HomeMy WebLinkAbout9.1 Motion to accept proposal for 2023 Water Main Replacement Project Design and Construction engineering services [for portions of Emmerson Lane, Debbie Drive, Jerry Drive, Owen Street, School Street, Elm Street, and Lancaster Street] in an amount not toMr�GauC �'d'+rt;�iect
Subject Motion to accept proposal for 2023 Water Main
Replacement Project Design and Construction
engineering services• portions ofEmmerson
Debbie Owen Street,
School Street, Elm Street, . • Lancaster Street"
in an amount not •exceed•
Meeting October 18, 2022 - REGULAR MEETING OF THE MOUNT
PROSPECT VILLAGE BOARD -
Fiscal Impact true
Dollar Amount $186,725.00
Budget Source Water and Sewer Enterprise Fund
Category VILLAGE MANAGER'S REPORT
Type Action Item
As part of the 2017 Water and Sewer Rate Study, replacement of the Village's
water mains, fire hydrants, valves, and other distribution system appurtenances
was identified as a high priority. One outcome of this study was an increase in
funding for water main replacement projects. A primary goal of accelerating the
pace of water main replacements is to reduce the life cycle of water mains from
an unsustainable 600 years to a more pragmatic 130 years.
2018 was the first year of an accelerated water main replacement schedule
supported by new water and sewer rates. Combined, in the first five years of this
accelerated program, the Village has replaced 26,634 feet of water main and
rehabilitated an additional 6,154 feet of water main through the cured -in-place
pipe lining. The Village owns approximately 160 miles, or 844,000 feet of water
main.
In 2023, staff seeks to replace 11,770 of existing 6" water main. The locations
include Emmerson Lane, Debbie Drive, Jerry Drive, Owen Street from Gregory
Street to Central Road, School Street from Gregory Street to Central Road, Elm
1
Street from Highland Street to Thayer Street and Lancaster Street from Lonnquist
Boulevard to Golf Road.
These pipe sections are scheduled for replacement due to multiple water main
breaks within the last 10 years. Plans are to abandon the existing water main in
place and install new water main adjacent to the old one. Associated main line
valves, fire hydrants and residential buffalo boxes will also be replaced. The water
main size will also be increased from 6" to 8" to improve flow and pressure. The
attached location map depict the proposed project area(s).
To design these improvements, staff requires technical assistance from a qualified
civil engineering consultant. Accordingly, staff prepared a detailed request for
proposals (RFP) necessary to solicit these services. A copy of this RFP is enclosed.
Consulting engineers were asked to submit a technical proposal detailing the
firm's background, key personnel, and approach to the project. In addition, each
firm was also asked to submit a separate cost proposal indicating work effort
anticipated and a not -to -exceed fee.
The required scope of work included topography and field data collection;
preparation of plans and bid documents; meetings and obtaining all necessary
regulatory permits.
RFPs were distributed to six (6) local engineering firms and publicized on the
Village's Demandstar website.
Eleven (11) technical proposals and eleven (11) cost proposals were received.
Each proposal was evaluated based on the background of the firm, related project
experience, proposed services and scope of work, schedule work effort and
proposal content. Each firm received a point ranking (total points = 100) for each
criteria. Table 1 below summarized this analysis.
Table 1: Technical Proposal Evaluation
Category
Background Experience
Scope
Schedule Work ContentTotals
Effort
Max. Points
20 20
25
15 10 10
100
2
IMEG
19
19
22
13
9
9
91
Thomas
19
19
22
13
8
9
90
Burns &
19
19
21
13
8
9
89
McDonnell
Chastain &
18
18
20
14
8
9
87
Assoc.
Ciorba Group
17
17
21
13
8
8
84
Arcadis
18
16
22
15
8
8
87
Bloom
19
18
21
13
8
8
88
Company
GSG
18
17
21
14
7
8
84
Consultants
Mackie
17
16
20
14
7
8
82
Consultants
Applied
19
19
21
14
6
8
87
Technologies
Gewalt
Hamilton
19
19
19
14
5
8
84
The highest rated firm was the IMEG Group of Gurnee, Illinois (IMEG).
IMEG's proposal provided numerous examples of successful water main
replacement and rehabilitation projects similar in scale and scope as the proposed
work. Examples cited water main replacement in the Village of Arlington Heights,
Village of Stone Park, and the City of Macomb. A copy of the firm's technical
proposal is enclosed.
In addition, IMEG provided design engineering, survey and construction
engineering services for the Village of Mount Prospect's 2021 water main
replacement and rehabilitation project. The project included the design and
inspection of 8,000 linear feet of water main replacement in various parts of the
Village. IMEG performed well. The project was completed on time and under
budget.
Each firm was asked to submit a cost proposal as well. Table 2 below summarizes
staff's analysis of costs.
KW
Firm
Hours
Total Cost
Cost /
Hour
IMEG
11450
$169,750
$117
Chastain &
11640
$198,399
$121
Associates
Arcadis
11246
$199,449
$160
Burns &
McDonnell
11158
$205,480
$177
Ciorba Group
21087
$267,884.29 $128
Thomas
21121
$284,122
$134
Engineering
Bloom Company
1,674
$291,960
$174
GSG Consultants
21825
$312,035
$110
Mackie
Consultants
21604
$363,660
$140
Applied
Technologies
21271
$350,000
$154
Gewalt Hamilton 3,964 $586,903 $148
IMEG also submitted the lowest cost proposal. A copy of the firm's cost proposal is
enclosed.
It is the opinion of staff that IMEG has allocated sufficient work effort (1,450
hours) to complete the specified scope of work. In addition, and it is the opinion of
staff that IMEG'S proposed hourly rate ($117/hour) and total fee ($169,750) is
customary and competitive for this type of work.
Staff recommends including a 10% contingency in the award for this proposed
contract because time spent on construction engineering and inspection can vary
due to circumstances beyond the engineering consultant's control. For example,
contractor delays, material availability and inclement weather are all parameters
that can lengthen anticipated construction time. Inclusion of a 10% contingency
($16,975) will increase the project award from $169,750 to $186,725.
Alternatives
1. Accept IMEG Group's proposal for design and construction engineering for
4
2023 Water Main Replacement Project
2. Action at discretion of Village Board
Staff recommends that the Village Board accept the proposal for 2023 Water Main
Replacement project design and construction engineering as submitted by IMEG
Group of Gurnee, Illinois in an amount not to exceed $186,725.
ATTACHMENTS:
2023 PROPOSED WATER MAIN REPLACEMENTS. pdf
IMEG cost Proposal.pdf
IMEG Technical Proposal.pdf
Request for Proposals - 2023 Water Main Replacement Project.pdf
5
2023 PROPOSED WATER MAIN IMPROVEMENTS
CAMP MCDONALD RD
IN
i
J oD
W F
N
W+r
S
KENSINGTON RD
410
Tye
CENTRAL RD
LONNQUIST
Map as of September 2022
By JJP/P W
2023 PROPOSED WATER MAIN REPLAGEMENTS.mxd
M
0
J
W
N
EUCLID AV
GOLF RD (RT 58)
J
0
F-
U
W
CL
O
w
a
I -
SEMINOLE LN
Location of Proposed Replacement
F-
6
I
165im", "ll a -a' -Oil-ol ''
I � F 11 �11'
3 Pavement Cores / LPS-663
Sub -Consultant
LS
$7.50000
4 Project Design:
Preliminary Design
Senior Civil Engineer III
24
Coordination with Utility Companies to Access
Civil Field Technician
120
Possible Conflicts with Projected Water Main Install
Civil Designer IV
120
$?9,960.00
Access Alternates for Water Main Location &
Material Types with Associated Costs
Determine Extent of Roadway Rehabilitation
Review with Village Staff
Final Design:
Construchor Drawings and Documents to Include
Senior Civil Engineer III
24
Plan and Profiles with Existing and Proposed Water
Sr. Civil Technician Specialist
120
Main
Civil Designer IV
120
Specifications
Administration
16
$31,800.00
Quantiles
Estimate of Probable Cost
Bidding Documents
5 Permits
Civil Designer III
16
Coordination with Regulatory Agencies (IDOT, IEPA)
Civil Designer
24
Process Permit Applications
Administration
16
$6.44000
6 Bidding Assistance:
Contract Prospective Bidders
Civil Designer III
8
Distribute Plans and Specifications
Civil Designer
8
Attend Pre -Bid Conteience
Administration
8
$2,52000
Attend Bid Opening
Bid Review and Recommendation
7 Full Time Construction Inspection:
Weekly Site Meetings with Project Manager, Village,
Senior Civil Engineer III
16
and Contractor
Field Technician IV
600
Pre -construction Photo Survey
Senior Civil Tech Specialist
20
Full Time Resident Inspector
Senior Field Technician
8
Construction Layout
Civil Designer IV
8
Site Verification to Pay Estimate Quantities
Administration
8
$71,92000
P ocess Pay Request
Prepare Punch List
Verrfv Final Restoration
Piovide As -Built CADD Files
TOTAL
1,450
$169,750.00
Client Executive ! Market Director
$230
Project Executive
$190
Senior Civil Engineering Specialist
$185
Senior Civil Engineer III
$175
Senior Civil Engineer II
$155
Senior Civil Engineer
$145
Civil Project Engineer II
$135
Civil Project Engineer
$125
Civil Engineer
$115
Geotechnical Engineer II
$160
Geotechnical Engineer
$125
Senior Civil Technical Specialist
$155
Senior Civil Designer III
$140
Senior Civil Designei II
$135
Senior Civil Designer
$125
Civil Project Designer II
$115
Civil Project Designer
$110
Civil Designer IV
$105
Civil Designer III
$100
Civil Designer II
$95
Civil Designer
$90
Design Technician II
$80
Design Technician
$75
Land Surveyor III
$150
Land Surveyor II
$130
Land Surveyor
$120
Senior Survey Technician
$100
Survey Technician III
$90
Survey Technician II
$75
Survey Technician 1
$65
Senior Construction Administrator
$130
Construction Administratoi
$125
SPnrnr Field TPrhnirian
$120
Field Technician IV
$100
Field Technician 111
$90
Field Technician II
$85
Field Technician 1
$75
Administrative Assistant
$75
*Adjusted annually,
REIMBURSABLE EXPENSES
Invoiced with a 1.1 multiplier of actual cost, including:
CAD plots, reproductions and delivery costs of
drawings, specifications, and duplicate reports
beyond one set provided at each normal stage of
review
Reproduction of drawings on Mylar media
Plan review fees or imposed government agency
fees
Premium delivery charges
Photographic supplies and developing
Meals and lodging wherr required to travel
overnight
State filing and/or permit fees related to energy
life cycle costs
Necessary consultants
Travel expense: AUtornoNe mileage will be
invoiced at the IRS rate in effect at the time of
travel Travel expenses also Include tolls, parking
fees, taxi, train, airfare, rental cars (CD only), and
other out of pocket expenses.
9
IR III Q U ll:..: S'll lF:01IR 1'Illi 011POSAIII S If IIR
2023 WA'rii:..:.ii'k MAIIIIIN R11M ACIE.W11I 1:'11I
114 AIII11INSlIF4:..:.C"lI 11101N SlI:..:,1IRVllIClI:..:.S
VII III III,,,AGE 011F: MOU1114 II l[-)lIlZ'OSllPIE" C III "'q III11
S ll:..:! P"ll EM 1113 111. II30 p 2022
i P]
•FOL I I 4-a
.. WEST CENTRAL ROAD
MOUNT PROSPECT, I L 056
It is with pride that we present the Village of Mount Prospect with our Statement
of Qualifications for Professional Services for Water Main Replacement design and
Inspection services.
0p 1 Engineering Firm in
• p 50 Greenest Firm in uve
i
IMEG's growing office in Gurnee, IL, led by Principal -in -Charge Harlan Doland, PE, PLS, %
-;-
has the staffing and capability to deliver this project on time and within budget. IMEG
maintains a consistent point -of -contact for municipal engineering services. Harlan
Doland will be the primary point -of -contact for this project with the Village of Mount Prospect. We have assembled a team with recent
experience in watermain replacement projects. Said team completed these tasks. For the Village of Mount Prospect in 2021, on time
and in budget and is readily available to begin work promptly upon your approval. IMEG has the experience and resources to perform all
tasks associated with the scope of services for the project. Our staff resumes are included in this submittal, which demonstrates that our
professionals are considerably qualified and experienced.
Communication is the key to success on any construction project. \A/e have a keen understanding of our role in the project, and the
Importance of communicating effectively. The Village approving regulatory agencies must be fully informed of the project progress and
assured conformance with its Policies, Standards, and Procedures. Residents and businesses along the route of a project must be kept
abreast of how the construction will impact them and must always be kept safe. Communication with the contractor must be firm and
consistent, as they construct the project in conformance to the plans and specifications.
IMEG continues to be the firm of choice in the region because of our ability to seamlessly integrate and manage all activities of the
various parties involved, and to ultimately produce a completed project that exceeds expectations. Thank you for this opportunity to
submit our Statement of Qualifications to be of assistance to the Village of Mount Prospect.
Respectfully Submitted,
Harlan D. Doland, PE, PLS
Client Executive
4850 (3111 Avii�.'.iiI
G ull R N k.11:::, III III... 3.11
IR: 847-336-7-1100
IIII IIIklll.. II'4.IIDau)OlI A11411'.)@ul uP.-.GCOuIu�.COM
11
■
V'VVVW.III M I::I:R..;C IFSIFIX.O
IMEG is the leading U.S.-based engineering design firm that delivers a rare combination
— the broad expertise of a national leader with the personal relationships and deep
collaboration of a local firm.
Our specialties include water and wastewater engineering, food and beverage industrial
design, infrastructure, program management and construction -related services, but our
secret to success is found in our deep bench of 2,000 team members and challenging
ourselves to be thought leaders in the A/E/C industry.
IMEG's civil water and wastewater engineering team has provided professional engineering
design services across the United States and into the Virgin Islands. Our expertise includes
municipal, industrial, and food and process niches. Our expanded resources allow us to tap
into the expertise of our entire corporation and involve in-house experts from various fields
to assist in the design process with our local project partners.
IN"'III III III,,, III IIG Ill,. IIIA III III°1 Illiii', IIII III,,,
II 11 o-::11 III:::'xl:.:, .0 iru u:::.
4.,8!io , kJl l I:::I:::, 1] 6 (.'.)0 3 11
III I1I...AI4mli...AIN1::)@11Ml:..:G : 1~ER.a:.t)M
m fih a re e III lr°III IIp III oy�„III�u,E m
„ " 1\�' `N1'w III i ��9k °i� �° °�II r �II.. d IIIA � °Ili.., �I" ���q Illi DIY III 4'W , s
d I III eIIci MdI III a pa s s i aIIc Ill
f 'o IIr Ill"ln sfo IIII III'll IIV Illg
e riv III 116 o IIIr i In 11 i e rill t�,
a d co r iI i r it i i v l III- i III t III e s
III'°�„ III �� IIIA III yll yll ° Ilu°°�laaro �„ des igII°°Ilu
a Ilu°°IIId
Top 10 Engineering Firm in U.S. (BD+c)
100% Employee -Owned
Full-service Engineering & Consulting
70 Locations
2,000 Team Members
500+ Licensed Engineers
$276M in Annual Revenue
#71 / Top 500 Design Firm List (ENR)
WATER TREATMENT
WASTEWATER TREATMENT
COLLECTION AND
DISTRIBUTION DESIGN
Water Treatment and Distribution
Raw and Treated Water Supply Design
Water Reclamation
Treatment and Distribution
Finished Water Storage
Facilities Planning
Wastewater Treatment Plant Design
Lift Station and Collection Design
Wastewater Reclamation
Sludge Handling
WrIMEG
The FUTURE. Built Smarter.
13
MUNICIPAL
Design, plans, and bid documents
Engineering review
Utility design and planning
Studies
Environmental
Permitting
Construction services
Funding administration
Conformance with federal, state, and
local agencies
TRANSPORTATION
Transportation Design
Bridge Design and Rehabilitation
Interstates and interchanges
Major tvvro-, four-, and six -lane highways
Roads, streets, and rail design
Signal design & Traffic operations design
Transportation Services
Traffic control systems analysis, design,
and implementation
Subsurface Utility Engineering (SUE)
Hydraulic and design reports
Studies
Feasibility
Location Design
Intersection Design Studies (IDS)
Pavement Condition
Traffic Operations
Traffic Signals
Environmental Assessments (EAs)
Right -of -Way plats, plans, and
descriptions
In -Service Bridge Inspection
LSURVEY AND DEVELOPMENT
S u rveys:
Easement and Right -of -Way
ALTA/ACSM land title
Construction and layout
Aerial photo control, topographic,
property, and boundary surveys
3D machine control and 3D file
preparation
Flood elevation certificates
Letter of Map Amendment (LOMA)
applications
Global Positioning System (GPS) control
surveys
LAND ACQUISITION
Project pre -planning
Cost estimating
Route selection
Stakeholder meetings
Title research
Appraisal coordination
Permitting
Negotiation/acquisition
Condemnation/eminent domain support
Relocation assistance
Document preparation and recording
Project database management
Quality Assurance/Quality Control
Property management
Utility cross -easements
Scheduling
Adherence to the Uniform Relocation
Assistance and Real Property Acquisition
Policy of 1970
Field layout and control verification
Property/boundary/topographic surveys
Aerial control
Construction staking
Easements
Wetland mitigation
Feasibility studies
Conceptual planning and design
Coordination with municipalities
Construction plans and documentation
Technical specifications
Site grading
Utility coordination
Storm sewer and storm water detention
design
Sanitary sewer design
Water service and fire protection
Permitting (federal, state, and local)
American with Disabilities Act (ADA)
compliance
Construction administration
• r 6,
Project management
Material specifications and material
testing
On-site observation and documentation
Cost estimating
Project coordination
Plan compliance
Cost tracking during construction
Drawing documentation
14
Harlan Doland, PE, PLS
Civil Client Executive
Steve Grant, PE
Project Manager
Harlan is a Senior Principal and Client Executive with IMEG. He is responsible for
complete management of the Naperville civil engineering team Including principal
design, quality control, proposal preparation, client management, marketing,
establishing and maintaining schedules, establishing manpower needs, and
contract negotiations and administration. He is also experienced In boundary and
topographic surveys, preparation of plats and legal descriptions, and construction
management/inspection/layout.
Village of Mount Prospect, IL, Watermain Rehabilitation project 2020
Village of Stone Park, IL Watermain Rehabilitation project 2010-2022
Village of Arlington Heights, IL Watermain Rehabilitation project 2010-2022
Village Engineer (1995 - Present), Stone Park, IL - Engineering services
Village Engineer (1996 - Present), Third Lake, IL - Engineering services
O'Plaine Road Reconstruction - Lake County DOT, Gurnee, IL - Provided Phase II
engineering services that included surveying, preparation of plan specifications
and bidding documents for the resurfacing of 10 -miles of County Highway
Stearns School Road and Bridge Improvements - Lake County DOT, Lake County,
I L - Rehabilitation of the bridge carrying Stearns School Road over 1-94 in Lake
County, IL. Visual inspection of the structure, preparation of inspection report
along with rehabilitation alternatives and recommendations, design and plan
preparation for a new concrete overlay
Sheridan Road Reconstruction, Waukegan, IL - Master Plan for Lakefront and
Downtown Redevelopment. $9.5M project included a complete roadway
reconstruction, water main and sanitary sewer replacement, three signalized
intersection improvements, a pedestrian underpass, a complete streetscape
enhancement and new street lighting
O'Plaine Road Reconstruction - Lake County DOT, Gurnee, IL - Provided Phase II
engineering services that included surveying, preparation of plan specifications
and bidding documents for the resurfacing of 10 -miles of County Highway
Stearns School Road and Bridge Improvements - Lake County DOT, Lake County,
IL - Rehabilitation of the bridge carrying Stearns School Road over 1-94 in Lake
County, IL. Visual inspection of the structure, preparation of inspection report
along with rehabilitation alternatives and recommendations, design and plan
preparation for a new concrete overlay
Comprehensive Infrastructure Study St. Joseph Hospital, Chicago, IL -
Comprehensive infrastructure study for the expansion of St. Joseph Hospital
Experience
36 Total, 27 with IMEG
Education
University of Illinois, BS Civil Engineer
Registrations
Professional Engineer
Illinois (062-048891)
Indiana (11900224)
Michigan (6201068645)
Wisconsin (30390-6)
Professional Land Surveyor
Illinois (035-003121)
Affiliations
National Society of Professional Engineers
Illinois Society of Professional Engineers
Illinois Professional Land Surveyors
Association
American Society of Civil Engineers
American Public Works Association
American Council of Engineering
Companies
17
Steve is responsible for assisting in design, quality control, proposal preparation,
client management, and project management for civil engineering projects. His
experience includes all phases of civil engineering environmental engineering,
survey and construction layout/guidance. Steve has experience in infrastructure
planning and feasibility studies, commercial and residential subdivision design, site
design, stormwater management, sanitary sewer, water main, storm sewer design,
transportation engineering, project permitting and coordination with regulatory
agencies.
Various Locations - Developed Spill Prevention Control and Countermeasure
(SPCC) plans for various commercial, industrial and municipal locations. This
rule includes requirements for oil spill prevention, preparedness, and response to
prevent oil discharges to navigable waters and adjoining shorelines
East Hazel Crest, IL - Conducted a limited Phase II investigation for historical
PCE contamination, including oversight of well construction, well development,
quantitative and qualitative groundwater analysis. Designed Soil Vapor Extraction
system for remediation of shallow soils contamination.
Libertyville, IL - Oversight of the removal of heating oil Leaking Underground
Storage Tank (LUST). Activities included soil and groundwater investigation,
preparation of site characterization, and corrective action completion reports to
receive No Further Remediation Letter,
Palos Hills, It - Sampled and developed a soil management plan for disposal
of soils In planned development. Oversight of and development of plans for
entrance into the Site Remediation Program (SRP). Conducted oversight of well
construction, well development and groundwater sampling for qualitative and
quantitative use in groundwater modeling.
Chicago, IL - Conducted a limited Phase II site investigation in order to evaluate
recognized environmental conditions for property transfer. Evaluation included
soil and groundwater sampling for volatiles, Polynuclear Aromatic Hydrocarbons
(PAH) and metals.
Calumet City, IL - Provided management and oversight of Leaking Underground
Storage Tank (LUST) removal. Conducted soil testing per TACO regulations to
obtain a No Further Remediation letter.
Walworth, WI - Conducted monthly outfall sampling and quarterly surface and
groundwater sampling in compliance with Wisconsin Department of Natural
Resources regulations. This sampling includes a monthly 24-hour composite
sample from the outfall.
Experience
16 Total, 7 with IMEG
Education
Southern Illinois University, BS Civil
Engineering
Registrations
Professional Engineer
Illinois (062-062539)
Wisconsin (46259)
Michigan (6201067064)
Indiana (PE11800276)
18
William brings more than 12 years of experience providing construction overslte and
quality assurance on multiple construction projects. This vast experience includes
watermain installation, road paving, landfill, and concrete placement projects.
Village of Mount Prospect, It, Survey and construction engineer 6000 -If water
main rehabilitation
Village of Arlington Heights, IL, Survey and construction engineer 2019
Village of Arlington Heights, Arlington Heights, IL, Surveying and construction
engineer for a 13,395 -If Water Main Replacement 2020
Village of Arlington Heights, Arlington Heights, IL, IDOT Watermain Construction
Services
Village of Stone Park, Stone Park, It, Survey and Design Work for Alley
Improvements
Village of Stone Park, Stone Park, It, Stone Park 2021 CDBG Application
Village of Stone Park, Stone Park, It, Construction Services to Frontage Road
Village of Stone Park, Stone Park, It, Construction on 40th Avenue
Experience
12 Total, 1 with IMEG
Education
Morrison Institute of Technology, AA
Degree
19
Theodore Is responsible for land and route surveys. He schedules and oversees the
survey crews, providing boundary, topographic, and construction staking surveys
to aNide range of private and governmental clients. He currently heads Gurnee
Survey Department. He has experience in performing and directing field crews in
the accomplishment of ALTA surveys, topographic surveys and construction staking.
He has experience in writing legal descriptions and preparing plats. Ted currently
using AutoCAD/Civil 3D 2016. Set up control networks with traditional and GPS
equipment.
PTB 181/010 Various Survey/IL 78 Monument, Various Locations, IL - Provide
sub -consultant services to monument approximately 46 -section corners and ties
in sections 1, 12, 13, 24, 25, and 36, T22N-R4L and also sections 1 and 12, T21N-
R4E. Prepare monument records per IDOT District 2 standards
PTB 168/14, Various Locations, IL - Prepare 10 ROW plats, 10 easement plats,
25 premise plats, staking plans. Stake 259 points with 5/8" rebar and aluminum
cap. The scope includes to write 25 legal descriptions for ROW takes and 25
descriptions for easements
PTB 168/14 Various Surveys, Various Locations, IL - This project consisted of
performing a full hydraulic topographic survey and creation of a DTM south of
Hanover, IL for Box Culvert #SN 043-1024 over an unnamed tributary to the
Apple River, 0.9 -miles +/- NW off Whitton Rd. The survey included topographic
data from R.O.W. to R.O.W. Centerline data for I L Route 84 was provided by the
Department
Bus Parking Facility, Gurnee, IL - Prepared concept plan and preliminary project
budget. Performed topographic and boundary survey of site. We provided erosion
control, stake building box with off -sets and grade, storm sewer structures,
sanitary structures, water valve vault, stake parking lot and access road (rough
grading), stake parking lot and access road with off -sets and grades (final
grading), stake bio -Swale, stake site lighting and fencing, and as -built site utilities
and geometrics
S02 Modeling Data Collection, North Chicago, IL - Provided survey services to
obtain the site data requested by the ILPA for their use in preparing a S02 Model.
They also provided services to obtain additional ground elevation data and add to
current drawings
North Chicago and Abbott Park, IL - Various Abbott Laboratories Projects
(Boundary and Topographic Surveys and Building Layout and Control)
Experience
30 Total, 29 with IMEG
Education
College of Lake County, AA Science
Santa Barbara City College, AS
California Polytechnic State University,
Construction Management
University of Wisconsin, Extension
Introduction to MicroStation
Registrations
Professional Land Surveyor
Illinois (035-003395)
Wisconsin (2396-8)
Member of I PLSA
20
MCHARD LEEECK
CONSTRUCTION MANAGEMENT
Experience
2 Total, 1 with IMFG
Education
University of Wyoming
Richard is responsible for performing as a resident engineer and
quality control on a variety of transportation projects. He is also
responsible for overseeing construction inspection, surveying,
documentation, paving appurtenance work and performing
constructability reviews.
U.S. Silica, Ottawa, IL, Structural steel support for pump house
wrap design
Village of Stone Park, IL, Survey and design work for alley
improvements
Village of Stone Park, IL, 2021 CDBG construction, survey,
design water main and road rehabilitation
Village of Arlington Heights, IL, Verify existing right-of-way and
easements, topographic survey and compile existing utility
information
Village of Bureau Junction, IL, Resident project construction
observation services
Village of Cedar Point, IL, Water Main Design 18,000 lineal
feet of 6' water main, fire hydrants, air release valves and one
booster pump station, building and standby generator
Village of Mount Prospect, IL, Project administration, survey,
testing, project and final design, permitting, bidding and
construction inspection for the 2021 water main replacement
and rehabilitation project
Axs Points - Illinois, West Chicago, IL, Topographic survey and
prepare documents required for the approval of the installation
of 485 feet of underground CATV cable
College of Lake County, Grayslake, IL, Topographic Survey of
Parking Lot 3 and 4 Resurfacing
KOLE KAMINE
CIVIL DESIGN
Experience
6 Total, 6 with IMEG
Education
Southern Illinois University, Civil Engineering
Kole Is responsible for providing solutions to engineering issues
that are then checked and edited by a licensed Professional
Engineer. He creates proficient, detailed, and precise plan sets
that are used for distribution as contract documents. Kole has
knowledge in Autodesk based software, and in creating plans and
conceptual layouts for exhibits. His technical writing skills have
come in to practice vvith specifications.
9TI S
Village of Third Lake, IL Construction Administrative services
for the Village
Village of Stone Park, IL Construction Administrative services
for construction on 40th Ave
Village of Stone Park, IL Construction Administrative services
for the Village of Stone Park for the Frontage Road
Village of Arlington Heights, IL, Construction Administrative
services for the watermain lining
Village of Arlington Heights, IL, Construction Administrative
services for IDOT watermain construction services
Lake County Division of Transportation, Beach Park, IL,
Construction Administrative services Beach Park McClory Bike
Path contingency for uncontaminated fill certification for clean
construction and CCDD for a storm sewer replacement along
both right-of-ways of Wadsworth Road
Village of Gurnee, IL, Engineering and construction observation
services
Village of Lakemoor, IL, Construction Administrative services
for Route 120 Westerly Watermain Construction Services
Village of Woodhull, IL Construction Documents, Bid, and
Survey services for the Last Lift Station Forcemain Design
Gurnee Park District, Gurnee, IL, Survey, Design, Bidding and
Construction Services
21
M . " t :' : 1CIVIL DESIGN
Experience
30 Total. 30 with IMEG
Education
AAS in CAD Drafting and Architectural/Civil Technology
Devey University
Edward's principal duties are in the field of CADD Design and
Drafting. He has worked on transportation, water, storm and
sanitary sewer projects and his experience includes drafting on
topographic surveys, preparation of construction documents and
setup of construction layout. Eduardo is very knowledgeable in
AutoCADD, MicroStation along with associated design software.
Gilbane Building Company - Chicago, Lake Forest, IL, Site utility
layout for sanitary sewer, water main, storm sewer, and electric,
site grading and paving layout, and building layout services
City of Waukegan, It, Provided surveying, civil engineering,
and construction management services for the replacement
of 2,000 -If of water main along Green Bay Rd. and 3,500 -If of
water main along Kellogg Avenue. Performed construction
management services
City of Waukegan, It, 0.8 mile section of urban right-of-way
vital to the City of Waukegan's Master Plan for Lakefront and
Downtown Redevelopment. This $9.5 M project Included
a complete roadway reconstruction, water main and
sanitary sewer replacement, three signalized intersection
improvements, a pedestrian underpass, a complete streetscape
enhancement and new street lighting. Phase I and Phase
II were developed concurrently resulting in the successful
acquisition of federal STP funding ahead of competing
municipalities
Village of Arlington Heights, IL, Surveying and engineering
assistance for a 3 -Year period to prepare construction
drawings, specifications, bidding documents and bidding
assistance of water main replacement
Village of Stone Park, IL, Surveying and civil engineering for
proposed water main and street rehabilitation plans
MIKE HULBACK
SURVEY/GIS
Experience
26 Total, 16 with IMEG
Mike is responsible for the observation of construction procedures
as they relate to acceptable practice, the testing of construction
materials for conformance with design plans and specifications,
and the tracking of project quantities and costs. He is experienced
in performing resident engineering and quality control functions
on a variety of interstate, highway, local roadway, building, site
preparation, and utilities projects.
Village of Mount Prospect, IL, Construction Administrative
Services for survey, testing, project and final design, permitting,
bidding and construction inspection for the 2021 water main
replacement and rehabilitation project
Camosy Construction, Mount Prospect, IL, Construction
Administrator for the Mt. Prospect Police Station Pavement
Layout. Services including: curb removal, pavement removal,
new curb, new pavement, new storm sewer, new sanitary sewer
and sidewalks/concrete stairway
Leo j Fox Trucking & Excavating, Inc., Mount Prospect, IL,
Construction Administration services for the police including
Storm Sewer and Sanitary Sewer
Stone Park, IL, Construction Administrative services for
surveying and engineering services to prepare construction
drawings and bid documents.
Gilbane Building Company - Chicago, Highland Park,
IL, Construction Administrative Services for survey and
construction layout services
Village of Stone Park, IL, Construction Administrative Services
to the Village of Stone Park for the Frontage Road
Village of Arlington Heights, IL, Construction Administrative
Services for IDOT watermain construction services
Village of Lakemoor, IL Construction Administrative Services
for Route 120 Westerly Watermain Construction Services
22
WATER MAIN
VILLAGE OF MOUNT PROSPECT
ZMEMG��11
IMEG provided Civil, Survey and Construction Engineering Services Cosi $2.4 million
for CIPP lining of existing water mains in Mount Prospect, IL. COMPLETION 2021
The project included the design and inspection of 8,000 -If of water
mains in several areas of the Village. Also included in the cost was SERVICES Civil, Survey, Construction Engineering
rehabilitation of roadways, sidewalk and curb replacement and Services
landscape restoration
IMEG also provided, construction inspection, measurements,
computations, and documentation of quantities, and reporting and
record keeping of construction work.
IMEG is providing permitting from IDOT and IEPA as part of the
design process.
24
WATER MAIN
VILLAGE OF ARLINGTON
ARLINGTON HEIGHTS, IL
For the last 10 years IMEG has provided Civil, Survey and
Construction Engineering Services for the installation of new water
mains in Arlington Heights, IL.
The projects included the design and inspection of 15 miles of
new ductile iron pipe water mains In several areas of the Village.
Also included In the cost was the patching and partial overlays
of roadways, sidewalk and curb replacement and landscape
restoration.
IMEG also provided, construction inspection, measurements,
computations, and documentation of quantities, survey and
staking, and reporting and record keeping of construction work.
COST $9.5 million
COMPLETION 2022
SERVICES Civil, Survey, Construction Engineering
Services
25
WATER MAIN
VILLAGE OF STONE R
iri EAVMVITA ff Mk,
For the last 15 years IMEG has provided Civil, Survey and
Construction Engineering Services for the installation of new water
mains in Stone Park, IL.
The projects included the design and inspection of 17 miles of
PVC water mains in several areas of the Village. Also included
in the cost was rehabilitation of roadways, sidewalk and curb
replacement and landscape restoration.
IMFG also provided, construction inspection, measurements,
computations, and documentation of quantities, survey and
staking and reporting and record keeping of construction work.
COST $8 million
COMPLETION 2022
SERVICES Civil, Survey, Construction Engineering
Services
WATER MAIN ExPERIENCE
CITY OF GOLDEN, C
Annual system evaluation and water system improvements
CITY OF HAMILTON, IL
CDBG Water Main Bidding and Construction Inspection
CITY OF MACOMB, IL
Engineering Services to Update the Plans for Water Main
Replacement In the N\N Part of the City
Bidding, Construction Inspection and Guidance for the N\N Phase
2 Water Main Replacement
CDBG Water Main Phase 3 Project, Bidding and Construction
Engineering Services
Plans. Specifications and Permit Applications for the Replacement
of Existing Transite Water Main
CITY OF MANITOU SPRINGS, CO
Ute Trail Water Main Replacement
CITY OF NORTHLAKE, IL
Replacing the Water Main and Resurfacing 43rd Ave
CITY OF ROCK ISLAND, IL
Engineering for \Nater Main Replacement On 35th St from 6th to
7th Ave
CITY OF ROCKY FORD, C
Highway 266 Water Main Replacement
FRENCHMAN'S REEF RESORT, ST. THOMAS, VIRGIN ISLANDS
Reviewed and replaced water main, booster pumps and treatment
Plant
IOWA AMERICAN WATER, DAVENPORT, I
Replacement of Water Main On Division St 76th St and Ridgeview
Drive
TOWN OF JO NSTOWN, C
Thornton Water Main - Johnsto\/\m Floodplain Permitting
VILLAGE OF ARLINGTON HEIGHTS, IL
Improving Water Main Lining with Construction Administration
Services
Surveying and Engineering Assistance for a 13,395 -Lf of Water
Main Replacement
VILLAGE OF COAL VALLEY, I
Water Main, Water tower, Booster Station Design Niabi Zoo Road
and East 3rd Avenue
Water Main Replacement at 22nd Ave
Water Main Replacement at E & W 21st Avenue
VILLAGE OF LONDON MILLS, I L
London Mills Additional Water Main Design
Water Main Bidding and Construction Services for a Phase 3 Water
Main Replacement
VILLAGE OF STONE PARK, I L
Surveying and Engineering Assistance for a 13,395 -Lf of Water
Main Replacement
VILLAGE OF WOODHULL, IL
Water Main Replacement Including Topographic Survey and Design
27
IMEG understands the city is requiring the service of a consulting
engineer to provide design and construction administration
services for 12,000 feet of water main rehabilitation. The team
assembled has extensive experience in these types of projects. We
have outlined a brief design and construction phasing.
)uuir polrqposed � �eula
of s�� �c-�I�� �� ��� � uur ulnl Our lull o clull ofllla���
h") ensi iiia IbcaVIII Ill uln VIII % alrid
e .Ilpelriii elnclw m iui .11lla de m°`IIIl belndh of
iiiii !.' iiiii iilnalull lresat,rlrces.
DATA COLLECTION:
Immediately upon selection, we vvill request copies of available
data including, but not limited to, existing city utility/street maps,
previous site improvements plans, and any other Information
regarding the existing conditions for the site.
TOPOGRAPHIC SYS:
After review of available information, we will schedule the field
surveys of the project site. This information will provide the base
necessary to develop plans sheets and identify any issues that need
to be addressed in the design phase.
ILS AND SUBSURFACEINVESTIGATIONS:
Depending on the availability and relevance of existing
geotechnical information, soil borings and/or pavement cores may
be ordered to determine thickness of the existing pavement, as
well as physical composition of the soils to provide to contractor
for soil disposal.
PRELIMINARY SI
Coordinate with utility companies to obtain all possible utility
information to determine points of possible conflict. Access
alternatives for proposed water main location determine locations
for proposed valves and fire hydrants. Determine appropriate street
rehabilitation.
DESIGN:
Once the preliminary plans are approved, \A/c will begin preparation
of the plans and bidding documents. Upon completion, these
plans will be provided to the team along vvlth the estimate of cost
at this time, we will also begin meeting and coordinating with the
regulatory agencies.
E
COMMUNICATION:
IMEG believes communication with the client, design team and
regulatory agency is essential to a successful project. The project
manager will be In constant contact with the city, design team and
regulatory agency to ensure all aspects of design and costs are
addressed to the satisfaction of the city and in accordance with the
requirements of the regulatory agencies.
CONSTRUCTION ADMINISTRATION PHASE
We will respond to all RFI's and questions the contractor may have,
review material submittals and pay application/pay order requests.
We will provide full time construction observation of the proposed
improvements, so they are constructed in substantial accordance
with the documents. We will, also, perform construction staking
of the proposed improvements. IMEG will prepare as-builts and
incorporate them along with all RFI's and ASI's into the drawings.
The drawings will be submitted electronically to the team and \A/ill
assist in updating the GIS.
All work will be coordinated with and in accordance with city
requirements.
Our proposed team consists of staff from our local offices to utilize
local knowledge and experience —with a deep bench of additional
resou rces.
APPROACH TO PROJECT MANAGEMENT:
During all phases of the project the project manager will provide
the appropriate manpower necessary is available. The project
manager will be involved in all decision making and ensure that
QA/QC is performed on each phase of the project.
STAFFING COMMITMENT:
IMEG has a culture of can do and /ve exhibit that commitment
to all of our clients by doing what ever Is necessary to exceed
exception. That includes involving senior staff in all projects.
We are committing the staff whose resumes are included in our
submittal, these are senior leaders who will remain involved in
the project from beginning to end. While we will involve younger
engineers in a production capacity they will work under constant
senior leadership and guidance.
COMMUNITY CIC TI
We keep an open line of communication with the residents and
business in the project area. We will provide a weekly schedule
updating to all residents and business, along with a 24 hour cell
line to address any concerns or field issues.
E
I
��
muuQ
III ILII
q�g ur r
� IIID
1.
Project Administration:
Client Executive
fia�����mi�i
� io���l
Project Coordination and Review with Village Staff
Project Manager
16
2.
Route Survey
Land Surveyor
10
Verify Existing R.O.W./Easements
Senior Field Technician
60
Topographic Survey
Field Technician
60
Compile Existing Site Utility Information
Civil Designer IV
60
3.
Pavement Cores / LPS-663
Sub Consultant
LS
4.
Project Design:
Preliminary Design
Senior Civil Engineer III
24
Coordination with Utility Companies to Access
Civil Field Technician
140
Possible Conflicts with Projected Water Main Install
Civil Designer IV
140
Access Alternates for Water Main Location & Material Types with Associated Costs
Determine Extent of Roadway Rehabilitation
Review with Village Staff
Final Design:
Construction Drawings and Documents to Include Plan and Profiles with Existing and
Proposed Water Main
Senior Civil Engineer III
24
Specifications
Sr Civil Technician Specialist
140
Quantiles
Civil Designer IV
140
Estimate of Probable Cost
Administration
16
Bidding Documents
S.
Permits
Civil Designer III
16
Coordination with Regulatory Agencies (IDOT, IEPA)
Civil Designer
24
Process Permit Applications
Administration
16
6.
Bidding Assistance:
Contract Prospective Bidders
Civil Designer III
8
Distribute Plans and Specifications
Civil Designer
8
Attend Pre -Bid Conference
Administration
8
Attend Bid Opening
Bid Review and Recommendation
7.
Full Time Construction Inspection:
Weekly Site Meetings with Project Manager, Village, and Contractor
Senior Civil Engineer III
16
Preconstruction Photo Survey
Field Technician IV
600
Full Time Resident Inspector
Senior Civil Tech Specialist
40
Construction Layout
Senior Field Technician
16
Site Verification to Pay Estimate Quantities
Civil Designer IV
16
Process Pay Request
Administration
16
Prepare Punch List
Verify Final Restoration
Provide As -Built CADD Files
Total Hours
1,614
01]
Village of Mount Prospect Professional Services
t it Main IR 1pII c it ent Il esii in and linspection IPiroject Schedule
October NovemberDecember January February March April May June July August
Proiect Administration
hill "' i "° lilli rD i IIID
�w VIII �� ' ul� � Illl�w
m
""" i ii hill "'Vi"µ IIID hill "' Illri "'
�I IIIIIPr""�� VIII VIII , Illlr" VIII "': ,
Illlr lilli IIID
to stjccess�fti�d�y
iliiveIllr' your, Illy llllro jec we, a lr
co lllr'°Ilri Illr° 'iVIII"'t:'t','ecl t. -o yotj as ar
'µ 'flllr~Illrir°ull IIID' Illlr'" lllir°°i e r a lr° hill IIID rov hill
'lhI Ilriiecess&ry resotjIrces to rinee
t V IIIb' to I IIIb VIII � Illlr d� h ed t
mu
uur� a VIII IIIb lllrr'i e lr°i "'t"'s.
31
I-scoll a
L
'kM
Ocl
VHHage
of MoiljiiI IIC:j"irosIpe°t
202,2 Wateii, a Iii ui III' . ^� Ilhm Iii III
iu' °��� °'� iii ui m inC�"�j)e
'iii, iri aind II iiiri IIlie
.°t iii ui m
�p
muu �;
,
gill
,�
�
ilio ii�iiuum"P�I
1. Project Administration:
Client Executive
Project Coordination and Review with Village StafF
Project Manager
16
$3,000.00
2. Route Survey
Land Surveyor
10
Verify Existing R.O.W./Easements
Senior Field Technician
60
Topographic Survey
Field Technician
60
Compile Existing Site Utility Information
Civil Designer IV
60
$21,850.00
3. Pavement Cores / LPS-663
Sub-Consultant
LS
$7.500.00
4. Project Design:
Preliminary Design
Senior Civil Engineer III
24
Coordination with Utility Companies to Access
Civil Field Technician
120
Possible Conflicts with Projected Water Main Install
Civil Designer IV
120
$29,960.00
Access Alternates for Water Main Location &
Material Types with Associated Costs
Determine Extent of Roadway Rehabilitation
Review with Village Staff
Final Design:
Construction Drawings and Documents to Include
Senior Civil Engineer III
24
Plan and Profiles with Existing and Proposed Water
Sr. Civil Technician Specialist
120
Main
Civil Designer IV
120
Specifications
Administration
16
$31,800.00
Quantiles
Estimate of Probable Cost
Bidding Documents
5. Permits
Civil Designer III
16
Coordination with Regulatory Agencies (IDOT, IEPA)
Civil Designer
24
Process Permit Applications
Administration
16
$6,440.00
6. Bidding Assistance:
Contract Prospective Bidders
Civil Designer III
8
Distribute Plans and Specifications
Civil Designer
8
Attend Pre-Bid Conference
Administration
8
$2,520.00
Attend Bid Opening
Bid Review and Recommendation
7. Full Time Construction Inspection:
Weekly Site Meetings with Project Manager, Village,
Senior Civil Engineer III
16
and Contractor
Field Technician IV
600
Pre-construction Photo Survey
Senior Civil Tech Specialist
20
Full Time Resident Inspector
Senior Field Technician
8
Construction Layout
Civil Designer IV
8
Site Verification to Pay Estimate Quantities
Administration
8
$71,920.00
Process Pay Request
Prepare Punch List
Verify Final Restoration
Provide As-Built CADD Files
TOTAL:
1,450
$169,750.00
Ocl
VHHlage of lixill Illi" iir µpec
2023 to ui Mahn uiRIII��'���IIL ����� Ilhm Iii III iu`�d��°d iii �ui�m a in d lRe IA III ace urun el in't IIC�"�j)e s Iii 3uri a ind IIII iris III'ie''t iii ui•m
Client Executive / Market Director
Project Executive
Senior Civil Engineering Specialist
Senior Civil Engineer III
Senior Civil Engineer II
Senior Civil Engineer
Civil Project Engineer II
Civil Project Engineer
Civil Engineer
Geotechnical Engineer II
Geotechnical Engineer
Senior Civil Technical Specialist
Senior Civil Designer III
Senior Civil Designer II
Senior Civil Designer
Civil Project Designer II
Civil Project Designer
Civil Designer IV
Civil Designer III
Civil Designer II
Civil Designer
Design Technician II
Design Technician
Land Surveyor III
Land Surveyor II
Land Surveyor I
Senior Survey Technician
Survey Technician III
Survey Technician II
Survey Technician I
Senior Construction Administrator
Construction Administrator
Senior Field Technician
Field Technician IV
Field Technician III
Field Technician II
Field Technician I
Administrative Assistant
$230
$190
$185
$175
$155
$145
$135
$125
$115
$160
$125
$155
$140
$135
$125
$115
$110
$105
$100
$95
$90
$80
$75
$150
$130
$120
$100
$90
$75
$65
$130
$125
$120
$100
$90
$85
$75
$75
*Adjusted annually.
REIMBURSABLE
Invoiced with a 1.1 multiplier of actual cost, including:
CAD plots, reproductions and delivery costs of
drawings, specifications, and duplicate reports
beyond one set provided at each normal stage of
review
Reproduction of drawings on Mylar media
Plan review fees or imposed government agency
fees
Premium delivery charges
Photographic supplies and developing
Meals and lodging when required to travel
overnight
State filing and/or permit fees related to energy
life -cycle costs
Necessary consultants
Travel expense: Automobile mileage will be
invoiced at the IRS rate in effect at the time of
travel. Travel expenses also include tolls, parking
fees, taxi, train, airfare, rental cars (CD only), and
other out of pocket expenses.
34
REQUEST FOR PROPOSALS
Professional Services /
Water Main Replacement Project - Design and Inspection Services
DATE: September 13, 2022
FROM: Casey Botterman, Water and Sewer Superintendent
Village of Mount Prospect
Public Works Department
RE: Request for Proposal
Water Main Replacement Design and Inspection Services
Your firm is invited to submit a Technical Proposal and Cost Proposal to become eligible for a possible
interview for engineering design and construction management services for the Village of Mount
Prospects, 2023 water main replacement project.
Attached to this memo are:
• A list of materials and information that should be included with your Technical Proposal and Cost
Proposal (Exhibit A).
• A general definition of the scope of work and a schedule of dates and requirements for the selection
process (Exhibit B).
• An overview location map of the project (Exhibit C)
The Village of Mount Prospect appreciates your interest in this project. Any questions regarding this
Request for Proposals can be directed to Casey Botterman, Water and Sewer Superintendent with the
Village of Mount Prospect, by phone at 847-870-5640 or email at cbotterman@mountprospect.org.
A cover letter along with a Technical Proposal and Cost Proposal (Electronically or by mail) should be
forwarded to the following address or email and received no later than 5:00 p.m. on September 30, 2022.
The Technical Proposal and Cost Proposal are to be submitted in separate, sealed packages clearly marked
Technical Proposal for the Village of Mount Prospect Water Main Replacement Project and Cost
Proposal for the Village of Mount Prospect Water Main Replacement Project.
Mr. Casey Botterman
Water and Sewer Superintendent
Village of Mount Prospect
1700 W. Central Road
Mount Prospect, Illinois 60056
cbotterman@mountprospect.org
35
Requirements for Technical and Cost Proposal
Agency: Village of Mount Prospect
Project: Water Main Replacement Project
Your Technical Proposal and Cost Proposal should include the following information:
• Name, address and brief history of firm.
• Organizational chart and resumes of key personnel to be assigned to this project.
• Related experience during the last five (5) years.
• Description of process to accomplish the required tasks of the project. This should include:
• An understanding of the project.
• Objectives to be met as part of the project.
• Your approach to completing the project.
• The projected number of hours to complete the project broken down by task and personnel.
• A project schedule.
• A separate complete cost proposal broken down by task as described in the General Scope of Work.
36
Fvhihit R
General Scope of Work
Agency: Village of Mount Prospect
Project: Water Main Replacement Project
Summary
The Village of Mount Prospect (Village) is seeking proposals from qualified civil engineering
consultants to prepare plans and specifications for the replacement of estimated 12,000 linear
feet of water main within the Village -owned potable water distribution system. Desired services
also include solicitation and review of bids as well as construction management and inspection.
Background
The pipe segments that are up for replacement are due to pipe age and water loss from main
breaks. The project includes the replacement of all associated fire hydrants, main line water
valves and water services from the main to the b -box. Also, a pipe size increase at each location.
Maps of all the location are included in exhibit C and all are located within residential
neighborhoods.
Several of the locations will require a connection to an existing water mains on Central Road and
Golf Road. These connection could potentially need IDOT permitting.
There is also a potential of encountering minimal lead Service lines specifically on Elm Street,
School Street and Owen Street. The Village does have inventory data on the majority of these
properties.
Problem Statement
The Village seeks a qualified Consultant to provide specified civil engineering services necessary
to let, award, and implement a water main replacement project utilizing contracted resources.
The scope and scale of this proposed project will be limited by available funding.
Project Scope
The consultant will provide professional engineering services and provide, at a minimum, the
following:
Design/Bidding Phase
• Consultant shall prepare detailed plans and specifications suitable for bidding.
Plans and specifications shall conform to all current Village of Mount Prospect,
Illinois Environmental Protection Agency and Standard Specifications for Water
& Sewer Main Construction in Illinois design criteria.
37
• Consultant will make application for and obtain any and all necessary permits
IDOT, County, IEPA and/or MWRDGC permits.
• Consultant will answer and resolve any IDOT, County, IEPA and/or MWRDGC
concerns or issues with design.
• Consultant shall have a geological and topography survey completed.
• Consultant shall supply a detailed engineer's estimate of costs for construction of
the project.
• Consultant shall submit all bid documents to the Village for review and approval
prior to distribution.
• Consultant shall advertise and solicit bids for the proposed project from
qualified, capable, and experienced water main construction contractors. All
prospective bidders will obtain plans and specifications from the Consultant.
(Printing of documents will be billed at cost to the parties requesting plans.)
• Consultant shall evaluate bids, check references, verify contractor
representations, and make a written recommendation for award to the Village.
• Consultant shall assist the Village in assembling all construction contract
documents for necessary for execution of the awarded contract.
Construction Management and Inspection Phase
• Consultant shall conduct a preconstruction conference with representatives of
the Owner, Contractor(s), Utilities and other interested parties affected by the
proposed construction.
• Consultant shall provide resident engineers, inspectors, technicians, and
surveyors for the project as follows:
• Provide a Resident Engineer/Inspector (RE/1) for daily
observation of the work during the construction period to
observe and record construction progress under the general
guidance of the Engineer. On the basis of on-site observation, the
Engineer will keep the Owner informed of the progress of the
work, shall endeavor to guard the Owner against defects and
deficiencies in the work of the Contractors, and may disapprove
or reject work as failing to conform to the contract documents.
38
• Provide one set of construction survey stakes. The projects are
to be staked only once in the field. Any additional staking will be
at the contractor's expense.
• Prior to the start of construction, the Consultant shall make a
digital photographic survey of the targeted work zone(s) to
document existing conditions of both public and private
property. The survey shall be conducted at a scale sufficient to
note defects in driveways, sidewalks, structures, and landscaping
in or adjacent to probable construction work areas.
• Prepare written daily inspection reports. Reports are to be
delivered to Owner in an electronic format. Digital photographs
documenting work tasks in progress as well as any potential
problems or unusual conditions shall also be included with each
report.
• Assist the Owner in preparation of any necessary change order
and/or field directives.
• Process monthly applications for payment submitted by the
Contractor(s), and forward to Owner with recommendations for
approval and payment.
• Assist the Owner with the resolution of inquiries, complaints, or
concerns raised by residents or the public.
• Review shop drawings and other equipment/material submittals
as may be required by the contract documents.
• Perform a field observation of all completed work before a final
application for payment is processed for the Contractor.
39
Proposed Schedule
Submit proposals
September 2022
select firm
October 2022
award contract to consultant
October 2022
Kick-off meeting
October 2022
Submit preliminary plans to Village
Submit final plans to Village
December 2022
January 2022
Bid Opening
January/ February 2022
Construction
March — September 2022
Final Completion
October 2022
Post project review
November 2022
40