTAL $2,500-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 0113cii atlionall Cost $500 $500 $500 $500 $500 $2,500 Totall $500 $500 $500 $500 $500 $2,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 357 chavow RNMM Omni' Ci,,(�y 1150 teirinain,Wfleir/Soweir sujjpeirfinkixh11r , kflblkoirks Ikpmminl sun my Amni, "w CAAWHmKowIra nifl 3csodpHon Ib moan bmrKnUUmmVFM we mywMon a wwnVu coe. 2025 VII ]D's to 1k relp1wed: V1::11:92 115oosLcrsf�aJa[15 V11D1 NoMarladonl/ VID3 2029VIIIID's In I replace(L * Il oo,,Lor tat AIan 16 VII 11) 2 * INMIQ INBAL VIII[: 3 * RaMer SoNa" 17 V! D 2 Wages MWW cmtrw CMA uyum.,,�, mu's Dkds 11,11rojed "Jurnber 16 11 1W 00002 Acci:xnn1,4unnilbeir 11-111rojed Life 7pars Category 700t,^a" uteirSy.Lenn 11111-ion1LY 3 Il injinirLaint Stir�4egIc 0��111 Goa ill 3, Pajjp Qtijailfty \Ulzige llii frash mbinii e: 113,,aIairiced,-Anc,] 11 li[ o,,x;iive CoirnirnuinIty II inve.,.IrneinI INIII �is Grant 11 ijii ded? tlf) Justification In UwvadAdu RogwaNdAws NHY M to MAbn"s am War 1mver 20rms Ad II a Pum bum umdwnW;nmx1y 2,1/7,anrIH Is autIthe eindN H. wx4nll IIHe IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 358 Operating Budget Impact Noire, Capital Cost FY2025 Budget Total Budget (all years) Project Total $50,000 $1.001K $1001K Capital Cost by Year 2025 �,so,(.)00.aaaa 2029 $50,00000 IIIIIIII E..x:pa.uill ilnelnt IIirc:III ase Cost Capital Cost for Budgeted Years 1111111111 Purchase Coss (100%)0100,00().00 TOTAL $100,000.00 Capital Cost FY2025 FY2029 Total I:..d;.Nu llpll'IncIf1Q I° uIrd-lIlixi '. $50,000 1150,000 $100,000 tI otaalV $50,000 $50,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 359 Funding Sources FY2025 Budget p $50,000 Funding Sources by Year VAM NM Total Budget (all years) $1.001K $0 $ 21K $241K 050 11r+"anter and '' ew eir i::: iwurnd Project Total 1 $,,.;0 000.()0 Funding Sources for Budgeted Years 9 <)SO Wager and Scwor Fund (100%)$100,000 0( TOTAL $100,000.00 Funding Sources FY2025 FY2029 Total 050 Water Ir eau nd Sew eii II'IIrInd $50,000 $50,000 $1.00,000 TotaalV $50,000 $50,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 360 Water 111111 lhrii 0v(,,irvk,w kxqiue, Owner 11 )ell ba r til 11 wil pYjjw �� )CScirilpfloin Aii iiii iii oll wa[oi i-rdin ep1,xeiinenL I inni ages t:;r,,s���y1150 teirii nain, Wfl eirlsoweir Sulperfil d endell u, kflblkodks ftflp arld S(,Wrl, Cajjpi[,a11 kinpiroveirincid Locatioin 11,11rojed Ilquirdbor 2 3. 11 1W W008 AB'count Numbeii 11,11roject Iffe /5 yeza'; categoi,y /00 w"Itell. SYAorn 11111-loi1ty I cddcall Stirategk Crmll Goall 3 pojp Qij:�di(y vfll,tge 1114 rastructure: 111,albinced a nd IN dhfsGirciirit 11 i'llinded? 11,110 Justification kCjjplamilnoi ft CA detel iol-a(rd w"Acir Innviulrn IthA are proirw to Ilr=npll age/breakagre (o 11 nill diiriu/e sorvucv dkirujjA ions and pirowirve wAor fpcill Iity. I'vin(filing i1-1,11 11' ovallen(s� 11 If 11 'us!! SL GoIrvkM(11,11. * 11 dward SL * will lialin St, * lalii[ii D11, k $600;� finear foot for,,iw,Aei� nrrJin uaychaige depandingoin hyd1aij1!cw,,Arii modding. Operating Budget Impact Floteintllnll swhgs hin d le r,r)A chmatell" -,nw;AerRebs; , kred ucr�d by toweir u7n All hircnflkr,. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 361 Capital Cost FY2025 Budget Total Budget (all years) Project Total $6,500,000 $32.8921M $32.8921M Capital Cost by Year 2025 $6,500,000 00 2026 $6,,500,000 00 2027 $6,,500,000 00 2028 $E,,630,000 00 2029 $6,762,000DO Capital Cost for Budgeted Years $0 $2 IM $4M $61A Const.ruc6cn CosL (100%� $32,892,0MOO 111111111 Construction Cost TOTAL $32,892,000.00 Capital Cost FY2025 FY2026 FY2027 FY2028 FY2029 Total Coil l"' bru4,tiol-11 Cost $6,500,000 $6,500,000 $6,500,000 $6,630,000 $6,762,000 $32,892,000 Totall $6,500,000 $6,500,000 $6,500,000 $6,630,000 $6,762,000 $32,892,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 362 Funding Sources FY2025 Budget $6,500,000 Funding Sources by Year 2025 2026 2027 2028 2029 Total Budget (all years) $32.8921M $0 $2 1A $4M $61A 1111111111 050 Water and Seweir Fiund Funding Sources 050 Water and Seweii II und Totall Project Total $32.8921M $6,500,000.00 $6,500,,000.00 $6,500,000.00 $6,,630,000 00 $6,762,000DO Funding Sources for Budgeted Years 9 OSO Wat.cr and Scwor IFund (100%)$32,892,00( TOTAL $32,892,000.00 FY2025 FY2026 FY2027 FY2028 FY2029 Total $6,500,000 $6,500,000 $6,500,000 $6,630,000 $6,762,000 $132,892,000 $6,500,000 $6,500,000 $6,500,000 $6,630,000 $6,762,000 $32,892,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 363 Operational Costs FY2025 Budget Total Budget (all years) Project Total $5,000 $251K $251K Operational Costs by Year 2026 $5,000.00 2028 $5,00000 2029 $5,00w)o $0 $L21K $2 41K $3�61K $4 81K 1111111111 Aninuall Olpeiiafloinall Cost Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $2S,000.00 TOTAL $25,000.00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Csn $5,000 $5,00o $5,000 $5,000 $5,000 $25,000 Totall $5,000 $5,000 $5,000 $5,000 $5,000 $25,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 364 Water ileseryQuill liar IllSlunrflber 11 1 0v(,,irvk,w Owiliell, (.a,;r�y 11150 Sulporild oil Idell I l, lubfir wodk�' 11 )ell �a - tilliell ftfl r�r all id Sower �Yjjw Callpitall IIuuop iroveirilicid [)CScrilpfloin 11111, 1 a nd coa� iii ug, of intorilai and extra11 uoii surf"wes of watell ;toragc I:a In k 11, llm aLed a1. 113 oosl.ei, M -uUloi) 11 I inniages 11,11roject lquirdber 21b 1W 0000/ Account Numbeii 0!K18(190,0()A,/()U6/1 D01 11,11roject Aff, 15 yeai[', Category /00 W,'ateilr SY'Aarin 11,11-10111ty 2 Voi y IT1113011 I,allllt Strategic Coall Goall 3 pojp Qualli(y Village 11 n4 rashructuire: 113allanced and IIlrtl h":Sve ("onni-nijinity 11 llvestii ineii ii, 11 11 Ifs Grant 11 11,111111ded? 11,110 Justification mainteinall Ice (A wa(er "Aoiragv Lairill"s flco�ssairy Lo I wnl� Lary ��on�fidoiw� all d jjpire�xrvl, ,O,irur� uirall III ftegirky. 11 XlSbn;,, wateir stoirago capadi'y N 11 equill ed g o saHsfy 1111'111A xi id JAWA ii eq1rurricird s ai id i-riah itafin 1150 hii e radii Wal,cr talrlks all e hilisped,ed aii iid i� elpaiii ed/i, epaiii ited oii a I if; ba"I", Jhi,,, I cseirvchi was rell rdbflhllat ed and palinted in 2008, Operating Budget Impact Annuall ii-nalintenance co,,L Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 365 CoirrAiruciJoin co�sts have !I if icireased 30% fiii�tl-w IIstye um. Capital Cost Total Budget (all years) Project Total $7001K $7001K Capital Cost by Year $700,000.00 $0 $2001K $4001K $6001K Constructoin Cost Construction Eingineeiring 41111, E)esigin Engineering Capital Cost for Budgeted Years 111ill, Corfst.fuc.:Lion C.:osL $600,000.00 411 Corfsl,fuction Fnyineeiinc..3 (91%) $6(),()0U00 0/'� Dc Ig E.:rfgincc6ng (RX�) $/,0,000.00 TOTAL $700,000.00 Capital Cost FY2028 Total Dcsfgin 140,000 c➢insbnxtioiri FIii gIII eciliniqg $60,000 $60,000 Cloicis briuhoiri Clos S',600,000 $600,000 Totall $700,000 $700,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 366 Funding Sources Total Budget (all years) $7001K Funding Sources by Year Project Total 7 IK 0 4:50 Water and Sewt€stir i::::iwund Funding Sources 050 Water and Sw,te ii II nuund TotaalV Funding Sources for Budgeted Years 9 050 Wager and Sewoi- Fund (100%)$700,C1000 TOTAL $700,000.00 FY2028 00,000 700,000 Total $700,000 $ 700,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 367 Operational Costs FY2025 Budget Total Budget (all years) Project Total $500 $ 2.5 IK $ 2.5 IK Operational Costs by Year 2025 2026 2027 2028 2029 $0 V20 $240 $360 $480 1111111111 Aninuall Olpeiiafloinall Cost $500.00 $500.00 $500.00 $SOOOO $50w)o Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $2,500.00 TOTAL $2,500-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 011poi abonall Clos% $500 $500 ,C, � 15()() $500 $500 $2,500 Totall $500 $500 $500 $500 $500 $2,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 368 Water ileservoll�r IllSlunrflber 11 6 Oveirvk,w 11,4"quo"f Owner IuL,rIhr WoOks Departinionf ftfl r�r al id Sower fy1po Cqjpika11 kinpiroveirinent [)CScrilpfloin 111w,pecHeirl, rrlAalur a nd co'lking of�Inteirk)ii .vid e)doii it �;urfarr'^� of yr eii M011"Ige nlk 1.6, ocaUxl a . BriwAor S4 a0k)i) 16. I nages 11,11roject lquirdber 23 1W 000T� Account Numbeii (f!K18(190,0()A,/()U6/1 D01 11111-rj�ect Afe 1 S ye�,n s Category /00 W,'uteir SY'A arn 11,11-10111ty 2 Voi y IT111P011 JAllt sBeater k Crmll Codll 3 fajp ()uAll (y Vfll,�ge 11 infrash ucWire: 113alhinced and lrtmd ve ("oll-ni-nijinity 11 investil inell 111, 11, L11 Ifs Gir,"iint 11 1131111dpd? 11,110 Justification Kifintoriance d W.Acr ,(oirage L,,wflks k rwo','FF,airy Lo rnahnLafin ^sairfl Lary e:oirid k iairiu� arld piresenfr, ,(Irur:�ful-all h ae�,,irky. 11 xisUni,, wa� eir stoirage capadf,Y N 11 equill ed o sa(fsfy 1111'11:1A xi id JAWA ii equ1rurricird s ai d rnah �tahn 1150 hii e radii qs Wa(cr t,lnks all e insped,ed aii iid u elpaiii ed/i, epah oted oii t1 -(Aabii r', Iluaa^Js, f II is ii eseirvohi was IIzist rellrdAIN,,)P ed fin 2010, 11 )urlii r), LN" t1l Ile tairilk vv -at; pzdntfA�-n d U1 e (roof Operating Budget Impact Annuall ii-nahMenaince, cO,,L Inflationary Impact IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 369 Coinsbruc,Hoin co�ks haw; !I if Cii,eased 30% lin tl-w as I: yea ir. Capital Cost Total Budget (all years) Project Total $6851K $68511 Capital Cost by Year RM $0 $2001K $4001K $6001K Constructoin Cost (11 Constirucdon Einglineeiring 41111, E)esigin Engineering Capital Cost for Budgeted Years 111ill, Const.rucLion C:or.,L (8,15%) $,"?,s,c)oo.00 Dc Ig E.:ngincc6ng (616>) TOTAL $685,000.00 Capital Cost FY2027 Total Dcsigin $40,000 Coinsbru(boiri Fnginccilinqg $60,000 $60,000 $58S,000 Totall $685,000 $685,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 370 Funding Sources Total Budget (all years) Project Total $6851K $6851K Funding Sources by Year $685,,000.00 $0 $2001K $4001K $6001K 0 050 Water and Seweir i::: und Funding Sources 050 Water and Seweii II und Totall Funding Sources for Budgeted Years 9 050 Wat.cr and Sewoi- Fund (100%)$(585,000 0( TOTAL $685,000-00 FY2027 $685,000 $685,000 Total $685,000 $685,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 371 Operational Costs FY2025 Budget Total Budget (all years) Project Total $500 $ 2.5 IK $ 2.5 IK Operational Costs by Year 2025 2026 2027 2028 2029 $0 V20 $240 $360 $480 1111111111 Aninuall Olpeiiafloinall Cost $500.00 $500.00 $500.00 $SOOOO $50w)o Operational Costs for Budgeted Years 9 Am-WDI Opcmidoral Cost (100%} $2,500.00 TOTAL $2,500-00 Operational Costs FY2025 FY2026 FY2027 FY2028 FY2029 Total Aninuall 0113cii atlionall Cost $500 $500 $500 $500 $500 $2,500 Totall $500 $500 $500 $500 $500 $2,500 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 372 Wlhrdess 6l4nrietry Systerri, lii)pgradeVIII VIII C Ulpgrades Ove,irvlicw kx'cpje»d Owiliell, 11 )ell aa - tilliell lypo (.a,;r�y 11150 Slillporild oil Idell I I, kiblir wodks,' ftfl r�r all id Sower Callpil'all Iluuulf iroveiruua=irirt [)CScrilpfloin 11111 Cslhavo. airieMii-naged Iliifoof 12yrai-,, Ilan2028, I accii i ion L of 11 111 Cs I,,, plairined rat� ,:, 14 llevated lank I I 11 )CA;fils 11111'0tecl, I'llumber 25 W 00008 A(,counl: lauirdbeir 011K).80 90,0U 1,/00A&,D/9 4 11 f fe 8 Year', Category /00 Water SY'Aer,[ 11 111-foll1ty 2 Very Iluvulparu tl d1l lit stirategk Goall Goall 3 iolp 01 ja If ty A lage 111111 firas t ii ud uire: 11 Itlaii lo dl a nd 11 lroa(p fvo t': urirnirnl.AN ty 11 investrinein 1. IN t1hisGrant Il undled? 11,,pia Justification Locadoin illevilla""'e", watell, a IrldwaMewakell, ,Ystc I[ in !I,,, -1011ii.0red lfry as wlrrdc,,,, tdeiinelrysyslrmni, caninonly refeinrcd to,,,6 a SCA11 )A ;ysteirri Flik ° yOorn was lin 20(Y3 and has pcirfoin-ned oxceedhiglywdll over thus yea r F, 11-16111.aling Lo In'[ or illa, I, the uU114y ysteirrls' pw-rljp.,,;, inriot.o 5, badkillp gcimirafixs, lift Stat b ns, Irellefst at bis and nuteir vik-'d jpairt,, of t I ucvillago's ill oiilastilluct I aIre fl -4 a leed I hrv;p h !is l alligns wit In flhc�, Vlllagds, sAii A(�gic iilfii a ��I.11 udwre goall regairdirig [I ood wintird,wal,er a rid sew(, r to !I ll7jjl,)Irove a and In a !I I, ll�a !11111 hdirasLirijctuire fw� !III klcs, a inild sysl.eins, ro - I heallill aild ',a fely, lo I (juir illivw-'11, I n('Inl: lin Llkw vN all rx)irinirinuinity rwouircc; all id Inplim(ed 11)1( lvalk,proIrwilly. Operating Budget Impact Zed lr:ed Ylaill I 0 nnlailic:e cost s for Llhc Vi 11 ago,, SCAIDA syM eirri. IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 373 Inflationary Impact Yatorkfls Inavc uincreasod 1 5%awr dhe Ilan i.yr,�air Capital Cost Total Budget (all years) $1.001K Capital Cost by Year vam Project Total $1.001K $0 $251K $501K $751K $1001K 111111111, G::.qkjililpirrieiritll:)uircll) ase C<)st Capital Cost 11 . quillpi-inent I'luirchase Cost Totall $ioo,000.00 Capital Cost for Budgeted Years Purcl-sase TOTAL $100,000.00 FY2028 Total $'too,000 $ I oo,000 $100,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 374 Funding Sources Total Budget (all years) $1.001K Funding Sources by Year Project Total $1.001K $m0,000.00 $0 $251K $501K $751K $1001K 0 OSO Water and Seweir fmund Funding Sources 051rWatcii andkwcirl::�und Totall Funding Sources for Budgeted Years 9 OSO Water and Sower IFund (100%)$100,000 0( TOTAL $100,000.00 FY2028 $100,000 $100,000 Total $ 100,000 $100,000 IN Village of Mount Prospect I FY2025 Community Investment Program Requests Page 375