HomeMy WebLinkAboutIV. Fire Station 14 Construction Manager 03/25/2008
INTEROFFICE MEMORANDUM
Mount Prospect
Village of Mount Prospect
Fire Department
TO:
MICHAEL E. JANONIS, VILLAGE MANAGER
FROM:
MICHAEL J. FIGOLAH, FIRE CHIEF
DATE:
MARCH 18, 2008
SUBJECT: PHASE I FACILITY PLANNING - NEXT STEPS
Steady progress on the Phase I facility improvements is being made. This memorandum is
intended to provide a status overview of the progression, illustrate the next steps, and
provide the Village Board with background in preparation for the March 25, 2008
Committee of the Whole meeting. Staff, at this meeting will elicit Board approval for the
recommended actions as outlined below.
Next Steps
There are several methods used within the construction industry when it comes to
designing, constructing, and/or remodeling buildings. Staff recommends the Construction
Management "At Risk" process for this project. This same process was used to design and
construct the Village Hall and parking deck in 2004 and staff found that process to be
productive and cost efficient. The following illustrates the suggested sequence of events to
proceed with the facility improvements:
1. Finalize Land Agreement for Fire Station 14
2. Select Construction Manager- see below
3. Negotiate design services contract with SRBL Architects. See below
Finalize Land Agreement for Fire Station 14 - Staff from the River Trails School District
26, River Trails Park District and the Village continue to meet in an effort to finalize a land
agreement.
Select Construction Manager - On February 12, 2008 staff presented an overview of the
proposed facilities project status and received permission to enter into contract with SRBL
Architects for their services in managing the selection process of a Construction Manager.
Staff has met with SRBL on several occasions to determine the appropriate course of
action. In accordance with state and local law, the selection of a Construction Manager is
not required to meet the competitive bidding process. The selection process is designed to
pick the most qualified professional and then negotiate a price for service. Of course the
statute does not prohibit the Village from going out to bid for this service. It is staff's
recommendation to send Request for Proposals to a maximum of five (5) Construction
MARCH 18, 2008
PHASE I - NEXT STEPS
PAGE 2
Management vendors. Staff will then make a selection based upon past positive
experience of the Village and recommendations from SRBL Architects based upon their
experience. See Attachment A - Request for Proposals - Construction Manager Services
DRAFT.
Negotiate design services contract with SRBL Architects - The selection of an
architect is another professional service similar to the Construction Manager selection. It is
staffs recommendation to begin negotiating with SRBL Architects for design services of the
identified Phase I facility improvements. Staff recommends this vendor based upon their
performance on the following projects:
1. Fire Station 12 Renovation - A complete rehabilitation of this structure
that was originally built in 1964 was necessary and renovation was
completed in 2003. While the structure itself was solid, the mechanical
systems, space usage, windows, and interior finishes desperately needed
improvements. SRBL Architects was hired to perform a feasibility study
and construction design of the fire station. Their performance was
exemplary. The project was completed on time and on budget.
2. Facilities Study - In 2006, the Village developed a Request for
Proposal/Qualifications for firms to conduct a space needs study for the
facilities eventually identified in the Fire, Police and Public Works
Departments. SRBL Architects was awarded the contract. While the
Phase I Facilities Study is complete and has already been presented to
the community, Phase II is nearing completion and should be ready for
public presentations by the end of this year. Staff is very pleased with the
overall work performed in relation to the Phase I Facilities Study.
This design services contract would cover schematic design, design development and,
should a final Village Board decision to proceed be made, construction documents. The
schematic design and design development phases will result in the production of more
specific information necessary for further review and discussion of the products by the
Village Board and residents. The contract would be structured so that the Village has the
option to abandon the project at anytime.
Conclusion
While the land agreement for the property that will ultimately house the new north side fire
station has not yet been finalized, I recommend moving forward with the steps identified
above.
Schematic design should begin as soon as possible so as to be in position to begin
construction on these projects before the start of adverse weather conditions this coming
winter. Additionally, construction costs continue to increase and locking into construction
contracts early will limit further price escalation.
MARCH 18, 2008
PHASE I-NEXT STEPS
PAGE 3
The timeline in Attachment B is conservative given the scope of the proposed projects.
However, there is still a possibility for construction to begin this fall if we move through the
decision making process and reach a favorable conclusion.
Village staff and Jake Davis of SRBL Architects will be present at the March 25, 2008
Committee of the Whole meeting to discuss the next steps for Phase I of the Facilities
Study.
MF
Attachment A & B
~.~~
rm
SRBL
AACHITECl"S
1 / ,'.
Attachment A
Village of Mount Prospect
Fire Station 14
Addition and Remodel at Public Works
Emergency Operations Center
Preliminary Outline Project Schedule*
Task
Proposed Completion Date
Architectural Services Approval
ApriVMay 2008
Selection of a Construction Manager ApriVMay 2008
· Necessary to begin planning construction phasing
· Early budget and cost conscious design
Schematic Design
· Sets basic layout and design of building
· Floor plan organization is determined
· Most meetings
Total Duration - 2-3 months
Start - May 2008
Finish - June/July 2008
Design Development
· By the end of this phase we know:
· What the building will look like
· What products are being specified
Total Duration - 3-4 months
Start - June/July 2008
Finish -Sept/Oct 2008
Total Duration - 3-4 months
Start - Sept/Oct 2008
Finish - Dee 2008/Jan 2009
Construction Documents
· Largest part of the architectural services
· Design is turned into bid documents
· Inclusive of documents for all 3 projects
. If the decision was made to issue a foundation package ahead of the rest of
the design, foundation work could be bid and construction could start as early
as Nov 2008
Bidding/Board Approval
· Bidding is about 3 weeks
· Contractors mobilize following approval
Total Duration - 1-2 months
Start - Jan/Feb 2009
Finish - Feb/March 2009
Construction - Fire Station 14
Total Duration - 11-13 Months
Start - March/April 2009
Finish - Feb/May 2010
Construction - Public Works/EOC
Total Duration - 8-10 Months
Start - March/April 2009
Finish - Nov 2009/Feb 2010
',<,-
",\' \", .,
t, E ~ -, r ," I, '.,J
c: ~ \
~
~
SRBL
AiKH1ITm
Attachment A
* General Schedule Notes
.
Please note that this is a highly preliminary schedule that assumes
Construction Management as a delivery method with possible separate
foundation package issue. Once a CM is selected, significant variations are
possible. However, total design duration of 6-8 months is realistic for
multiple projects of this size and complexity.
.
All dates indicated on the above schedule contingent on timely approvals by
both the Fire Department, Public Works Department and Village of Mount
Prospect for Building and Zoning approvals. Any significant deviation or
delays will have commensurate impact on dates listed above.
· The overall schedule is highly preliminary in nature. SRBL does not
guarantee or otherwise have knowledge of all issues related to schedule.
SRBL does not have control of the construction delivery method selected or
construction scheduling. This is merely a reflection of potential timeframes
based on past experience and our preliminary thoughts on required space
and design of the project.
· Owner/User participation in schematic and design development is crucial.
Time for typical approvals, revisions and design adjustments are built into the
above schedule. An above average timeframe for owner approvals and/or
excessive changes will result in longer SD and DD timeframes. We will work
very closely with all parties to the projects to manage expectations and to
maintain the schedule. Owner participation after the completion of design
development (and the issuance of complete DD materials manual and
progress drawings) the amount of owner involvement is lessened, but no less
crucial.
I { - ,'" ;'~ ~< ':" :; G k f{ ~-: ~; ~.: ~ ( r 1 t? \ ,J :' (": U 0, '/v V'v' V\' '-, i, E ,f,_ ;~, C t I -!.. t" ~ '- ':: 0 f\-,~ r [ p, ~i / 2.: "U 0 :., X ,~'/., " q t C
Attachment B
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY OPERATIONS
CENTER
REQUEST FOR PROPOSALS
CONSTRUCTION MANAGEMENT SERVICES
TABLE OF CONTENTS
Title Pa ge .............................................................................. ....................................... .................. 1
Table of Conte nts ........... ........................................... ............. ............................. ........ .... ................ 1
Instructions for Proposals for
Construction Ma nagement Services Firms ..................................................................... 1- 6
S pecia II nstructio ns............................................................... .............................. .............. ........ 1- 1
Confidentia I Proposal Form ..... ....................... .......................................................................... 1- 8
Fee Pro posa I Form ..................................................... ......................... ........... ...... .......... ........... 1- 9
Genera I Cond itions Form .......................................................................................................... 1- 3
END OF TABLE OF CONTENTS
DRAFT
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY
OPERATIONS CENTER
INSTRUCTIONS FOR PROPOSALS
CONSTRUCTION MANAGEMENT SERVICES FIRMS
SRBL Project # 08105 & 08106
1. PURPOSE
The purpose of these proposals is to permit the Owner to evaluate Construction
Management services firms' capabilities to undertake and complete the construction of the
proposed new Fire Station, Additions and Remodel at Public Works and a new Emergency
Operations Center. The owner intends to award all three projects to one Construction
Manager and receive a guaranteed price for all three projects together. The owner intends
to seek qualified Construction Management services firms to proceed to the oral interview
stage. Upon completion of the interview stage, the owner intends to enter into contract
negotiations with the firm deemed most qualified to successfully provide these services.
OWNER: Village of Mount Prospect
Fire Department
112 E. Northwest Highway
Mount Prospect, Illinois 60056
Mr. Michael J. Figolah
Fire Chief
ARCHITECT: SRBL Architects
1161-A Lake Cook Road
Deerfield,IL 60015
Mr. Jake Davis, AlA
Project Manager
Phone: 847/870-5660
Phone: 847/559-7715
2. WHO MUST OUALlFY
All invited Construction Management services firms who wish to be considered for this
project must submit the required proposal information.
3. FACTORS CONSIDERED
Proposals shall be opened in private to avoid disclosure of proprietary or confidential
information of competing submittals. A list of the names of those firms that have made
submittals will be made available following the closing.
In order to provide a fair basis for determining the qualification of Construction Management
services, the proposal response form contains questions related to the respondent's ability
to perform and experience with the type of work to be bid; the organizational structure of the
firm; contracts completed during the last five years; contracts currently under construction;
contracts being bid; bankruptcy, claims, settlements, and suits; references; experience with
sustainable building projects and financial information. A copy of the form is attached.
A separate, sealed Fee Proposal and General Conditions Form will be required to be
submitted as part of the proposal. These envelopes will not be opened until after the
Proposal Form
Page 2
interviewed firms are ranked by the Owner. The Fee Proposal and General Conditions Form
for the top ranked firm will be evaluated at that time and used as a basis for negotiation with
the top ranked firm. Should the Owner be unable to negotiate to a contract with the top
ranked firm, negotiations will commence with the second ranked firm and will continue in
the same manner until a contractual agreement can be reached.
The ability of the firm to obtain a Performance Bond and a Labor and Material Payment Bond
will be considered but shall not be regarded as the sole test of a Construction Management
services firm's capabilities.
Construction Management services firms will participate in a detailed oral interview to more
fully discuss how their approach to this project satisfies the Owner's criteria and respond to
any questions relative to their proposal.
4. APPLICATION
Proposal information must be submitted on or in the form provided by SRBL Architects, Ltd.
Proposals shall be submitted in a labeled and sealed box or container. Label shall read as
follows:
Proposal for Construction Management Services
Village of Mount Prospect
Deliver to:
Village of Mount Prospect
Fire Department
112 E. Northwest Highway
Mount Prospect, Illinois 60056
Attn. Michael J. Figolah - Fire Chief
Due:
On or before 3:00 p.m.
Tuesday, April 15, 2008
Submittals must be received on or before 3:00 p.m., April 15, 2008, at the Village of Mount
Prospect. Submittal shall be in the form of a binder and have six (6) total copies with
original signatures on all. The Village of Mount Prospect reserves the right to reject any and
all submittals, to waive any informalities in the submittals received and to accept any
submittal which the owner deems most favorable and in the best interest of the Village.
All questions on the overall project and/or requests for interpretation of any part of the
submittal form should be directed to the Architect's office, Mr. Jake Davis (Phone: 847/
559-7715.)
All submittals shall become the property of the Village of Mount Prospect and may not be
returned to the submitting Construction Management services firms.
All costs associated with the preparation of the proposal will be the full responsibility of the
submitting Construction Management services firm.
Proposal Form
Page 3
There will be a pre-proposal meeting at the Mount Prospect Village Hall, 50 S. Emerson at
10:00 am on Tuesday, April 1, 2008.
Electronic versions of the Pre-Qualification Form in Microsoft Word format will be made
available to the Construction Management firms upon request. Please send requests via e-
mail to iaked@srblarchitects.com.
5. FINANCIAL STATEMENT
Data submitted shall include a certified financial statement resulting from an audit of the
Construction Management services firm's records in accordance with generally accepted
auditing standards by a Certified Public Accountant licensed to do business in the state in
which the Construction Management services firm's principal place of business is located.
The audit of the financial statement must have been conducted within the last fifteen (15)
months. See Proposal Form for specific requirements.
6. SIZE OF PROJECTS COMPLETED
In order to qualify, the Construction Management services firm must have successfully
completed or been actively engaged in at least two projects of construction of a similar
nature, cost, and complexity, with a construction cost of $10,000,000.00 or more, within the
past three years.
7. OSHA
This work is to be in accordance with the Williams-Steiger Occupational Safety and Health
Act of April 1990 and other Federal, State, and local rules and regulations. Any and all costs
associated with any fines/penalties determined or imposed by the governmental agency will
be the responsibility of the Construction Management services firm. No costs'of any kind will
be considered to be the responsibility of the Owner or Architect.
8. PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND
The Construction Management services firm shall be responsible to purchase bonds
covering 110% of the entire job cost, including all sub-contractors.
9. INFORMATION ABOUT PROPOSAL PROCEDURES and FORMS
For additional information about the proposal procedures or the required forms, contact:
Mr. Jake Davis, AlA
SRBL Architects, Ltd.
1161-A Lake Cook Road
Deerfield,lL 60015
Phone: 847/559-77115
Fax: 847/272-9510
Proposal Form
Page 4
Email: jaked@srblarchitects.com
A) The Owner wishes to retain the services of a Construction Manager for the project.
B) All laborers and mechanics employed by the contractors and/or subcontractors for this
project shall be paid wages at rates not less than those prevailing wages current at the
time work is performed as determined by the Illinois Department of Labor (Cook County).
Contractors and subcontractors will be required to submit with each request, weekly
payroll documentation to comply with the Davis-Bacon Act.
C) The Construction Management services firm shall maintain a "full time" field
superintendent(s) on the site(s) during any/all project progress. The superintendent
shall not be changed unless approved by the Owner and Architect. The superintendent
must demonstrate successful completion of a project of similar type and scope. Primary
duties of the superintendent are to supervise and coordinate gl[ aspects of the work.
Superintendent must be oresent whenever any trade is working on the oroiect.
D) The Owner is not subject to the payment of Retailer's Occupational Tax or any other state
sales or use taxes.
E) Construction Management services firms qualifications will be considered based on the
following criteria. Criteria is not necessarily listed in order of importance.
. Fire Station experience.
. Public Works experience.
. Emergency Operations Center experience.
. Firm's overall qualifications with similar size and scope of work.
. Project team's experience, qualifications and reputation.
. Experience providing CM services in general and CM at Risk services in particular.
. Performance of previous contracts.
. Experience with sustainable and energy efficient design, including LEED Certification
and fundamental systems commissioning.
. LEED Accredited Professionals on staff.
. Experience with significant renovation work.
. Safety records including OSHA citations in the past three (3) years.
. Abilities, staffing and skills.
. Accuracy of budget and timely completion without delays and/or interference.
. Compliance to Federal, State, and local construction codes and ordinances.
. Bonding capabilities, financial resources.
. Overall quality of firm's response to the proposal.
. Oral presentation.
. Response to interview questions.
. Any other information required by the Owner to determine the most qualified
Construction Management services firm.
F) Construction Management services firm may be disqualified by, but not necessarily be
limited to, the following factors:
Proposal Form
Page '5
. Late submittal.
. Non-compliance to the requested information.
. Incomplete submission and not signed or notarized.
. Reasonable grounds or belief that falsification of sworn statements has been made.
. Submission of more than one proposal, Le. individual firm, joint venture, etc.
. Submittal via fax, telegram, or orally.
. Submittal prepared with other than ink or typewriter.
G) Provide a project time schedule for each project, assuming an award of contract is made
by May 31, 2008.
H) The Construction Management services firm's pre-construction basic scope of services
are to include but not necessarily be limited to:
. Establish a guaranteed maximum price.
. Establish multiple detailed estimates.
. Provide an integral part of the design approach.
. Provide value engineering during the design phase.
. Attend all design meetings with Owner and Architect.
. Establish bidding procedures in conjunction with Architect.
. Establish all scope of work bid packages for bidding.
. Publish notice for pre-qualification of contractors.
. Solicit a minimum of three (3) bids from pre-qualified subcontractors for all trades.
. Conduct public bidding, open and record all bids from sub-bidders.
. Evaluate all bids, prepare recommendation and make presentation to Owner.
. Owner retains and reserves the right to approve and/or reject the CM
recommendation of all sub-bidders contracts.
I) The Construction Management services firm's basic scope of services are to include but
not necessarily be limited to:
. Preconstruction services including cost estimating, scheduling, constructability
reviews, and value engineering during the design phase.
. Responsibility for all Construction Management services and general conditions
services.
. Estimating total project cost.
. Scheduling entire project(s).
. Administration/project coordination.
. On site management.
. Adherence to prevailing wage for all work on site(s).
J) Negotiations: Following interviews, the Village will rank the CM firms as needed to reflect
any changes in ranking based on the results of the presentations and interviews. The
Village will then contact the highest ranking firm and attempt to negotiate a contract for
the services at a fair and reasonable compensation taking into consideration the project
budget and the estimated value, scope, complexity and nature of the services to be
rendered. Should negotiations with the highest ranked firm prove unsuccessful; the
Village will terminate those negotiations and enter into negotiations with the next highest
ranked firm.
Proposal Form
Page 6
K) Following completion of successful negotiations, the Selection Committee will make
recommendation to the Village of Mount Prospect for the award of a contract to the
Construction Management firm.
10. IMPORTANT DATES
Proposal forms are due: on or before April 15, 2008: 3:00 p.m. at:
Location:
Village of Mount Prospect
Fire Department
112 E. Northwest Highway
Mount Prospect, Illinois 60056
Attn. Michael J. Figolah - Fire Chief
11. Construction Management services firm will be required to solicit competitive bids for all sub-
trades via public notice and other methods, If the CM wishes to perform construction with their
own forces, they must state their intention prior to the Notice To Bid and will be required to
submit their bid for each trade separately and one (1) day (24 hours) in advance of the bid due
date. Should Construction Management firms wish to submit multiple bids, then individual bids
for each trade must be submitted. Multiple trade bids on one form will disqualify the submittal
and the bid will be rejected.
12. Construction Management services firms will be required to enter into a Standard Form of
Agreement Between Owner and Construction Manager, A.I.A. A121jCMc-2003 (where
Construction Manager is also the Constructor), including owners modifications. Respondents
are to use the format presented within the "Confidential Proposal Form" to make copies for
submittal. The submittal shall consist of one (1) original and five (5) copies, but all must have
original signatures.
A) All information, including the required fee proposal information, and material which a
respondent wishes to include are to be bound in the submittal.
13. The Village of Mount Prospect reserves the right to select the CM process that it judges best
serves its interest. The Village reserves the right to reject any or all submittals and to waive any
and all informalities or irregularities to any submittal when such is deemed by the Owner to be in
the Owner's best interest.
Special Instructions
Page 1
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY OPERATIONS
CENTER
SPECIAL INSTRUCTIONS
Proiect Descriotions
The Village of Mount Prospect recently completed the first phase of a Village-wide facilities study.
This study identified the need for three individual projects, located on two different sites in town.
These projects are as follows:
Fire Station 14
The proposed new satellite fire station is designed to be 20,724 SF and is to be constructed
on a site adjacent to the existing Station 14 on the north side of Kensington Road, just to the
West of River Road. The Fire Station is to include three (3) drive-thru apparatus bays, living
accommodations for up to seven (7) full time staff, Training Room, Fitness Room, Hose
Tower and a number of storage and support spaces. The building is conceived with 12,000
SF on the ground level and a 4,000 SF partial basement and 4,000SF partial second floor.
The current preliminary estimated cost of construction for Fire Station 14 is $5.4 to 6 million
Additions and Remodel at Public Works - 1700 Central Road
The proposed scope of work at Public Works is as follows:
· Create new construction to accommodate two additional maintenance bays for Fire
maintenance operations at the east and west ends of the existing vehicle maintenance
wing.
· Relocate and replace the existing wash bay and paint booth to allow for the two additional
bays
· Security updates throughout the facility
· Construction of a new storage mezzanine within the Vehicle Maintenance Area
. Replacement of the existing fuel pump island
· Relocation of outdoor seating for the lunch room to accommodate the addition of the
Emergency Operations Center to the southwest corner of the facility.
. Two additional material storage bins.
. Construction of a new pre-engineered cold storage building at Pump Station 16.
. Replace the existing portable generator with a new generator serving all circuits in the
building.
The current preliminary estimated cost of construction for the Additions and Remodel at
Public Works is $1.2 to 1.6 million
Proposal Form
Page 2
Emergency Operations Center (At Public Works)
The proposed new Emergency Operations Center (EOC) is to be approximately 3,500 SF in
size and is to be constructed as a semi-autonomous addition to the southwest corner of the
Public Works facility. The EOC is to consist of a communication center where multiple
department heads, Village staff and elected officials can gather, monitor, communicate, plan
and orchestrate the civic response to emergencies. In addition to a large command room,
there are to be sub-dividable break out conference rooms, a telephone answering point,
toilets, kitchen and pantry. The building is to be of a hardened construction with complete
self-sufficiency, including UPS and full generator backups, the generator including the
possibility of a diesel storage tank.
The current preliminary estimated cost of construction for the Emergency Operations Center
is $1.2 to 1.4 million
The Construction Management services firm's responsibilities shall include providing all pre-
construction and construction services necessary to completely construct all three projects as
described above as will be defined within the construction documents. The expectation is to have
contract documents for all three projects created simultaneously. Construction Management
services and one single GMP are to be provided for all three projects, as if they were one project.
However, this approach is not firm and is subject to alteration based on alternative suggestions by
respondents to this request for proposals.
The project will seek USGBC LEED Certification for New Construction for all three projects. The
Village has benchmarked LEED Silver Certification as a project goal for each.
Agreement
Consideration is being given by the Owner to utilize a Standard Form of Agreement Between Owner
and Construction Manager (where the Construction Manager is also the constructor) (A.I.A.
Document A121jCMc) 2003 Edition with Owner's modifications.
General Conditions of the contract for construction of the project shall be A.I.A. Document A201-
2007, with modifications.
CONFIDENTIAL PROPOSAL FORM FOR
CONSTRUCTION MANGEMENT SERVICES
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY
OPERATIONS CENTER
SUBMITTED TO:
Proposals
Village of Mount Prospect
Fire Department
112 E. Northwest Highway
Mount Prospect, Illinois 60056
Attention: Michael J. Figolah - Fire Chief
Separate Sealed Envelope for Fee and General Conditions Costs
SRBL Architects, Ltd.
1161-A Lake Cook Road
Deerfield, Illinois 60015
Attention: Project Manager Jake Davis
NAME OF PROJECT:
Village of Mount Prospect New Fire Station 14, Additions and
Remodel at Public Works & Emergency Operations Center
QUALIFICATION
PROPOSAL FOR:
Construction Management Services
Submitted by:
(Name of Organization)
Address:
City:
State:
Zip:
Phone:
Fax:
Contact:
Email:
1. Type of Firm:
A. Corporation
B. Partnership
C. Sole Proprietorship
D. Other
Proposal Form
Page 2
2. If the organization is a corporation, provide:
State of Incorporation:
Date of Incorporation:
Name and address of registered agent:
3. How many years has your organization been in business as a Construction Management
services firm under your present name?
Include any ownership changes that have occurred in the last five (5) years.
4. Classification of work within own forces, (list all trades) if any.
5. Number of personnel in organization:
a. Administrative
b. Engineering
c. Office
d. Shop
e. Field
f. Other
Submit an organizational chart.
6. If the organization is not a corporation and does business under a name other than the real
name or names of persons conducting the business, is it registered with the County Clerk in
accordance with the Assumed Business Name Act?
Yes
No
7. Is the organization in any way an outgrowth, result, continuation or reorganization of a
former business?
Yes
No
If yes, give name and address of each predecessor business and the date of the change in
entity.
Proposal Form
Page 3
8. Do the Owners, Partners or Principals have any interests or holdings in any other companies
conducting business in the fields of Construction, Architecture, Cost Estimating, Construction
Management, Engineering, or similar endeavors.
Yes
No
If yes, give name of business, type of business, and name of person with interest or
holdings.
9. Is the organization delinquent in the payment of any tax administered by the Illinois
Department of Revenue?
Yes
No
10. Has the organization ever sought protection under bankruptcy or receivership laws?
Yes
No
If yes, when and explain fully:
11. Has your organization, or any principal, ever failed to complete any work awarded to you?
Yes
No
If yes, explain when, where, and what were the circumstances.
12. What percentage of your total institutional/municipal workload has been performed in the
following manner in the past five (5) years?
a.
b.
Construction Management Services
Construction Management services at Risk (with G.M.P.)
Lump Sum Bid
Other
%
%
%
%
c.
d.
13. On a separate sheet, list name of projects, owners, architects, contract amounts, percent
complete, and scheduled completion of the major construction projects your organization
has currently in progress. What percentage of your organization's resources is committed to
these projects?
Proposal Form
Page 4
14. On separate sheets, list the major Fire/Public Works/EOC projects your organization has
completed in the past five (5) years. This list shall include the name of the project, owner,
architect, brief written description of the project, size of project in square feet, initial
contract amount or G.M.P. vs. final contract amount, date of actual completion vs. date of
contracted completion, total duration of the project, type of contract, and percentage of the
cost of the work performed with your own forces. In addition, describe extra costs and
reason for extra costs incurred to the owner. List names for your Project Team; including
but not limited to Principal in Charge, Project Manager, Estimator, and Field
Superintendent. Provide phone numbers of appropriate job reference individuals from the
Owner, and Architect. List the names of the following sub-contractors and provide contact
names and phone numbers for each: Site Utilities, Excavation, Concrete, Masonry,
Carpentry, Structural Steel, Electrical, Plumbing, HVAC and Telecommunications.
15. On separate sheets, list the other major projects your organization has completed in the past
five (5) years. Please limit this list to those projects of a similar size, scope, complexity and
value to this project, preferably $10,000,000 in value or greater, minimum of $6,000,000.
This list shall include the name of the project, owner, architect, brief written description of
the project, size of project in square feet, initial contract amount or G.M.P. vs. final contract
amount, date of actual completion vs. date of contracted completion, total duration of the
project, type of contract, and percentage of the cost of the work performed with your own
forces. In addition, describe extra costs and reason for extra costs incurred to the owner.
List names for your Project Team; including but not limited to Principal in Charge, Project
Manager, Estimator, and Field Superintendent. Provide phone numbers of appropriate job
reference individuals from the Owner, and Architect. List the names of the following sub-
contractors and provide contact names and phone numbers for each: Site Utilities,
Excavation, Concrete, Masonry, Carpentry, Structural Steel, Electrical, Plumbing, and HVAC.
16. On separate sheets, list the any projects your organization has completed the have included
extensive work within owner occupied facilities. The Additions and Remodel at Public Works
will entail phased construction and all work will be done within owner occupied areas.
Please give at least three (3) examples of such projects with a list of the name of the project,
owner, architect, brief written description of the project, size of project in square feet, initial
contract amount or G.M.P. vs. final contract amount, date of actual completion vs. date of
contracted completion, total duration of the project, type of contract, and percentage of the
cost of the work performed with you r own forces.
17. On separate sheets, list the any projects your organization has completed the have included
"Green Building Initiatives", or USGBC LEED certification in the past five (5) years. Provide a
written description of the "Green" and/or "LEED" work that was included in each project and
the contractors that were responsible for the work. This list shall include the name of the
project, owner, architect, brief written description of the project, size of project in square
feet, initial contract amount or G.M.P. vs. final cOntract amount, date of actual completion
vs. date of contracted completion, total duration of the project, type of contract, and
percentage of the cost of the work performed with your own forces. Please provide the
incremental cost of sustainable features for the project in question expressed as a
percentage of the construction cost.
Proposal Form
Page 5
List steps taken by your organization to assist in the design and construction of LEED or
sustainable and/or energy efficient building projects. This is to include any programs your
firm may have in place for recycling or the acquisition of renewable or recyclable materials.
List names for your Project Team; including but not limited to Principal in Charge, Project
Manager, Estimator, and Field Superintendent. List also all staff members with LEED
accreditation and/or affiliation with the USGBC or any other organizations promoting
sustainable design of buildings. Provide phone numbers of appropriate job reference
individuals from the Owner, and Architect.
Please include a sample of the following: Construction Waste Management Plan, Indoor Air
Quality Plan and LEED submittal cover sheet. Additionally, actual performance values from
Waste Management Plans from at least two (2) past projects are to be furnished.
18. The form of agreement will be the American Institute of Architects Document A121jCMc
"Standard Form of Agreement Between Owner and Construction Manager where the
Construction Manager is also the Constructor", 2003 edition, with modifications. Contract
requirements include the CM soliciting competitive bids for all sub-trades, via public notice
and other methods. Should the CM wish to perform construction with their own forces, they
must state their intentions prior to the Notice To Bid and will be required to submit their bid
for those trades 1~ (24 hours) in advance of the bid closing date. As the CM, are you
willing to abide by this requirement?
Yes
potential suggestions.
No
If No, state your reasons why or
19.
Is your firm an equal opportunity employer? Yes
No
20. Has your firm, or any predecessor or principal for the firm, been named in any litigation,
arbitration claim, mediation, or other settlement agreement in conjunction with past or
present job performa nce?
Yes
No
If yes, state reasons.
21. Provide a resume for each individual likely to be involved in this project. Field
Superintendent must be included. For each individual on the Project Team provide a list of
the projects they are currently involved in, include an Owners reference contact and phone
number for each. For each individual on the Project Team provide a list of the Police
Station projects they have been or are currently involved in, include an Owners reference
contact and phone number for each.
22. List current projects for which your firm is a candidate for contract award:
23. Trade references:
Proposal Form
Page 6
24. Bank references:
25. Name of Bonding Company and name and address of Agent:
Such bonds shall be written by a surety company licensed to do business in the State of
Illinois with a general rating of A minus and a financial size category of Class X or better in
Best's Insurance Guide. Each bond shall be in the penal sum of the Contract Price.
a. State the number of years the bonding company has been of service to your
organization.
b.
State your total bonding capacity
$
c. State your total current available bonding capacity. $
26. Describe your firm's policy in requiring bonding of sub-contractors.
27. Describe your firm's policy with respect to union labor on your projects.
28. Provide evidence of insurance with minimum comprehensive coverage.
a. State your insurance experience modifier rate:
29. Outline your pre-construction services. Identify the intervals and at which stages budgets will
be prepared. Include a sample of the firm's estimate for each stage.
30. A guaranteed maximum orice (GMP) will be required prior to completion of final contract
documents. Describe your firm's capabilities to perform this service and at what oercentage of
documentation comoletion the GMP is typically established. The GMP for this project is to be
established no later than at 95% contract documents. Please note that the GMP for the
"project" is actually the combined costs of all three (3) individual projects.
31. Describe your proposed construction safety program, field management, payout procedures,
quality control, job site meetings and documentation procedures.
32. Attach a copy of the most recent audited financial statement (must be within the last fifteen
months) including an income statement and balance sheet, which must contain the
following information:
Proposal Form
Page 7
a. Current assets: Net fixed assets and other assets; cash, joint venture accounts, accounts
receivable, notes receivable, accrued interest on notes, deposits, and materials and
prepaid expenses.
b. Current liabilities: Accounts payable, notes payable, accrued interest on notes, provision
for income taxes, advances received from owners, accrued salaries, accrued payroll taxes
and other liabilities. Capital: capital stock, authorized and outstanding shares per values,
earned surplus.
c. Date of statement or balance sheet.
d. Name, address, and phone number of Certified Public Accountant/firm and name of
principal accountant preparing the statements.
33. Describe your previous and/or current work history for projects located in Cook County
and/or the Village of Mount Prospect.
Proposal Form
Page 8
M , being duly sworn, deposes and says that he/she is
the of , Construction
Management services firm(s), and the answers to the foregoing questions and all statements
therein contained are true and correct. He/she has examined and carefully prepared this proposal
based upon the pre-qualification documents and all issued addenda and have checked the same in
detail prior to submittal. I have full authority to make statements and submit this proposal on this
firm's behalf.
Name or Organization:
By:
Title:
Subscribed and sworn before me this
day of
2008.
Notary Public:
Notary Stamp:
Dated th is day of , 2008.
Pursuant to information for proposers for above mentioned proposed project, the undersigned is
submitting the information as required with the understanding that it is for confidential use only to
assist in determining the qualifications of their organization to perform the type and magnitude of
work included; and further, guarantee that truth and accuracy of all statements herein made. We
will accept your determination of qualifications sub-contractor, supplier, or any other persons, firms,
or corporations with whom we have done business, or who have extended any credit to us are
hereby authorized to furnish you with any information you may request concerning our organization
including, but not limited to, information concerning performance on previous work or credit
standing with any of them. We hereby release any and all such parties from any legal responsibility
whatsoever of having furnished such information to you.
Each prospective Construction Management services firm making a proposal for Construction
Management services agrees to waive any claim it has or may have against the Owner, the
Architect/Engineer, and their respective employees, arising out of or in conjunction with the
administration, evaluation, or recommendation of any submittal.
Name of Organization
By
Title
Date
Attested to by
Title
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY
OPERATIONS CENTER
FEE PROPOSAL FORM
CONSTRUCTION MANAGEMENT SERVICES FIRMS
Based upon the written submissions, the interview, and any supplementary information submitted in
response to the Village's request, and based upon such independent investigation (e.g. discussions
with previous clients) as the Village determines to be necessary and desirable to assist in evaluating
a firm's qualifications; the Village will rank the finalists in the order of their qualifications for the
Project. The fees will be open after the finalists are ranked and are to be used as a comparative
and negotiation tool.
The Village will then contact the highest ranking firm and attempt to negotiate a contract for the
services at a fair and reasonable compensation taking into consideration the project budget and the
estimated value, scope, complexity and nature of the services to be rendered. Should negotiations
with the highest ranked firm prove unsuccessful; the Village will terminate those negotiations and
enter into negotiations with the next highest ranked firm.
Following completion of successful negotiations, the Village will award the contract to the successful
Construction Management firm.
PROVIDE FEE INFORMATION AS FOLLOWS:
A. Provide proposed fee for Construction Management services to be provided totally for a
complete project(s): %.
B. State the cost included in the fee for pre-construction services prior to the establishment
of the GMP. $
C. Provide proposed anticipated budget cost for reimbursable items listed by completing the
General Conditions Form. No other indirect costs will be considered for reimbursement after
award of this work. It is a requirement of the proposal request that the following items be
included in each firm's General Conditions (not in Sub-Contractor's cost):
. Cost for Project Manager
· Cost for Project Superintendent
. Trailer Cost
· Telephone/fax/copy machine, including service and equipment
· Temporary job site toilets
. Temporary job site water
. Construction Testing
· Survey layout
· Drinking water
. Final Clean-up
. First aid and fire extinguishers
Fee Proposal Form
Page 2
. Dumpsters and administration of Waste Management Plan
. Two temporary project signs (4'x 8' ea) with temporary lighting, including associated sign
permits
. Postage and messenger service
. Reproduction costs during construction
. Safety and OSHA
. Coordination of utility locates
. Bi-weekly construction progress photos
To reiterate, it is mandatory for the purposes of this proposal for the costs of all of the above items
to be included in the Construction Manager's General Conditions. It is not permissible to put the
costs for any of the above items under the subcontractor category.
D. Consideration: All subcontracts will be required to public bid.
E. Change Order (Percentage of overhead and profit for Change Order requests) %
F. Bond rate. % based on current estimated cost of construction (for all three projects) of
$8,000,000 To 10,000,000.
G. In the event of cost of work plus the contractor's fee is less than the guaranteed maximum
price; the undersigned agrees to return all savings to the Owner.
Yes
propose returning?
No
If no, why not? What percent might you
H. Indicate the overhead mark-up on any work your own forces will consider performing
excluding General Conditions. List which trades/work will be considered to be performed by
your own forces.
I. Provide mark-up for fee and General Conditions on any changes in the work after the
establishment of the guaranteed maximum price.
Add
General Conditions
C.M. Fee
$
$
J. State the cost for a 110% Performance Bond based on $8,000,000 To 10,000,000 total
contract value:
K. Construction Management services firm is invited to add any additional items that would be
customarily considered as required on this project.
L. Construction Manager agrees to bidding conditions for work being performed by their own forces
as stated in the Instructions for Proposals for Construction Management Services Firm.
Fee Proposal Form
Page 3
M. Provide name, signature, and title of individual who has prepared the "fee schedule" and does
the firm hereby agree to enter into a contract, if offered, that reflects the above statement?
M , being duly sworn, deposes and says that he/she is
the of , Construction
Management services firm(s), and the answers to the foregoing questions and all statements
therein contained are true and correct. He/she has examined and carefully prepared this proposal
based upon the pre-qualification documents and all issued addenda and have checked the same in
detail prior to submittal. I have full authority to make statements and submit this proposal on this
firm's behalf.
Name or Organization:
By:
Title:
Subscribed and sworn before me this
day of
2008.
Notary Public:
Notary Stamp:
Dated this
day of
,2008.
Pursuant to information for prospective bidders for above mentioned proposed project, the
undersigned is submitting the information as required with the understanding that it is for your
confidential use only to assist in determining the qualifications of their organization to perform the
type and magnitude of work included; and further, guarantee that truth and accuracy of all
statements herein made. We will accept your determination of qualifications sub-contractor,
supplier, or any other persons, firms, or corporations with whom we have done business, or who
have extended any credit to us are hereby authorized to furnish you with any information you may
request concerning our organization including, but not limited to, information concerning
performance on previous work or credit standing with any of them. We hereby release any and all
such parties from any legal responsibility whatsoever of having furnished such information to you.
Each prospective Construction Management services firm making a proposal for Construction
Management services agrees to waive any claim it has or may have against the Owner, the
Architect/Engineer, and their respective employees, arising out of or in conjunction with the
administration, evaluation, or recommendation of any submittal.
Name of Organization
By
Fee Proposal Form
Page 4
Title
Date
Attested to be
Title
The Village of Mount Prospect reserves the right to select the eM process that it judges best serves
its interest. The Village of Mount Prospect reserves the right to reject any or all submittals and to
waive any and all informalities or irregularities to any submittal when such is deemed by the Village
of Mount Prospect to be in the Village of Mount Prospect's best interest.
Fee Proposal Form
Page 5
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY
OPERATIONS CENTER
CONSTRUCTION MANAGEMENT SERVICES FIRM CERTIFICATION
STATE OF
COUNTY OF
. As part of its proposal
for Construction Management services for the NEW FIRE STATION 14, ADDITIONS AND REMODEL AT
PUBLIC WORKS & EMERGENCY OPERATIONS CENTER for the Village of Mount Prospect, hereby
certifies that said Construction Management services firm is not barred from executing said contract
as a result of a violation of Illinois Compiled Statutes, 2002: ARTICLE 33E. PUBLIC CONTRACTS, 720
ILCS 5/33E-1, 5/33E-3, 5/33E-4, 5/33E-7, 5-33E-8.
Signed:
(Signature of Authorized Officer)
Print Name of Signatory:
As Its:
(Title of Signatory)
Dated:
,2008.
Subscribed and sworn to before me by:
I, the undersigned, a notary public in and for the State and County aforesaid, hereby certify that_
appeared before me this day in person and, being first duly
sworn on oath, acknowledged that (s)he is authorized to act on behalf of Construction Management
services firm, and the (s)he executed the foregoing certificate as his/her free act and deed and as
the act and deed of Construction Management services firm.
Dated:
(Notary Public)
(Notary Seal)
Fee Proposal Form
Page 6
Illinois Compiled Statutes. 2002: ARTICLE 33E. PUBLIC CONTRACTS, 720 ILCS 5/33E-1, 5/33E-3,
5/33E-4, 5/33E-7, 5/33E-8:
g33E-1. Interference with Public Contracting: It is the finding of the General Assembly that the cost
the pUblic is increased and the quality of goods, services and construction paid for by public monies
is decreased when contracts for such goods, services or construction are obtained by any means
other then through independent noncollusive submission of bids or offers by individual contractors
or suppliers, and the evaluation of those bids or offers by the governmental unit pursuant only to
criteria publicly announced in advance.
g33E-3. Bid-rigging. A person commits the offense of bid-rigging when he knowingly agrees with any
person who is, or but for such agreement would be, a competitor of such person concerning any bid
submitted or not submitted by such person or another to a unit of State or local government when
with the intent that the bid submitted or not submitted will result in the award of the contract to such
person or another and he either (1) provides such person or receives from another information
concerning the price or other material term or terms of the bid which would otherwise not be
disclosed to a competitor in an independent noncollusive submission of bids or (2) submits a bid
that is of such a price or other material term or terms that he does not intend the bid to be
accepted.
Bid-rigging is a Class 3 felony. Any person convicted of this offense or any similar offense of any
state or the United States which contains the same elements as this offense shall be barred for 5
years from the date of conviction from contracting with any unit of State or local government. No
corporation shall be barred from contracting with any unit of State or local government as a result of
a conviction under this Section of any employee or agent of such corporation if the employee so
convicted is no longer employed by the corporation and; (1) it has been finally adjudicated not guilty
or (2) if it demonstrates to the governmental entity with which it seeks to contract and that entity
finds that the commission of the offense was neither authorized, requested, commanded, nor
performed by a director, officer or a high managerial agent in behalf of the corporation as provided
in paragraph (2) of subsection (a) of Section 5-4 of this Code.
g33E-4. Bid Rotating. A person commits the offense of bid rotating when, pursuant to any collusive
scheme or agreement with another, he engages in a pattern over time (which, for the purposes of
this Section, shall include at least 3 contract bids within a period of 10 years, the most recent of
which occurs after the effective date of this amendatory Act of 1988) of submitting sealed bids to
units of State or local government with the intent that the award of such bids rotates, or is
distributed among, persons or business entities which submit bids on a substantial number of the
same contracts. Bid rotating is a Class 2 felony. Any person convicted of this offense or any similar
offense of any state or the United States which contains the same elements as this offense shall be
permanently barred from contracting with any unit of State or local government. No corporation
shall be barred from contracting with any unit of State or local government as a result of a conviction
under this Section of any employee or agent of such corporation if the employee so convicted is no
longer employed by the corporation and: (1) it has been finally adjudicated not guilty or (2) if it
demonstrates to the governmental entity with which it seeks to contract and that entity finds that
the commission of the offense was neither authorized, requested, commanded, nor performed by a
director, officer or high managerial agent in behalf of the corporation as provided in paragraph (2) of
subsection (a) of Section 5-4 of this Code.
g33E-7. Kickbacks: (a) A person violates this Section when he knowingly either: (1) provides,
attempts to provide or offers to provide any kickback; (2) solicits, accepts or attempts to accept any
kickback; or (3) includes, directly or indirectly, the amount of any kickback prohibited by paragraphs
(1) or (2) of this subsection (a) in the contract price charged by a subcontractor to a prime contractor
or a higher tier subcontractor or in the contract price charged by a prime contractor to any unit of
State or local government for a public contract.
(b) Any person violates this section when he has received an offer of a kickback, or has been
solicited to make a kickback, and fails to report it to law enforcement officials, including but not
limited to the Attorney General or the State's Attorney for the county in which the contract is to
Fee Proposal Form
Page 7
be performed.
(c) A violation of subsection (a) is a Class 3 felony. A violation of subsection (b) is a Class 4 felony.
(d) Any unit of State or local government may, in a civil action, recover a civil penalty from any
person who knowingly engages in conduct which violates paragraph (3) of subsection (a) of this
Section in twice the amount of each kickback involved in the violation. This subsection (d) shall
in no way limit the ability of any unit of State or local government to recover monies or damages
regarding public contracts under any other law or ordinance. A civil action shall be barred unless
the action is commenced within 6 years after the later of (1) the date on which the conduct
establishing the cause of action occurred or (2) the date on which the unit of State of local
government knew or should have known that the conduct establishing the cause of action
occurred.
g33E-8. Bribery: Bribery of inspector employed by contractor. (a) A person commits bribery of an
inspector when he offers to any person employed by a contractor or subcontractor on any public
project contracted for by any unit of State of local government any property or other thing of value
with the intent that such offer is for the purpose of obtaining wrongful certification or approval of the
quality or completion of any goods or services supplied or performed in the course of work on such
project. Violation of this subsection is a Class 4 felony.
(b) Any person employed by a contractor or subcontractor on any public project contracted for by
any unit of State of local government who accepts any property or other thing of value knowing
that such was intentionally offered for the purpose of influencing the certification or approval of
the quality or completion of any goods or services supplied or performed under subcontract to
that contractor, and either before or afterwards issues such wrongful certification, commits a
Class 3 felony. Failure to report such offer to law enforcement officials, including but not limited
to the Attorney General or the State's Attorney for the county in which the contract is performed,
constitutes a Class 4 felony.
Illinois Com oiled Statutes. 2002: DIVISION 42.1 PUBLIC CONTRACTS 65 ILCS 5/11-42.1-1
Delinquent Taxpayers.
gll-42.1-1. (a) Except as provided otherwise in this Section, a municipality may not enter into a
contract or agreement with an individual or other entity that is delinquent in the payment of any tax
administered by the Department of Revenue unless the individual or other entity is contesting, in
accordance with the procedures established by the appropriate revenue Act, its liability for the tax or
the amount of tax. Before awarding a contract, the municipality shall obtain a statement under oath
from the individual or entity that no such taxes are delinquent. Making a false statement is a Class
A misdemeanor. In addition, making a false statement voids the contract and allows the
municipality to recover all amounts paid to the individual or entity under the contract in a civil action.
A municipality may not regulate contracts with individuals or entities that are delinquent in payment
of such taxes in a manner inconsistent with the Section. This Section is a limitation under
subsection (i) of Section 6 of Article VII of the Illinois Constitution on the concurrent exercise by
home rule municipalities of powers and functions exercised by the State.
(b) For purposes of this Section, a person or other entity shall not be considered delinquent in the
payment of a tax if the person or entity (1) has entered into an agreement with the Department
of Revenue for the payment of all such taxes that are due and (2) is in compliance with the
agreement. In that case, the sworn statement required by subsection (a) shall state those facts.
(c) Notwithstanding the provisions of subsection (a), a municipality may enter into a contract
with an individual or other entity that is delinquent in the payment of a tax if the contracting
authority for the municipality determines that:
(1) The contract is for goods or services vital to the public health, safety or welfare; and
Fee Proposal Form
Page 8
(2) The municipality is unable to acquire the goods or services at a comparable price and of
comparable quality from other sources.
Fee Proposal Form
Page 9
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY
OPERATIONS CENTER
CONSTRUCTION MANAGEMENT SERVICES FIRM CERTIFICATION
STATE OF
COUNTY OF
. As part of its proposal
for Construction Management services for the NEW FIRE STATION 14, ADDITIONS AND REMODEL AT
PUBLIC WORKS & EMERGENCY OPERATIONS CENTER for the Village of Mount Prospect, hereby
certifies that said Construction Management services firm is not delinquent in the payment of any
tax administered by the Illinois Department of Revenue (unless the firm is contesting its liability for
such tax in accordance with the appropriate procedures), pursuant to Illinois Compiled Statutes,
2002: division 42.1 PUBLIC CONTRACTS, 65 ILCS 5/11-42.1-1 Delinquent Taxpayers.
Signed:
(Signature of Authorized Officer)
Printed Name of Signatory:
As Its:
(Title of Signatory)
Dated:
,2008.
Subscribed and sworn to before me by:
I, the undersigned, a notary public in and for the State and County aforesaid, hereby certify that_
appeared before me this day in person and, being first duly
sworn on oath, acknowledged that (s)he is authorized to act on behalf of Construction Management
services firm, and the (s)he executed the foregoing certificate as his/her free act and deed and as
the act and deed of Construction Management services firm.
Dated:
(Notary Public)
(Notary Seal)
VILLAGE OF MOUNT PROSPECT
NEW FIRE STATION 14, ADDITIONS AND REMODEL AT PUBLIC WORKS & EMERGENCY OPERATIONS
CENTER
GENERAL CONDITIONS FORM
The following list represents items to be categorized as General Conditions, and are not to be
included as part of the proposed fee. This list is intended for evaluation purposes. During
negotiations with the selected Construction Manager, certain items may be negotiated into the base
fee. Provide an estimate for each item, and indicate whether or not the work will be performed by
your own forces, or assigned to a subcontractor. For the General Conditions. assume a twelve (12)
month construction and a three (3) month construction closeout duration (for all three oroiects.
assuming that thev are done concurrentlv).
All other indirect costs are to be included as a part of the base fee, no other indirect costs will be
considered for reimbursement after award of this work.
General Conditions shall minimally include all labor, materials, equipment and incidentals:
Item Cost fu: fu:
CM SC
Full time on-site Superintendent D N/A
$
Full time Project Manager D N/A
Field office trailer including hook-up, and space for D N/A
construction meetings. $
Telephone/fax/copy machine, including service and D N/A
equipment. $
Temporary job site toilets. D N/A
$
Temporary job site water D N/A
$
Temporary job site heating and ventilation including D D
energy costs $
Temporary job site electrical power and lighting including D D
energy costs $
Temporary job site access road and fire lanes, including D D
initial construction, regular maintenance and removal. $
Temporary job site parking and staging area, including D D
initial construction, regular maintenance and removal. $
Temporary job site enclosures/doors/window openings D D
$
General Conditions Form
Page 2
Item Cost fu fu
CM SC
Temporary job site fencing 0 0
$
Temporary job site barricades 0 0
$
Construction testing 0 N/A
$
Survey layout (site, building, partition and spotted 0 N/A
foundation) $
Snow removal 0 0
$
Street cleaning 0 0
$
Tree protection 0 0
$
Drinking water 0 N/A
$
Generators as needed until temporary power is in place 0 0
$
In progress clean-up 0 0
$
Final clean-up 0 N/A
$
First aid and fire extinguishers 0 N/A
$
Dumpsters and administration of Waste Management 0 N/A
Plan $
Two temporary project signs (4' x 8' ea.) with temporary 0 N/A
lighting, including associated sign permits $
Winter protection 0 0
$
Postage and messenger service 0 N/A
$
Reproduction costs during construction 0 N/A
$
Safety and OSHA 0 N/A
$
Dust protection/partitions 0 0
$
Coordination of utility locates 0 0
$
Traffic Control 0 0
$
Item
Cost
Bi-weekly construction progress photos
$
Water control (grading, pumping and dewatering)
including all pumps and equipment as required. $
Insurance (include in fee proposal, do not include here) $ included in fee
TOTAL
List any additional items that mayor may not be
required:
$
General Conditions Form
Page 3
BY.
CM
o
BY.
SC
NjA
o
o
o
o
o 0
o 0
o 0
o 0
o 0
o 0
o 0
o 0