SUBJECT: PROPOSED CIP: 2009-2013
Attached hereto is the proposed 2009-2013 Capital Improvements Plan (CIP). The projects
being considered for the year 2009 total $21,989,401. The five-year total for all projects is
$57,178,404.
We encourage you to read the Manager's transmittal letter beginning on page ii. This
correspondence describes the purpose of the CIP, highlights some of the more significant
projects, and reviews project funding. To help you evaluate our ability to fund the requested
projects we have again provided five-year financial forecasts for the major operating and capital
project funds that provide funding for the CIP. These forecasts can be found in Section H of the
document.
In general, the projects being presented directly relate to the monies expected to be available.
However, from reviewing the CIP requests in conjunction with the five-year financial forecasts I
would like to direct your attention to several project areas.
General Fund Proiects
The CIP is showing the five-year average of projects being paid from General Fund revenues as
$407,000 (A-1 0). This is typical of the amount of capital projects funded by the General Fund on
an annual basis. I would like to point out the five-year financial forecast for the General Fund.
This forecast is showing an operating deficit in 2009 of $907,727 with annual deficits increasing
each subsequent year through 2013 ($3,759,017). See the complete five-year forecast for the
General Fund beginning on page H-1.
Motor Fuel Tax Fund (MFT)
Receipts from motor fuel taxes beginning in 2008 are expected to remain flat through 2013. Due
to the flattening of the motor fuel taxes, the Fund has annual deficits for every year of the
forecast. This is significant as the MFT Fund supports approximately one-half of the funding for
the annual street program. Originally to be finished in 2006, the completion of the street program
was pushed back to 2009 due to budget constraints. Shortfalls in MFT funding for the street
program will be made up using monies from the Street Improvement Construction Fund.
Proposed CIP
June 6, 2008
Page 2 of 3
Capital Improvement Fund
The Capital Improvement Fund is meant to support intermediate sized capital expenditures for
various departments that are non-recurring in nature. Some examples of these projects are
Detention Pond Improvements, PW Emergency Generator and Video Conferencing between the
three fire stations. From 2002 through 2007 approximately $3.7 million in projects were deferred
due to discontinuing the General Fund transfer. In 2007, the Village Board approved a
permanent funding source for these mid-sized capital projects. An additional ~ percent home
rule sales tax was implemented beginning January 2008 that will generated approximately $1.3
million annually. A portion of the revenue will be allocated towards building up the fund balance
for the Capital Improvement Fund and the Village's two Parking Funds. Approximately $1.0
million annually will be available for capital projects. Projects included in the five-year plan after
2010 will need to be further prioritized with some deferrals to bring the total annual amount down
to what can be supported with current revenue streams.
Street Improvement Construction Fund Proiects
The forecast for the Street Improvement Fund (H-11) is showing a positive fund balance of
$483,274 at the end of 2008, but the fund balance will become a deficit by the end of 2009 due to
slowing revenues. Revenue to support the program comes from the state and local motor fuel
tax and ~ percent home rule sales tax. Each of these revenue sources are expected to either
decline (home rule sales tax) or remain flat (state motor fuel tax) over the next year resulting in
fewer funds available to fund the street program. Adjustments to the amount of work planned
each year will be necessary if these revenue sources do not rebound during 2009.
Flood Control Construction Fund Proiects
Fund balance for this Fund is projected to be $81,511 at December 31,2008 (H-12). Two larger
size flood control projects for Prospect Meadows ($600,000) and McDonald Creek ($1 ,500,000)
are planned over the next five years. Although funding from the ~ cent sales tax (portion not
allocated for debt service) becomes available in 2010, there are temporary shortfalls in 2009 and
2011 that need to be addressed. After 2011, sufficient funding is available to support the
ongoing flood control program.
Water and Sewer Fund
There are several large capital projects included in the CIP for 2009-2013. The first is the
ongoing Combined Sewer Improvement project started in 2005. The total cost for the project
was originally estimated at $15 million and expected to take 10 years to complete. Funding for
this project comes from a $5 per month sewer construction fee and basic sewer usage fee.
Based on early results, the overall costs may come in lower than originally estimated and
completion could occur before the planned 10 years. Other major projects include ongoing
sewer and water main replacements/rehab averaging $813,000 per year and emergency
generators for water pumping stations at approximately $360,000 per year through 2011. Water
tank rehab totaling $1.3 million is also included in the five-year forecast for the Water and Sewer
Fund. The cash and investment balance is projected to remain relatively level over the five-year
period and end 2013 with approximately $3.5 million.
1:\CIP\2009-2013\2009-2013 CIP - Board Memo June 2008.doc
Proposed CIP
June 6, 2008
Page 3 of 3
Fundina to be Determined
The CIP is showing five new projects were funding has yet to be determined. These projects
include the construction of a new Fire Station 14 at $8.6 million, expansion of the Public Works
vehicle maintenance building at $2.3 million and construction of an Emergency Operations
Center for approximately $2.1 million. A funding source also needs to be identified for the Ash
removal/replacement program expected to cost $4 million over a ten-year period. All five
projects are slated to begin in 2009 and 2010.
Meetings to review the CIP are scheduled for June 18 (Finance Commission) and July 8 (Village
Board). Staff looks forward to discussing the project submittals and their impact to operations.
J~tPc~
David O. Erb
Director of Finance
Copy: Michael E. Janonis, Village Manager
Dave Strahl, Assistant Village Manager
Lynn Jarog, Deputy Finance Director
Department Directors
1:\CIP\2009-2013\2009-2013 CIP - Board Memo June 2008.doc
FINANCE COMMISSION
DRAFT
MINUTES OF THE MEETING
JUNE 18, 2008
POLICE AND FIRE TRAINING ROOM
DRAFT
I. CALL TO ORDER
The meeting was called to order at 6:05 p.m. Those present included Acting Chairman Vince Grochocinski
and Commissioners Wayne Gardner, John Kellerhals, Don Ocwieja, Tom Pekras, Ann Smilanic. Also
present were Village Manager Mike Janonis, Information Technology Director Joan Middleton, Community
Development Director Bill Cooney, Deputy Director of Community Development Brian Simmons, Deputy
Fire Chief John Malcolm, Fire Marshall Paul Valentine, Chief of Police John Dahlberg, Commander Tim
Janowick, Human Services Director Nancy Morgan, Director of Public Works Glen Andler, Deputy
Director of Public Works Sean Dorsey, Director of Finance David Erb, Deputy Director of Finance Lynn
Jarog and Finance Administrative Assistant Lisa Burkemper. Chairman Charles Bennett was absent.
II. ApPROVAL OF MINUTES
There was a discussion regarding a typographical error in the minutes. Commissioner Ann Smilanic
motioned to approve the minutes of May 22, 2008 as corrected. Commissioner Wayne Gardner seconded
the motion. The minutes were accepted as corrected.
III. REVIEW OF PROPOSED (2009-2013) CAPITAL IMPROVEMENTS PLAN AND
DISCUSSION ON DEPARTMENTAL ISSUES - INTERNAL AND EXTERNAL
Summary
Director of Finance David Erb provided a brief summary of the proposed CIP and advised that departments
would be presenting their CIP items along with any internal and external issues. The 2009-2013 CIP
contains approximately $57.2 million in projects, with first year projects totaling about $22 million.
Human Services
Director of Human Services Nancy Morgan provided an overview of the Human Services department and
outlined the wide range of social and nursing services the department provides.
Ms. Morgan spoke about a $200,000 state grant they received recently from the Department of Aging and
advised what types of equipment would be purchased with the grant money. The Village should receive the
grant money before the end of June, 2008.
Community Development
Director of Community Development Bill Cooney began by outlining the department programs that appear
in the proposed CIP, which are continuations from previous years. The projects include Downtown
Redevelopment and Corridor Improvements.
Mr. Cooney provided an update of several redevelopment projects in various stages throughout the Village.
Mr. Cooney advised the Randhurst redevelopment project was set for the Planning and Zoning meeting on
June 26 and that the proposed new design will be a lifestyle center consisting of retail, offices, restaurants,
entertainment and a hotel. Mr. Cooney also spoke briefly about the triangle redevelopment, the Norwood
condos and rowhomes for sale and the commercial Bosch building and Opus/ Alter Development.
Also discussed was the Crime Free Housing Program that has been very successful in licensing rental
property owners throughout the Village. At this time an estimated 90% of owners are now licensed.
Mr. Cooney provided the Commission an outline of the RT AP Grant that will address the ability to move
individuals throughout the community. The Village hired a consultant who will look at the proposed
Star line along the tollway, the RT A in and out of the community and bike routes throughout town. The
process is anticipated to last approximately 9 months and will include discussions throughout the year with
the public.
Commissioner John Kellerhals asked what the costs to the Village are as related to the redevelopment of
Randhurst and the Triangle Project. Mr. Cooney advised that the costs had been openly discussed at public
meetings in May and that the costs associated with the projects were broken down by public and private
contributions. Mr. Cooney stated that he could provide what was presented to the Village Board at the
public meetings.
Commissioner Vince Grochocinski asked what kind of sales tax rebate incentives the Village would be
offering the developer of Randhurst. Mr. Cooney advised that there is a revenue sharing agreement with
the developer and the incentive could be worth as much as $25 million dependent on the success of the
redevelopment. Mr. Janonis advised that this complex information is being sent out to the Village Board
and that the Finance Commission could be included in this mailing.
Fire Department
Deputy Fire Chief John Malcolm began with a summary of the department's items in the 2009 - 2013
proposed CIP. Deputy Chief Malcolm spoke about the Fire Station 14, Public Works expansion and the
Emergency Operations Center projects. Deputy Chief Malcolm advised that an architect has been hired and
a schematic design has been started. The department is also currently in the process of hiring a construction
manager for the projects.
Deputy Chief Malcolm then provided an update on the internal and external issues within the Fire
Department. Deputy Chief Malcolm mentioned that the call volume increased last year and is mostly
attributable to the August storm event. There was also a discussion regarding the process of rechassising
ambulances instead of purchasing entirely new ambulances. The current Ford ambulance vehicles have had
mechanical problems recently and the department is looking at other alternatives to the Ford vehicle. The
department will monitor the Ford vehicles and see if they are the best solution.
Commissioner Ann Smilanic asked Deputy Chief Malcolm if the department is planning the construction of
the new fire station with everything they want and think they will need for the future. Ms. Smilanic was
concerned about the department coming back in a couple of years and saying the needs of the department
have changed. Deputy Chief Malcolm said that the department is planning a building that will meet the
needs of the community and the department for the present and for the next 30-50 years.
2
Police Department
Commander Tim Janowick began the discussion on items the department has in the 2009 - 2013 proposed
CIP. Commander Janowick specifically discussed the need for new furniture to replace sergeant
workstations and commander offices, replacement of the department's temporary evidence lockers and the
need for a data backup system. The data back up system would be more efficient for the recovery of data or
in the event that the department's system goes down. The department would be able to easily access their
data at another offsite location.
Police Chief John Dahlberg provided a brief summary of the department's internal and external issues.
Chief Dahlberg discussed the traffic unit and the initiatives for which they are responsible for. The unit is
instrumental in the Click it or Ticket program and the Drive 25 Keeps Kids Alive Program. For the traffic
units efforts in the Click it or Ticket program last year, they were awarded a traffic enforcement laser gun,
as they were named best in the state.
Chief Dahlberg also discussed a new program called Operation Summer Heat. This program is a data driven
program that puts approximately 20-25 officers on the streets in problem areas every Thursday night for hot
spot enforcement.
Chief Dahlberg provided an update on the new prisoner transport vehicle, the new firing range system, new
mobile traffic control unit purchased with DUI funds, new speed monitoring trailer purchase and deferring
the purchase of 9 marked squad cars this year. The last item presented to the group was the overtime
control strategies that where implemented and which have been successful in curbing the amount of money
spent in overtime.
Public Works
Director of Public Works Glen Andler highlighted several pressing issues this year. Currently the
department is working on finalizing an exclusive commercial solid waste program. The new program would
make the Village administered refuse collection and recycling program available to approximately 1,000
commercial properties. Recycling will be a huge component to the new commercial refuse program. The
other item discussed was the implementation of a rear-yard drainage improvement program. The innovative
program will utilize a specific fee that is currently collected in lieu of detention reserves to alleviate surface
flooding in established neighborhoods. Approximately $100,000 in fees were collected in 2007 to help
residents with flood control projects. The department is currently in the process of developing criteria to be
followed in order to proceed with the program.
Director of Public Works Glen Andler briefly highlighted several of the items in the proposed CIP
pertaining to Public Works. Public Works Director Andler discussed the traffic signal replacement
program, lift station stand-by power, Kensington Road improvements and the construction of a salt storage
building. Under the IT - Computer CIP section is the proposed purchase of a laptop computers and docking
stations for the foreman crews to be used in the field to enter data instead of going back to the office to enter
the data from manually prepared documents.
3
Administration
Director of Information Technology Joan Middleton outlined several of the projects that were designated as
Computer - Hardware/Software projects in the proposed 2009-2013 Capital Improvements Plan. IT
Director Joan Middleton discussed server virtualization and the need to consolidate servers and provide for
better disaster recovery. Also discussed was the purchase of an EMS reporting system required by the
hospital network that all members of the paramedic system must begin using, the beginning RFP process for
the purchase of new financial software, the purchase of ruggedized laptops for the inspectors in the
Community Development department and the purchase of security cameras for the parking deck located next
to Village Hall.
Commissioner John Kellerhalls expressed his concern over purchasing ruggedized laptops for the Public
Works and Community Development personnel as they appear to be quite expensive and that based on the
life span of the equipment and the potential costs savings, other less expensive alternatives should be looked
at.
Commissioner Ann Smilanic asked why there aren't computer costs in the proposed CIP for the computers
that will be needed in the operation of the Emergency Operations Center. Village Manager Mike Janonis
stated that the initial costs of the computers are included in the cost of the building as outlined in the CIP.
IV. CHAIRMAN'S REpORT
There was nothing to report.
V. FINANCE DIRECTOR'S REpORT
There was nothing to report.
VI. NEW BUSINESS
There was nothing to report.
VII. Next Meeting: July 24, 2008
Commissioner John Kellerhals motioned to adjourn which Commissioner Tom Pekras seconded. The
meeting was adjourned at 10:30 p.m. The next meeting is scheduled for July 24, 2008.
Respectfully submitted,
~G-~WfvYC
Lisa Burkemper
Administrative Assistant
Finance Department
4