Loading...
HomeMy WebLinkAbout8.2 Motion to accept proposal for 2020 Water Main Replacement Project4/15/2020 BoardDocs® Pro Agenda Item Details Meeting Mar 03, 2020 - REGULAR MEETING OF THE MOUNT PROSPECT VILLAGE BOARD - 7:00 p.m. Category 8. VILLAGE MANAGER'S REPORT Subject 8.2 Motion to accept proposal for 2020 Water Main Replacement Project Design and Construction engineering services in an amount not to exceed $140,004. Access Public Type Action Preferred Date Mar 03, 2020 Absolute Date Mar 03, 2020 Fiscal Impact Yes Dollar Amount 140,004.00 Budgeted Yes Budget Source Water and Sewer Fund Recommended Action Accept the proposal for 2020 Water Main Replacement project design and construction engineering as submitted by Burns and McDonnell, Inc. of Kansas City, Missouri in an amount not to exceed $140,004. Public Content Information As part of the 2017 Water and Sewer Rate Study, renewal and replacement of the Village's water mains, fire hydrants, valves, and other distribution system appurtenances was identified as a high priority. One outcome of this study was an increase in funding for water main replacement projects. A primary goal of accelerating the pace of water main replacements is to reduce the life cycle of water mains from an unsustainable 600 years to a more pragmatic 130 years. 2018 was the first year of an accelerated water main replacement schedule supported by new water and sewer rates. Combined, in the first two years of this accelerated program, the Village has replaced 8,300 feet of water main and rehabilitated an additional 3,870 feet of water main on Northwest Highway. The 2020 Water Main Replacement project includes four areas; The 800 and 900 blocks of South Owen Street, 800 and 900 blocks of South William Street and the 600 blocks of South Louis and Albert Streets. This year, staff seeks to replace 6,000 feet of existing 6" main on Albert Street, Louis Street, Owen Street and William Street. These sections of water main have experienced multiple breaks within the last ten years. Plans are to abandon the existing water main in place and install new water main adjacent to the abandoned main. The water main size will be increased from 6" to 8" to improve flow and pressure. The attached location maps depict the proposed project areas. Request for Proposals To design these improvements, staff require technical assistance from a qualified civil engineering consultant. Accordingly, staff prepared a detailed request for proposals (RFP) necessary to solicit these services. A copy of this RFP is enclosed. Consulting engineers were asked to submit a technical proposal detailing the firm's background, key personnel, and approach to the project. In addition, each firm was also asked to submit a separate cost proposal indicating work effort anticipated and a not -to -exceed fee. https://go.boarddocs.com/il/vomp/Board.nsf/Private?open&login 1/3 4/15/2020 BoardDocs® Pro The required scope of work included topography and field data collection; preparation of plans and bid documents; meetings and obtaining all necessary regulatory permits. RFPs were distributed to six (6) local engineering firms and publicized on the Village's Demandstar website. RFP Results Nine (9) technical proposals and nine (9) cost proposals were received. Each proposal was evaluated based on the background of the firm, related project experience, proposed services and scope of work, schedule work effort and proposal content. Each firm received a point ranking (total points = 100) for each criterion. Table 1 below summarized this analysis. Table 1: Technical Proposal Evaluation Category Max. Points Burns & McDonnell Ciorba Baxter & Woodman Robinson Bono Applied Technologies V3 Hancock CEC Background 20 19 19 19 18 17 17 17 17 16 Experience 20 19 18 19 19 16 18 18 18 18 Scope 25 21 21 21 20 20 21 22 21 21 Schedule 15 14 13 13 13 13 13 12 13 8 Work Effort 10 8 8 8 8 7 7 7 6 6 Content 10 9 9 8 8 8 8 8 8 7 Totals: 100 90 88 88 86 81 84 84 1 83 76 The Highest rated firm is Burns & McDonnell of Kansas City, Missouri. Burns & McDonnell proposal provided numerous examples of successful water main replacement projects similar in scale and scope as the proposed work. Examples cited water main replacement in the City of Elgin, Chicago and Rolling Meadows. All references checks indicated Burns & McDonnell performed well. A copy of Burn's technical proposal is enclosed. Notably, Burns completed a $4,000,000 transmission main project in the City of Elgin. This project consisted of approximately 5,900 feet of 20" diameter water transmission main, 5,800 feet of 24" diameter water transmission main, 330 feet of 36" diameter steel casing pipe that was installed by jack -and -bore as required when crossing the Canadian National Railroad and 345 feet of 42" diameter steel casing pipe installed by jack -and -bore for crossing of a major highway. All work was completed with a tight timeframe and reference checks indicated Burn's performed well. In addition, Burns & McDonnell has successfully completed several water and sewer infrastructure improvement projects for the Village over the course of the past 20 years. Each firm was asked to submit a cost proposal as well. Table 2 below summarizes staff's analysis of costs. Table 2: Cost Proposals Firm Hours Total Cost Cost / Hour Burns & 964 $127,276 $132 McDonnell Bono Consulting, 1,057 $127,636 $121 Inc. Ciorba Group 1,347 $173,475 $129 Applied 1,432 $183,500 $128 Technologies Baxter & 1,656 $194,715 $118 Woodman V3 Companies 1,608 $202,853 $126. Robinson 1,800 $216,450 $120 Engineering Hancock 2,550 $218,000 $86 Engineering Civil & Environmental Did not $270,000 Did not provide Consultants provide hours hours https://go.boarddocs.com/il/vomp/Board.nsf/Private?open&login 2/3 4/15/2020 BoardDocs® Pro The lowest cost proposal was submitted by Burns & McDonnell of Kansas City, Missouri. A copy of Burns submitted cost proposal is enclosed. It is staff's opinion that Burns & McDonnell understands the proposed project, has prepared a thorough proposal based on extensive experience, requested a reasonable fee, and is well qualified to perform the work. Staff recommends including a 10% contingency in the award for this proposed contract because time spent on construction engineering and inspection can vary due to circumstances beyond the engineering consultant's control. For example, contractor delays, material availability and inclement weather are all parameters that can lengthen anticipated construction time. Inclusion of a 10% contingency ($12,728) will increase the project award from $127,276 to $140,004. Alternatives 1. Accept Burns & McDonnell's proposal for design and construction engineering for 2020 water main replacement project. 2. Action at discretion of Village Board. Staff Recommendation Staff recommends that the Village Board accept the proposal for 2020 Water Main Replacement project design and construction engineering as submitted by Burns & McDonnell Engineering of Downers Grove, Illinois in an amount not to exceed $140,004. i � • �" •��:... ,r � -'. sty R ',.R s• �• � • : ►•.� � �.., _.� r f � f�: i BMcD_Technical Proposal for Village of Mount Prospect Water Main Replacement Project.pdf (5,529 KB) 2020 Water Main Replacement Request for Proposals.pdf (574 KB) Administrative Content Executive Content Motion & Voting Accept the proposal for 2020 Water Main Replacement project design and construction engineering as submitted by Burns and McDonnell, Inc. of Kansas City, Missouri in an amount not to exceed $140,004. Motion by Richard Rogers, second by William Grossi. Final Resolution: Motion Carries Yea: William Grossi, Eleni Hatzis, Paul Hoefert, Richard Rogers, Colleen Saccotelli, Michael Zadel https://go.boarddocs.com/il/vomp/Board.nsf/Private?open&login 3/3 W+E 2020 PROPOSED WATER MAIN IMPROVEMENTS Fp Ros A ��IIIIIIIII C�.I ouomm �� ou� mlmuullll'01p°000lol uum lummmuwnmuuuuumwnmuuuuumwnmuuuuumwnmuuuuuuouuuuuuuuuuwnmuuuuumwnmuuuuumwnmuuuuumwnmuuuuuuo uuuuuuuuuuuuuuuuu � uuu"" o uml I uuuu111°u uuuuum . . . . . . . ............... ................ "I", �"'' uuuuuuuuuuuuuuumwnmuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuwnmuuuuuuuuuuuuuuuuuuuuum a uuuuuuuuuuuuuuuuuulllllllmmnuuuulllllllllllllllllmmnllllllllllllllllllllluummnlllllluuuuuuuuulmnmuuuuuuuuuuummmnuuuum o Immnuuuuuuummmnmuuumum uuuuuuuum !� uuuuuuuummmnuuuuuuuuuuuuuuuuuuumuuuuuuuuuuuuuullllllllllummllllluuuuuuuuuuuuuuuuuullmuuuuuu uummuuuuuuuuummmnuuuuuuIII, uuuuuuuuummmnluuuuuuouuuuuuuuuuuuuuuummnuuuum uuuuuuuuuuuuouuuuuuuuuuuuwnmuuuuuuuuouuuuuuuuuuuuuuuuuuuuuuuuouuuuum o uuuuuuuuuuuuuuuuuuuulllouuuuuullllllllllllllllllllllllllllllllllllllllllllllllllllllouuuuuuuuuuuuuuuummnullllllllllllluuuuuouuumuuum m uuuuuummnuuuuuuuuuuummnuuuuuuuuuuumuuuuuuuuullluuummnuuuuuuuuuuumuuuuuuuuuuuummuum I I uuuuuuumwnmuuuuuuuuuuuuuuuuuumwnmuuuuuuuuuuuuuuuuuuuuuuuuuuuuuumwnmuuuuuuuuuuuuuuuuuuuuuuuuuuuuuumwnmum Mllllllluuuuuuuuuuuuuuuuuullllmmnuuuuuulllllllllllllouuuuuuuuuuuuuuummmnuuuuuuuuuuuuu mmnu mmn uu mmn uullll uuum mmn uuuu mmn uuwnmuv 'wmlw ,mw^ � � � VIII uuum mmn uumm m uuuu m I mmn ummmnl m mmn ummmnl uuu ILII m �uumnmm '" "'N" '_... qm^ � ^� wn uuol uuummmn mmn uuuu mmn uuuu m mmmnml uuuu vs E COU NCI LTRL J� �I p Z' F- p1 _ W�� �� W C� �1 �� to V� ij '04 O� W Z J I LU W 0d14 LU a o W Z J — MORGAN OBRIEN ST Illm'II����������������������������������m����������������������������������������������llll �" Illllllllllllllllmmnllllllllllllll�lllll�llllm��������l�l�lllllllllllllllllmmn Illllllllllmmnll�llllllll III m mlllll���u�llllll I '+hr� �� m m � IIIIIIII aLU F v L uuMhmn or1 0 � m �� Im Him m�°��� III Illlllllmllmn ��� N = E IN Illlmll S BL III 111µL0. � .�.., 111 . o . ,. �,,,.. o� IIII L IIII III � ,�, ,,� ,,, � ,,, �. , n mmnuu mumu uum ism„wm m u u;, a �� �ar�, �,.. � �� � . � �, Weller _, _ SII m mml mml mml mml mmllllmml mml mml mml mmllllmmllllmml mml mml mml umm �� IIIIIII� "�»�� a u a.� m GOLFH U AV INN RST IIIIIIII VIII = IIIIIIIII IIIIIIIII �IIIII ���Immn I���� �m ���� IIIIIIII IIIIIIIII � ,,,., a �o r mlmuullu'01puoolo E SUNSET RmD 'Im ��mmmmmwmm"”"�,mrwmmuuummuuuuuuuuuuumuuuuuuuuuuuuuuuuuuuuuuummuuuuuuuuuuuuuuuuuum muuummnmuuuuuuuuuummnmuuuuuuuuuummnmuuuuuuuuuummnmuuuuuuuuuummnmuuuuuuuuuuuumuuuuuuuuu uuuuuuuuummmnuuuuumuuuuuuuuuuuuuuu �mmmmmwmm' ummuuuuuuuuuumuuuuuuuuuumnmuuuuuummuuuuuuuuuumuuuuuuuuuumnmuuuuuummuuuuuuuuuumuuuuuuuuuumnmuuuuuummu j�uI uuuuuuuuuuuuuuuuuuuuuuuummmnllllllllllllllllllllllllluuuuuuuuu uuuuuuuuuuuuuuuuuuuuuuuuuuuummnuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuu uuuuuuuuuuuuumuuuuuuuuuuuuuummmnuuuuuuuuuullllllmnmuuuullllllllllllllllllmuumuuuuuuuuuuuummnuuuuuuuuuuuuumuuuuum 'I�uuuuuuuuuuuuuuu ummmn uuuuuuuuuuuuuuuuuuuuuuuuuouuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuouuuuuuu uuuuuuuuuuuuuuuuuuuuuuuuuuuuuuulllllllllllouuuuulllllllmuuuuuuuuuuuuuummnuuuuuuuuuuuuuuuuuuuuuuuuuuuu L W �I L6 J O �i00 � IIIIIIIIIIII W IVIE. .F... ...... Gl.... VIII mmmmmmmmmmmmmmmm mmmmmmmmmmmmmmmmmmm�mmmnmm1000,III IIIIIIIII �I m m mlmumumlmumumumummu mumlmumumlmumlmumlmumlmumlmu IIII4IIINiumI m mlmummmumumumu II "' m Imummmummmumumm u I ullu� mummmmmmmummmmmu II Immmmmm uumuummumllllmlllllmllllmlllllmlllllmllllmllllmllllmlllmllllmllllmllllmlllmllllmlllmlllmllllmlllmlu mmlmumumummmlllmlllmlllmllmlllmlllmllmlllmlllmllmllmlllmllmlllmllmllmllmlllmllmllmllmllmllmllmllmllmumumumumlmumumumlmuuuuuoomomum�mnmmm O � C uomlmwmumlllllmmmmummumml � � Fauum�.RD uuuummmlmuuuumuuum '""u' uuummuuuummuuuummuuuummuuuummuuuummuuuummuuuummuuuummuuuummuuuummuuuumiwimuuumuuuummuumm uoummnmmmnmmmuuuummummmum uuum. � ■ uummnummmnummmnummmnummmnummmnummmnuulmnmuulmnmuulmnmuulmnmuulmnmuulmnmuullmulllluumnmumuumumuumumuuml mnmuumnmummuuummnmuumnmuumnmuumnmuumnmummuuummnmuumnmuumnmuumnmuumnmuumnmummuuu uuuumumumlllllllmlllllllm°°°m°°°Im°°°m°°°mllllllmllllllmlllllmllllllmlllllmlllllm111°m°°Imummummummuumummummumuumuumuumuumuumuummmuummmuummmmm �IIIIIIIIIII�IIIIIIIIII�I� luum°olllmllllllllllmm�m 'uuumumummmumumn� uuuuuuuumuuuuuummuuuuummuuuuuumuuuuuumuuuummuuuuumuuuuumuuummuuummuuummuuuumuuuum uummmmnmiiilmlumiiiliiiimlioi"w��ml�lllll@!II �IIIIIIIIIIIIIIIIWN�IIIIIIIIIIIIIIIWN�IIWN�Illllllllll�l�i ummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuuuumuuuuuuuuum uuumumomem mmnummuuummmnummuuulllmnmulllmllllluumnmluumuuummmnummuuuuumuuummmn uumnmuumnmuumnmuumnmuumnmuumnmuumnmuumuuummnmuumnmuumnmuumnmuumnmuumnmuumnmuumnmuumuuummnmuumnmuu��uuouuuuuuuuummN" mmuuummnmummuuummnmummuuummnmummuuummnmummuuummnmummuuum F:\\\\WATER MAIN IMPROVEMENTS\LOCATION MAP.mxd Map as of January 2019 By JJP/PW 2020 PROPOSED IMPROVEMENT LOCATION 0 OL Waft 0 ui CO O a 0 a 0 N O N W z+cr 4 �Q4P ��//�� m uuu uum uummmni mmn uuuu .� a°""' uuuummn ummnumi .j W W Z O� 00 uw W S 1213 8'74 11119,11'', 3!DH03J a21dM Ino -1 s Mi"I11M S 1S rN 3MO F r. >1 � Z 1S Wml3 S z W z Z � 1S 3l............. . ......................dVW S W W II ` b.... . ..... . V40S► I "1S n0 � NS213 W 3 S a H W J Z O F- C.) O J H Z W m W O w a 0 LU U) O a. O w a. O N O N x Z W 2 W O w a 2 Z a �(D N � O W N co 2!1O a O� � m 0.LL3: O oa CM N d N m Q7 LL � m imuum"°p0""oo uuuuuumuuuuuuu mu10' u uuuuuuuuuuuuuuumuuuuuuuuuuuuuuuummuuuuuuuuuumuuuuuumumuuuuuuuuuuuuuuumuuuuuuuuuuuuuuuuuummuuuuuuuuuuuuuuumuuuumuuuuuuuuuuuumuuuuuuuuuuuuuuuummuuuuuuuuuuuuuuuummuuuuuuuuuuuuuuuuummnuuuuuuuuuuuuuuumuuuuuuuuuuuuuuuumm ouuuuummnuuuuuumuuuuuuumnm uuuuuuuuumuuummuuum uuuu°uum oummmw" umwmnuuuuuuuuuuummuuuuuuuuuuuuuuum uuuw^....�ww��������wmwm.������������muuw..•�������������������^���������^���������mnw����•.���m�m�����������m���������������wnuw�^������muuuuuuu����������wn�������w��������������������������w���������mnu��������w������w������w�����������mmu uumoiopi uuuuuu muuuuuuuuuuuuuummmnuuuumuuuuuummmnuuuuuu m mumum""°uu000 ,wnuu of uuuuuummuuuuuuuuuuuuuummmnuuuuuuuuuuumimnmmuuuuuuuuuummmnuuuuuuuuuuuuu uuu mm uuuuuuuuuuuuumuuuuuuuuuuuuuummmnuuuuuuuuuuuuumuuuuuuuuuu ouuum O mmuuuuuuummmnuuuuuuuuuuuuumuuuuuuuuuuuuuummmnuuuuuuuuuuuuummn uuuouopii uuuuuuumim� ?! d 3 7 X211 213 Z a mmm mimrvwooi u uuuuuuuuuuuuuummmnuuuuuuuuuuuuuummuuuuuuuuuuuumuuummmnuumuuuuuuuuuuuumnmuuuuuuuuuuuuuumummuuuuuuuuuuuuuummmnuuuuuuuuuuuuuummmnuuuuuuuuuuuuuummmnuuuuuuuuuuuuuummmnuuuuuuuuuuuuuummmn �gY�mi ouuuuuuuuuuuuuumuuuu"uuuuuuuuuuuuummn uuuuuuuuuuuuuummmnuuuuuuuuuuuuumummnuuuuuuumuuuuuuumuuuuuuuuumuuuuuummmn um �����w uum mmn m ooc "'�" m m uummmn m uuumi m uuuum m uumw������ll�o'o u w O m uum mmn uuuu mmn mmmnuu m uummmn m uuuummn m mioilm °� a uum mmn m uum mmn m uumum uuuummn m uuuu mmn wM wnuuw� �n � wm'-^ .,� ww^ w iw^� w w � w`mn m � S 1213 8'74 11119,11'', 3!DH03J a21dM Ino -1 s Mi"I11M S 1S rN 3MO F r. >1 � Z 1S Wml3 S z W z Z � 1S 3l............. . ......................dVW S W W II ` b.... . ..... . V40S► I "1S n0 � NS213 W 3 S a H W J Z O F- C.) O J H Z W m W O w a 0 LU U) O a. O w a. O N O N x Z W 2 W O w a 2 Z a �(D N � O W N co 2!1O a O� � m 0.LL3: O oa CM N d N m Q7 LL � m REQUEST FOR PROPOSALS Professional Services / Water Main Replacement Design and Inspection DATE: December 30, 2019 FROM: Casey Botterman, Water and Sewer Superintendent Village of Mount Prospect Public Works Department RE: Request for Proposal Water Main Replacement Design and Inspection Services Your firm is invited to submit a Technical Proposal and Cost Proposal to become eligible for a possible interview for engineering design and construction management services for the Village of Mount Prospects, 2020 water main replacement project. Attached to this memo are: 1. A list of materials and information that should be included with your Technical Proposal and Cost Proposal (Exhibit A). 2. A general definition of the scope of work and a schedule of dates and requirements for the selection process (Exhibit B). The Village of Mount Prospect appreciates your interest in this project. Any questions regarding this Request for Proposals can be directed to Casey Botterman, Water and Sewer Superintendent with the Village of Mount Prospect, by phone at 847-870-5640 or email at cbotterman@mountprospect.org. A cover letter along with a Technical Proposal and Cost Proposal (two hard copies and one electronic copy) should be forwarded to the following address and received no later than 5:00 p.m. on January 27, 2020. The Technical Proposal and Cost Proposal are to be submitted in separate, sealed packages clearly marked Technical Proposal for the Village of Mount Prospect Water Main Replacement Project and Cost Proposal for the Village of Mount Prospect Water Main Replacement Project. Mr. Casey Botterman Water and Sewer Superintendent Village of Mount Prospect 1700 W. Central Road Mount Prospect, Illinois 60056 Requirements for Technical and Cost Proposal Agency: Village of Mount Prospect Project: Water Main Replacement Project Your Technical Proposal and Cost Proposal should include the following information: 1. Name, address and brief history of firm. 2. Organizational chart and resumes of key personnel to be assigned to this project. 3. Related experience during the last five (5) years. 4. Description of process to accomplish the required tasks of the project. This should include: a. An understanding of the project. b. Objectives to be met as part of the project. c. Your approach to completing the project. d. The projected number of hours to complete the project broken down by task and personnel. e. A project schedule. 5. A separate complete cost proposal broken down by task as described in the General Scope of Work. Exhibit B General Scope of Work Agency: Village of Mount Prospect Project: Water Main Replacement Project Summary The Village of Mount Prospect (Village) is seeking proposals from qualified civil engineering consultants to prepare plans and specifications for the replacement of estimated 6,000 feet of water main within the Village -owned potable water distribution system. Desired services also include solicitation and review of bids as well as construction management and inspection. Background The pipe segments that are up for replacement are due to pipe age and water loss from main breaks, Location such as in between houses and increase in capacity due to planned site redevelopments. The Village of Mount Prospect's Capital Improvement Plan allows for 2.4 million dollars in funds for water main improvements in 2020. This number includes Consultants fees for design and construction observation. Problem Statement The Village seeks a qualified Consultant to provide specified civil engineering services necessary to let, award, and implement a water main replacement project utilizing contracted resources. The scope and scale of this proposed project will be limited by available funding. Project Scope The consultant will provide professional engineering services and provide, at a minimum, the following: Design/Bidding Phase 1. Consultant shall prepare detailed plans and specifications suitable for bidding. Plans and specifications shall conform to all current Village of Mount Prospect, Illinois Environmental Protection Agency and Standard Specifications for Water & Sewer Main Construction in Illinois design criteria. 2. Consultant will make application for and obtain any and all necessary permits IEPA and/or MWRDGC permits. 3. Consultant will answer and resolve any TEPA and/ or MWRDGC concerns or issues with design. 4. Consultant shall supply a detailed engineer's estimate of costs for construction of the project. 5. Consultant shall submit all bid documents to the Village for review and approval prior to distribution. 6. Consultant shall advertise and solicit bids for the proposed project from qualified, capable, and experienced water main construction contractors. All prospective bidders will obtain plans and specifications from the Consultant. (Printing of documents will be billed at cost to the parties requesting plans.) 7. Consultant shall evaluate bids, check references, verify contractor representations, and make a written recommendation for award to the Village. 8. Consultant shall assist the Village in assembling all construction contract documents for necessary for execution of the awarded contract. Construction Management and Inspection Phase 1. Consultant shall conduct a preconstruction conference with representatives of the Owner, Contractor(s), Utilities and other interested parties affected by the proposed construction. 2. Consultant shall provide resident engineers, inspectors, technicians, and surveyors for the project as follows: i. Provide a Resident Engineer/Inspector (RE/1) for daily observation of the work during the construction period to observe and record construction progress under the general guidance of the Engineer. On the basis of on-site observation, the Engineer will keep the Owner informed of the progress of the work, shall endeavor to guard the Owner against defects and deficiencies in the work of the Contractors, and may disapprove or reject work as failing to conform to the contract documents. ii. Provide one set of construction survey stakes. The projects are to be staked only once in the field. Any additional staking will be at the contractor's expense. iii. Prior to the start of construction, the Consultant shall make a digital photographic survey of the targeted work zone(s) to document existing conditions of both public and private property. The survey shall be conducted at a scale sufficient to note defects in driveways, sidewalks, structures, and landscaping in or adjacent to probable construction work areas. iv. Prepare written daily inspection reports. Reports are to be delivered to Owner in an electronic format. Digital photographs documenting work tasks in progress as well as any potential problems or unusual conditions shall also be included with each report. V. Assist the Owner in preparation of any necessary change order and/or field directives. vi. Process monthly applications for payment submitted by the Contractor(s), and forward to Owner with recommendations for approval and payment. vii. Assist the Owner with the resolution of inquiries, complaints, or concerns raised by residents or the public. viii. Review shop drawings and other equipment/material submittals as may be required by the contract documents. ix. Perform a field observation of all completed work before a final application for payment is processed for the Contractor. Proposed Schedule Submit proposals Jan -2020 select firm Feb - 2020 award contract to consultant Feb - 2020 2019 Kick-off meeting Feb -2020 Submit preliminary plans to Village Mar -2020 Submit final plans to Village Apr -2020 Bid Opening May -2020 Construction June- Oct, 2020 Substantial completion Oct - 2020 Post project review Nov -2020 Village of Mount Prospect 2020 Proposed Water Main Improvements Estimated Fees for Design Engineering & Bid Phase Services January 27, 2020 Task Description Project Senior Manager Engineer (17) (13)' Staff Engineer (10) Project Engineer (8) Subcontractor / Admin. Expenses' (7)' Task Total Task 1 - Project Coordination $ 3,211 Kickoff Meeting 2 $ 25 $ 385 Project Management 6 8 $ 1,560 Design Review Meeting w/ Village (1) 2 2 $ 25 $ 633 Public Neighborhood Meeting (1) 2 2 $ 25 $ 633 Task 2 - Design $ 369454 Existing Data Review 8 $ 992 Develop Scope for Topographic Survey 1 2 $ 428 Field Investigation 8 8 $ 100 $ 11940 Develop Scope for Geotechnical Investigation 1 2 $ 428 Utility Coordination 8 $ 848 24 160 $ 250 $ 24,410 EOPCC 4 8 12 $ 2,984 Quality Assurance Review 12 8 12 $ 4,424 Task 3 - Permitting Support $ 701 IEPA - Water Main Construction Permit 1 4 $ 25 $ 701 Task 4 - Bid Phase Support $ 39158 Provide Bid Documents 2 $ 248 Pre -Bid Meeting 2 2 $ 25 $ 633 Bid Assistance 4 4 $ 1,216 Bid Opening 2 $ 25 $ 385 Bid Review & Recommendation 1 2 $ 428 Assemble Contract Documents 2 $ 248 Total hours 0 64 216 40 8 Hourly Billing Rate $218 $180 $124 $106 $60 Subtotals $0 $119520 $269784 $49240 $480 $ 500 $ 439524 Total Hours 328 Total Fee $ 439524 BURNS Mc..DONNELL Village of Mount Prospect 2020 Proposed Water Main Improvements Estimated Fees for Inspection Engineering Services January 27, 2020 Task Description FTask Client Construction. Manager Manager (17) (13) Resident Engineer (10) Project Inspector Assistant (10) (7) Subcontractor 1 Expenses Task Total - Project Coordination $ 19473 Preconstruction Conference 2 2 $ 25 $ 633 Project Management 2 8 $ 840 Task 2 - Resident Engineering & Inspection $ 759532 Submittal Review 2 8 $ 11352 Resident Engineering / Inspection * 40 480 40 $ 2,500 $ 749180 Task 3 - Project Closeout $ 69747 Punch List 2 16 $ 50 $ 21394 Conforming to Construction Documents 2 8 24 $ 25 $ 41)353 Total hours 0 50 514 64 Hourly Billing Rate 218 180 124 124 Subtotals $0 $9,000 $63,736 $79936 Notes: * RE Based on part-time inspection for 20 hours per week for 24 weeks. CM based on 2 hours per week for 20 weeks INS based on 5 working days at 8 hours per day 8 60 $480 $ 29600 $ 839752 Total Hours 636 Total Fee $ 839752 rrii r ffi,% / U O%%%i 1 a;. UNH All I j ffi,% / U O%%%i 1 a;. UNH BURNS IS MICE.DONNELL Casey Botterman, Water/Sewer Superintendent Village 1700 W. Central Mount Prospect, IL 60056 Dear Mr.Botterman- request for proposals. We bring iVillage - coordinated rj pleaseind our submittal in response to your request for proposals.t either of us if you have any questions. Randall L. Patchett,Department Manager Stephen Crecler j e r 630-724-3276 1 r t t C urns - ser e a' ur ®corn 1431 Copus Place, Suite 400 Downers Greve, IL 60515 630-724-3200 burns e,eem Company prolfille Organizational chart �Resuimes MMM lmm�lf Company profile. Local Presence & Depth of Staff Based in Kansas City, Missouri, Burns & McDonnell has more than 55 offices nationwide, allowing us to provide innovative, timely and cost-effective service to clients. With over 7,500 employee - owners, Burns & McDonnell has professionals with extensive experience in a wide range of engineering, construction and environmental disciplines. Locally, Burns & McDonnell has been providing water services to municipal clients in northeastern Illinois for over 25 years. We have local offices located in Downers Grove and the City of Chicago with a combined staff of over 330 professionals. We anticipate that all of the services in the January 15, 2019, request for proposal will be provided by staff located in our Downers Grove office. We will call upon national experience as required. 117111'1� =17, Burns & McDonnell Engineering Company, Inc. 1431 Opus Place, Suite 400 Downers Grove, Illinois 60515 630-724-3200 1 www.burnsmcd.com BURNS &MSDON N ELL' C:3���:�'uC�i i ►I�1�1��� ori Top Design Firms Engineering News -Record Midwest (2019) Top 100 Design -Build Firms Engineering News -Record (2079) Top 500 Design Firms Engineering News -Record (2079) Construction Management -for -Fee Firms Engineering News -Record (2019) Water Supply Engineering News -Record (2019) Corporate Structure & Semites We provide comprehensive services that cover the full life cycle of a project, finding cost-effective solutions to meet your specific needs. Our services cover all markets in the engineering and construction sectors to bring you and your projects seamless breadth and depth of knowledge and skills. oWater& Transportation o, Commercial, Retail & Environmental Institutional Construction Manufacturing & Aviation Industrial Governmental, Military Oil & Gas & Municipal Power lindustry Rainklings & Recoginiftions Burns & McDonnell has a reputation for providing qualIt y service and innovative solutions to clients. Engineering News-Pecord (ENP) ranks Burns & McDonnell in the top 2 percent of the leading 500 US design it and the top one-third of the leading program management firms, design - build firms, construction management -for -fee firms and construction ma nag ement-at- risk firms. �lin 2019, ENR Midwest inaimedA3urns-&-MtDomelt— No. 2 DesWineir ofthe Yean Also in 2019, 28 of our specific industry services earned spots in the top 30 in their field in ENPs industry -specific rankings. FORTUNE Burns & McDonneH has earned acknowledgment that calls attentio goto our industry leadership and stability, growth and low turnover, S experience and financial strength. We �have al��peaired on Fortuine 1311 MIN C 0 M P A N I E S 1. magaziline's 100 Best Coim�painies TO WORK FOR@ 'to Woirle �Foir 11111stfoir s1ix consecutive 2 0 1 ? years, rainlkiling No. 82foir 20119. The Professional Services Management Journal (PSMJ) has iioolo" presented Burns & McDonnell PS J. PREMIER AWARD FOR CLIENT SATISFACTION with the Premier Award for Client Satisfaction multiple times since its inception. The award recognizes A/E/C firms that go above and beyond in client communication, project delivery performance, and cost-effective solutions and receive award-winning ratings in key client service categories. PSMJ, the leading publisher, trainer and consultancy to the A/E/C industry, annually conducts an independent survey of A/E/C service provider clients to determine overall satisfaction levels in seven categories: helpfulness, responsiveness, quality, accuracy, schedule adherence, budget adherence and scope and fees. Commiltmen'tto Quallity Delivering quality work is a cornerstone of our it Backing the skills, knowledge and experience of our professionals is our robust Quality Assurance/Quality Control (QA/QC) Program. Providing the framework to confirm our project excellence, our QA/QC Program includes check and balances based on lessons learned throughout or more than 11 history and the experience of our employee -owners. We perform risk reviews to identify, assess and develop plans to mitigate risks and create project instructions, which include scope and responsibilities, schedule and budgets and project -specific requirements. We build six - step internal quality reviews into project schedules that involve regular coordination meetings and evaluations by experienced professionals at strategic milestones throughout the design and construction Commiltmen'ttothe Village of �Mouin't Prospect Our mission is "to make our clients successful", and we accomplish this by developing long-term relationships based upon mutual respect, technical competence and responsiveness. Burns & McDonnell is 100% employee -owned, and our clients tell us they see our pride of ownership in our work. Over 90% of our work is repeat business with existing clients, which demonstrates their level of satisfaction with Burns & McDonnell has been successfully providing consulting, design and construction services to the Village for 17 years. Our proposed staff are experienced in working with the Village on similar projects. We keep projects on budget and on schedule while maintaining effective communication. We pride ourselves on being qualified and responsive. We value our partnership and look forward to continuing to serve the Village of Mount N :41 _URNS MISDONNELL' 4D Project approach & methodology. Background Based upon our review of the December 30, 2019 Request for Proposals (RFP), it is Burns & McDonnell's understanding that the Village wishes to engage the services of a professional engineering consultant to provide design and construction engineering services for the 2020 Water Main Improvements Project (project). The Village is still in the process of determining the exact areas that will be included in the project. However, it is known that the project will consist of approximately 6,000 linear feet of water main replacement along typical residential streets. Project Approach Burns & McDonnell 's approach includes - Leveraging our unique knowledge of the Village's water system to meet Village objectives Providing quality design services by implementing best practices gained from projects we have completed for the Village and other clients Delivering a seamless, well -coordinated project by minimizing public impacts during construction After our review of the RFP and our discussions with Village staff, we understand that the existing water main in the project area is a 6 -inch water main which the Village wants to replace with a new 8 -inch zinc - coated class 56 ductile iron water main. For water quality purposes, any new water main being installed in cul-cle-sacs or other dead-end locations should be ® Our team will look at each location and identify suggestions for the Village to improve the flow of water through the water main. The servicesr it ill include the preparation of bid documents, permitting, bid phase services and construction management and inspection for the installation of new water main in both project areas. We intend to do this through proactive project management and coordination with the Village to confirm the Village's objectives can be met, project costs are minimized and an efficient plan to complete the project has been developed. Clear, concNe comimunilcatiloin iis our wayto dell'ilverthe project oin budget and oin schedulle whillle m1lin'iii m1lziii ng limpacts; tothe pUbllilc. This is critical to the public and Village Administration's perception of the project. BURNS N �**, WDONNELL' ,, "1" 40 Our approach includes pro -actively resolving the following key considerations: Resolution of Key Considerations The successful design and construction of the Prgject will present some unique considerations, The following paragraphs identify and discuss key considerations for completing the project as well as how the Burns & McDonnell team intends to manage and resolve these considerations. Knowledge of Village's Water System Burns & McDonnell has recently performed extensive water modeling for the Village's system which identified the need for numerous projects needing to be completed. Our team is currently modeling specific areas and this information will be used to determine the water main replacement areas to be designed under this RFP. In addition to our experience with modeling the Village's system, our design and construction teams have extensive knowledge of the Village's water main requirements and procedures for notification of residents for water main shutdowns and their procedures for testing and disinfection. Project Kickoff Meeting It will be very important to have a detailed project kickoff meeting prior to initiating any project work. The purpose of the kickoff meeting will be to establish lines of communication, review the project scope, document that the Village's objectives have been identified and discuss the critical path to meeting those objectives. Burns & McDonnell will review existing project documents, prepare a formal request for information (RFI) for any missing information, and review permitting requirements prior to the meeting. Schedule The design must be fast -tracked to complete the project during the 2020 construction season®T i ill be extremely important regarding permitting with IEPA so that the start of construction is not delayed. This team can accomplish is® Cost Burns & McDonnell recently supported the Village with development of a Water Main Asset Management Program and Water Rate Study, so we understand that this project is one of many water main projects the Village will be completing in the coming years. iii iis keyto making suire the V11i iiimpl1eimen'ttheir pirogiraimthe way It was linteinded. Simple design decisions can have a drastic effect on cost. We believe the Village should be provided with an opportunity to consider these issues and make data -driven decisions. Our approach will be to discuss feasible options with the Village, then design and bid the project taking Village requirements and preferences into consideration. Alternates can be included in the bid which will allow the Village to evaluate different installation methods and additional scope items; maximizing the cost-effectiveness of the project. For example, we understand that the Village has an existing water main leak on the main that passes under Weller Creek on Emerson Street south of Berkshire Lane. While the Village has been able to isolate the leak without impacting service to residents in this area, they need to get this 300 -feet of existing water main either replaced or rehabilitated so it can be restored to use. This section of water main could potentially be rehabilitated by lining the existing water main. Reviewing the as -built drawings for this main will be critical to determining the feasibility of this N BURNS WDON N ELL' 4P Our design team will evaluate costs early in the project in an effort to see if this additional work can be included in the overall project. Please note that we have not included any costs for the design and construction engineering required for this work. Utility Coordination Utility conflicts can result in significant delays during construction. The Burns & McDonnell team will initiate coordination with the various utility companies immediately upon receiving a Notice to ®T i ination begins with submitting a design -stage JULIE locate followed by contacting each utility company in the vicinity of the project to request copies of their utility atlases. The next step in this coordination is to share Preliminary Plans with each utility so that they can better evaluate the project's impacts upon their facilities. This team has used this approach in numerous communities, including the Village, with great success. Permitting The proposed improvements will require that permits be obtained. We anticipate that permitting coordination will be required with the following regulatory agencies- the Illinois Environmental Protection Agency (IEPA). There may be other permits that will need to be acquired based on the Village's final decision of the areas to be included in the project. One of our tasks will be to immediately evaluate each of the selected areas to verify if any additional permits will be required and notify the Village of our findings. We have excellent relationships with the IEPA and are confident that these relationships will result in timely permit reviews and issuance. Environmental Impact Burns & McDonnell will coordinate with the Village to determine if there are any known or suspected environmental impacts in the project area. We will review available environmental databases that contain records of known or suspected environmental impacts. As a part of our proposal, we will assist the Village with developing a scope of work that the Village can use to obtain proposals from geotechnical engineering firms. This scope of work will include recommendations for pavement cores and soil borings as well as pH testing and additional sampling and testing required per CCDD regulations. This scope will also include direction on completing either an LPC 662 or 663 form based on the results of the testing. IBuirins & McDoininell! �has over 60 einviii iiin our �Dowineirs Grove officethat cain assist ii iif ineeded. Water,, Sanitary Sewer and Natural Gas Services Based on our experience and initial field reconnaissance, the potential exists for existing water, sanitary sewer and/or natural gas services to conflict with the proposed water main. The design will need to consider minimizing the impact to the sanitary sewer services and water services, especially if tts installation methods are used. Sanitary and water service adjustments and details will be incorporated into the project as required. Coordination with the gas company early in the design phase of the project will be completed to make sure that conflicts are identified and managed. Maintenance of Traffic As the anticipated project areas are expected to be typical residential streets, we do not anticipate needing to develop detailed Maintenance of Traffic plans for this project. Based on the locations of the existing and proposed water main, we will include the appropriate IDOT traffic control details in our plans to provide the contractor with direction on how to protect the public and the work zone during construction activities. BURNS S MSDONNELU 4P Construction Staging The project areas will require careful considerations of the construction staging. The primary focus will need to be on maintaining driveway access for all of the residents on a daily basis as well as confirming that sidewalk access is maintained on one side of the road and two legs of each intersection at all times. In addition, special care must be taken to avoid damage to the existing parkway trees. This is extremely important to the Village who takes significant pride in being awarded the Tree City Award for the 34rd consecutive year. As a part of the requirements for this project, we will create a construction staging plan during the design phase to address these concerns. In addition to public meetings, Burns & McDonnell will support the Village by providing up to date information for the Village's website as well as Village issued newsletters. This was done as a part of the Isabella Drainage Improvements project and was very successful at keeping the public informed as to the progress and upcoming schedule of construction Prior to the start of construction on the project, we will require a detailed project schedule from the contractor that includes construction sequencing and identifies when work elements will be initiated and when they are expected to be completed by street and/or geographic locations. Two-week look ahead schedules will be requested to compare construction progress to the initial project schedule and identify work planned in the next two weeks. Based on the schedules provided by the contractor, letters will be prepared and submitted to each resident and business owner to inform them of anticipated construction impacts. These letters will be hand delivered and will include anticipated construction impacts, access limitations and resident engineer and construction manager contact information. This coordination will be vital to the numerous businesses along the project. In addition to the letters, Burns & McDonnell personnel will be highly visible and available at the project sites for interaction with all concerned project stakeholders. If requested, and with authorization from the Village, Burns & McDonnell will schedule a specific meeting time with an affected party to answer questions and mitigate concerns related to the project. Preconstruction Videotaping Preconstruction videotaping should be completed with sufficient time for the Village and the resident engineer to review the video. It is recommended that the contractor and resident engineer both be present during the videotaping to verify the appropriate information is recorded for each project ® Properly documented existing conditions will assist in mitigating potential construction related issues between the contractor, the Village and the public both during and after construction. activities. BURNS N WDONNELL' 0 Scope of services. Desligin Einglineeirling & Blid Rhase SeirVices Task 1: Project Coordination ®1 Iiiclkoff Meetiling Coordinate and conduct a project kickoff meeting to introduce key project team members, review the scope of work, objectives, information and coordination that will be required. ® Piroject Mainageiment Complete project management and administration tasks. 1® Desiin ReVilew Meetiling Conduct one project status meeting with the Village to review the design prior to submitting for permit(s). 1® Cooirdilinate Geotechinilcall linves'ii ga'ii oin Assist the Village with developing a scope of work for the geotechnical investigation and review the report generated by the Village's consultant. ® Publlilc Neilghborhood Meetiling Coordinate and conduct one public meeting for all project ® Meet with Village staff to review the presentation prior to the meeting. Task 2..,w Design ®1 Exilstiling Data Revilew Request and review existing data pertinent to the project. This is anticipated to include as -built drawings provided by the Village, site development plans, sewer televising videos completed by the Village and other information. ® Topogiraphic Survey Assist the Village with developing a scope of work for them to obtain pricing from a surveying it ® Filelld linvestilgatiloin Identify existing conditions. Perform detailed surface investigation of water, storm sewer and sanitary sewer structures. ® Utiflilty Cooirdilinatiloin Contact JULIE and request maps of existing utilities located on and near the project site. Review for potential conflicts and identify mitigation measures. ® Mallinteinaince of'Tiratfilc Identify required IDOT traffic control details for inclusion in the engineering plans. ® Preparation of Coinstiructiloin 1311d Documents Develop project plans consisting of the following- 1) plan and profile drawings of the project areas; 2) water main layout; 3) construction details; 4) construction staging plan. Develop specifications, considering Village procurement requirements, general conditions, bid documents, insurance requirements, performance bonds, etc. Documents will conform to Village, IEPA, IDOT and Standard Specifications for Water & Sewer Main Construction in Illinois requirements as applicable. Effort to make bid documents compliant with third- party financial aid requirements is not included. Submit up to three (3) hard copies for Village review. ® Eing1lineeir's Op'lliniloin of Pirdb6blle Coinstiructioin Cost (EOIPCQ Submit for Village review. ® Quallilty Assuiraince ReView Complete quality review. Task 3: Permitting Support Cooirdlinate wilth Perrin'll't Ageinc1les Prepare and submit the following permit applications. Permit application fees are not included in this proposal. P- IEPA - Water Main Construction Permit. Task 4- Bid Phase Support Pirovilde 1311d Documents Electronic copies of the final issued for bid documents will be made available to prospective bidders in PDF format for a nominal ® Bidders will be able to purchase hard copies of the documents at printing cost. Attend and Cooird'ilinate One (1) Pire-1311d Meet1ing Prepare meeting agenda and meeting notes. Pi Ilidding Asslistaince Review bidder questions and requests for clarification, respond to questions in writing and prepare addenda as BURNS 1% MISDONNELL: 0 necessary. Attend and Cooirdl Iiid Qpein1ing. Bild ReVilew and Recommendation Review and evaluate bids for completeness, develop and review bid tabulation, verify contractor representations, check references and make a written recommendation for contract r® Asseimbile Coins,tiructiloin Contract Docuimeints for execution of the awarded contract. Construction Managemen't & Inspection Task I.- Project Coordination Pireconstiructiloin Conference Coordinate, attend and conduct one Preconstruction conference with representatives of the Village, contractor, utilities and other interested parties affected by the proposed construction. Prepare meeting agenda and meeting notes. Piroject Management Complete project management and administration tasks. Task 2.,w Resident Engineering & Inspection SulbimIt lReVilew Review shop drawings and other equipment/material submittals as may be required by the contract documents. Resildeint Eingilineeiriling Provide a resident engineer/ inspector (RE/1) for observation of the work during the construction period to observe and record construction progress under the general guidance of the engineer. For the purposes of this proposal, Burns & McDonnell is assuming that the selected contractor will construct all of the underground utility work on one project area prior to commencing construction on the other project area. Based on this assumption, we will provide a part- time resident engineer with a part-time construction inspector to cover the concrete and asphalt work on one project area while underground work is being started on the next. Should the selected contractor choose to staff the project with multiple crews and work in both project areas simultaneously, we will evaluate the schedule and the subsequent impacts on our budget and let the Village know immediately if there will be any issues. Based on on- site observation, the engineer will keep the Owner informed of the progress of the work, shall endeavor to guard the Owner against defects and deficiencies in the work of the contractors and may disapprove or reject work as failing to conform to the contract documents. Other tasks include- • Prepare written inspection reports. Reports are to be delivered to Owner in an electronic format. Digital photographs documenting work tasks in progress as well as any potential problems or unusual conditions shall also be included with each report. • Coordinate material testing services with the consultant under contract to the Village for their roadway program. Assist the Owner in preparation of any necessary change order and/or field directives. Process monthly applications for payment submitted by the contractor, and forward to Owner with recommendations for approval and payment. Assist the Owner with the resolution of inquiries, complaints or concerns raised by residents or the public. Task 3: Project Closeout Punch List Perform a field observation of all compI eted work before a final application for payment is processed for the contractor. Coinfoirimiiingto Construction Documents Revise the original plans in accordance with construction observation records of the resident engineer, inspectors and the contractor, and supply the Owner with one set of as -built drawings in a suitable electronic format. BURNS N MSDONNELL: 0 Project team. Every member of Burns & McDonnell's project team has extensive experience designing and constructing water main throughout northeastern Illinois for municipalities and private sector clients. Every member of our project team has experience working on projects similar to the Water Main Improvements Design and Inspection project (project) for the Village of Mount Prospect (Village). Our team offers the following values: Employee -owners willing to go the extra it An enthusiastic and innovative spirit Proven track record with the Village Proven record of serving as problem solvers rather than propagators 100% Commitment to the success of the Village BURNS N MSDONNELL: 0 Based on the locations that we were asked to model, we have reviewed available information and have a strong understanding of the project requirements. Some of our experience working on the Village's water system includes, Randy was involved in developing the Village's 2008 Water System Master Plan and water distribution system hydraulic I® The Master Plan specifically noted some of the water main slated for replacement as part of this project had experienced considerable main breaks. Randy supported the Village by developing the 2076 Water Main Asset Peplacement Program. That study proposed an annual replacement program and identified the water main on Prospect Avenue from Maple Street to School Street as a Priority 4 rating - the second highest rating indicating a need for replacement. Randy was part of our team that supported the Village by developing the 2077 Water and Sewer Pate ® That is proposed utility rates to adequately and equitably recover costs fort e Village's water and sewer utilities. Since the 2008 Water System Master Plan was completed, lill1lage's water systeim usiiingthe hydiraulliic modellfoir appiroxi'matelly 10 aireasthiroughout,the Villllage. Evaluations have included assessing available fire flow, pressure requirements, booster pump station operating scenarios, water supply alternatives and options for providing water service to areas the Village has considered for annexation. rt has experience in the detailed design and construction of water main for the Village, most recently on the 2075 Maple and Evergreen Water Main Improvements project. Team Strength An organizational chart depicting key members of our project team follows this introduction, along with detailed resumes of our team members. The following paragraphs provide a brief description of our project team. Project Manager Randy Patchett, PI ill serve as the project manager for this project. Randy has 35 years of experience managing municipal projects. Randy is well versed in the design of water main and underground utilities. He will be responsible for project coordination, project scheduling, budget maintenance, project design, overall performance and most importantly, client satisfaction. Randy has experience in completing multiple projects for the Village including projects similar to the Water Main Construction Design and Inspection project. Design Steve Crede will serve as the assistant project manager on the project and as the lead designer. Steve will work directly under Randy and coordinate daily design activities. He has extensive experience with the Village and a strong understanding of Village requirements. Steve will be supported by project engineer Caleb ApIker. Steve Crede will serve as our construction manager. Inthis role he will represent the Village by coordinating with the contractor including attending progress meetings. He will coordinate closely with Matt Dunlop to make sure the project is constructed smoothly. He has over 20 years of experience in designing and constructing municipal water main projects. Steve has a proven track record providing construction services to the Village. Steve's experience with the Village includes the 2013 Stormwater Improvements project, the 2015 Isabella Drainage Improvements project, the 2015 Map/e& Evergreen Water Main Improvements project and the standby generator installations at Booster Pump Stations 11 and 17. Matt Dunlop will serve as our resident engineer. Matt has 5 years of experience inspecting municipal water main projects, as well as construction experience with the village. Matt was an inspector for the 2015 Isabella Drainage Improvements project. Caleb ApIker will also serve as our part-time construction inspector. His role will be to be on-site during the placing of concrete and hot -mix asphalt on the first project area while underground work is commencing on the next project area. An organizational chart and detailed resumes of Burns & McDonnell personnel follow this page. BURNSX �**, ,,M!;DONNELL' 4, 0 Steve Crede Lead Water Main Design Steve Crede Construction Manager Caleb A p ke r Water Main Design Matt Dunlop Resident Engineer Caleb Apker Construction Inspector ®i S BURNS �&MMON N ELL' 0 o� BS, Civil Engineering Regil'strations o, Professional Engineer (IL) 34 Randy Patchett E years of Project Manager experience Randy Patchett manages the water and municipal services practice for Burns & McDonnell's Chicago regional office. He is a senior civil engineer with extensive experience providing consulting engineering services on civil, environmental and hazardous waste projects to municipal, industrial, state and federal clients. Randy's responsibilities include developing and managing projects involving a wide range of services in the areas of water, wastewater, stor and flood management, hazardous/mixed waste management and general civil works. His experience includes performing investigations, feasibility studies, computer modeling, global information system projects, master planning, design and construction management. Maple & Everqree�n Wate�r Mal[n Improvements I V1111age of Mount Prospect Mount Prospect, Illinol"s 011ilein't imainageir. Design of new water transmission mains improving the Village's ability to fill and drain their elevated tank. The project included installation of approximately 250 linear feet of 24 -inch diameter transmission main, 670 linear feet of 18 -inch diameter transmission main and 160 linear feet of 16 -inch diameter transmission main. Responsibilities included design of the water transmission main, coordination with various utility companies, oversight of drafting and engineering staff and production of construction bid documents. Eagle Hellghts North Street Rdhablilllltatlo�n & Water Mal'[n I City of Elgl'un Elgin, Iffinol"s PiroJect imainageir. The complete replacement of approximately 13,500 linear feet of 8 -inch water main and water services in the Eagle Heights North Subdivision in the City of Elgin. The project included the replacement of all existing curb and gutter, sidewalks and driveway aprons as well as storm and sanitary sewer and the milling and resurfacing of approximately 2.5 miles of City streets. Managed in the project design, structure inspections, sewer televising, and coordination with the City, contractor, various utility companies and local residents and businesses. BURNS 4,MSDON N ELL' Randy Patchett E Project Manager Park StI 'I'I'I'I"ta,t'I'I'oIn & WateIr Mal[n J ClIty of Elgl[n Elgin, Illinoi's IN �Piro I Ject i® The complete replacement of approximately 3,200 linear feet of 8- and 6 -inch diameter water main and water services on Riverside Drive, College Street and Gifford Street. The project included the replacement of all existing curb and gutter, sidewalks and driveway aprons, concrete patching, installation of new storm sewer and milling and resurfacing of Park Street, College Street, Franklin Boulevard, Addison Street and Gifford Street. Managed coordination with the City, contractor, various utility companies, local residents and businesses, schools and s® Blackhawk Urlive Remnstructim & WlldeKl[ng J V11,11age of Westmont Westmont, Illinoi's IN �Piro I Ject dilirectoir. The reconstruction and widening of approximately 2,500 feet of Blackhawk Drive in the Village of Westmont from Chicago Avenue to Ogden Avenue. The project included the installation of 12 - inch diameter PVC water mains and water services, adjusting sanitary services, installation of a new storm sewer main line with new catch basins and inlets, installation of new sidewalk and installation of new street lighting. Role included management of staff performing design and on-site construction inspection as well as project coordination with the Village, Illinois Department of Transportation (IDOT), the contractor, various utility companies and local residents and businesses. 2015 Water Mallin Relplaceirneint J City of Eiglun Elgin. Illinoi's Piroject i® Replacement of approximately 3,000 feet of water main on Elm Street, Standish Street, Woodard Street and Hope Court. The existing water main had to be replaced in advance of another City project which was going to be separating the existing combined sewer. There were many locations where the new water main was lowered in preparation for the sewer separation project. The project required coordination with the City, various utility companies, local residents, ® Edwards High School, Metra and PACE. In addition, there was coordination with other City r® BURNS X MSDONNELL 0 o� BS, Civil Engineering Regil'strations o, OSHA 10 -HR Construction o, IDOT Documentation of Caleb Apker 04 Water Main Design/Construction years of Inspector (Part -Time) experience Caleb Apker focuses on water, wastewater and stormwater projects within the field of engineering. As a project engineer, he has played significant roles in numerous projects in his time with Burns & McDonnell. These projects include water main design, infrastructure studies, site development, stormwater and sanitary system assessment and design and construction management. His experiences have given him valuable knowledge in key aspects of his field. 2017 Water MaIlin Re�p!aceimeint J Oity of Elg'1111 Mount Prospect Is 1. Contract Quantities Certified Piroject eing1lineeir. The design and construction of approximately 3,500 NASSCO PACP/LACP & MACP linear feet of new water main ranging in size from 8- to 12 -inches in Certified diameter to replace existing 6 -inch -diameter water main. The project also included new valves, it hydrants and new services to private property and connections to existing water main. Responsibilities included preparation of plans and specifications for bid and permitting. WateIr MaihIt RrogIram J V11111age of Mount Piros�pect Mount Prospect, Illinoi's Piro`ect eing1lineeir. An assessment of the Village's water main system in order to develop an asset replacement strategy for the water distribution system. A program was developed to indicate quantity, cost and location of annual water replacement segments. The program was designed to be updated and evaluated on an annual basis and become a guide for decisions for annual replacement of water mains. Responsibilities included analyzing the water main system based on the selected criteria, creation of the water main replacement program and preparation of a report outlining the program and project findings. West Piressuire Zone �- 11-11111ghland Woods I Iins Im Issii o in Maiiin J Cilty of Elgiihn Elgin, Illinoi's PiroJect eing1lineeir for the installation of over 5,500 linear feet of 24 - inch water main, over 300 feet of which was installed via jack and bore method beneath an existing railroad. The project included storm sewer removal and replacement as well as bike path removal and replacement. Responsibilities included preparation of bid package, CAD drafting, traffic control design and permitting assistance. BURNS IKMSDON N ELL' 4D Caleb Apker Water Main Design/Construction Inspector (Part -Time) Saini'tairy Sewer Rep!aceI irthuir/Rratt 1311vd J E111k Grove V111111age Elk Grove Village, Illinoi's �Piro I Ject eing1ineeir and res'lldent eingilineeir for replacement of 600 feet of 8 -inch and 10 -inch sanitary sewer. The project location required the use of trs technology; pipe bursting and jack and bore. The pipe location required crossing beneath a stream and a railroad. The project was located near heavily -trafficked industrial sites and required a lot of coordination with property owners. Responsibilities included bid document preparation, permit coordination, communicating with property owners regarding construction activities, and inspection and documentation of the contractor's work. Statil'on SN Ground Storage"Tank Re1h6bil'1111tatIon J Vil'1111age of Mount Prospect Mount Prospect, Illinoi's IN �Piro I Ject eing1ineeir and resident engineer for rehabilitation of a I -MG ground storage tank in the Village of Mount Prospect. Project included blasting and rng the interior and spot -blasting and over -coating the exterior. As interior blasting occurred, it became evident that the condition of the steel rafters was worse than previous inspections indicated, so the scope of the project was altered to replace the steel in the worst condition. This additional work was completed without significantly affecting the overall project cost. Responsibilities included reviewing submittals and shop drawings, observing the work for conformance with the contract construction documents, reviewing progress and final pay requests prepared by the contractor, reviewing change orders, notifying the Village of items not in conformance and providing photo documentation of the project. TirainsimIssiioin Mail'in linstaIIIIat'i'loin I Newport Oheirniic De�pot �Reuse Authoril'Ity (NeODIRA) Vermillion County, Indiana 1 IN �Piro I Ject eing1lineeir. The design of a new water transmission main that will serve the Vermillion Rise Mega Park in rural Indiana. The project includes the installation of approximately 12,150 linear feet of new 24- inch diameter ductile iron transmission main. Responsibilities included Civil Engineering Regil'strations OSHA 10 -HR Construction OSHA 30 -HR Construction OSHA 40 -HR HAZWOPER Designated Erosion Control Inspector IDOT Documentation of Contract Quantities Certified Fermil-ab Electrical Safety o, Fermil-ab Radioactive Safety zo Steve Crede years of Design Lead/Construction Manager experience Steve Crecle serves Burns & McDonnell as a project manager and manages construction management services. He focuses on water, wastewater, stormwater and transportation projects for municipal clients. Steve has served as a construction manager and resident engineer on numerous projects providing construction inspection, layout and project oversight. In addition, he has extensive experience in water main, storm sewer and sanitary sewer design for land development and public works projects, using AutoCAD software. Maple & Evergree�n Wate�r Malihn llmprovemeIms J V1111age of Momt Prospect Mount Prospect Is Constiruction imainageir. Replacement of approximately 2,000 feet of water main on Maple Street and Evergreen Street ranging in size from 6 - to 24 -inch ductile it pipe. The existing water main had to be replaced to correct water pressure issues in the Village. This was determined from a water system study previously performed by Burns & McDonnell. As a part of the new water main installation, the Plans had a new connection to the Village's I -MG elevated tower is required concrete pipe supports, heat trace and pipe insulation as the connection point was approximately 4 feet above grade. The project required coordination with the Village, various utility companies, local residents and businesses, other Village construction projects and the Police and Fire Departments which shared a public safety building on the project and had to have access /® Isabella CombIlined Rellief Sewer J V1111age of Mouint Prospect Mount Prospect, Illinois Resident engineer for construction of approximately 17,400 feet of combined sewer in the Isabella Street area via installation of a relief sewer ranging in size from 12- to 96 -inches. Project included replacement of portions of existing curb and gutter, sidewalks and driveway aprons, as well as sanitary sewer repairs, water main lowering and the milling and resurfacing of approximately 3 miles of Village streets. Permits were obtained from IEPA, IDOT, MWRD, IDNR and IHPA. Project required coordination with the Village, various utility companies and local residents and businesses. BURNS WDONNELL' 4D Steve Crede Design Lead/Construction Manager 2015 Water M4'lin Relplaceimeim J O'lly of ElqI'iin Elgin, Illinois Construction imainageir. Replacement of approximately 3,000 feet of water main on Elm Street, Standish Street, Woodard Street and Hope ® The existing water main had to be replaced in advance of another it project which was going to be separating the existing combined sewer. There were many locations where the new water main was lowered in preparation for the sewer separation project. The project required coordination with the City, various utility companies, local residents, St. Edwards High School, Metra and PACE. In addition, there was coordination with other City contracts. Eagle HeIghts Noirth Stireet Rehabli'll'tatibin & Wateir Maiiin J Clfty of Elglm Elgin, Illinois Resilden't ® The complete replacement of approximately 13,500 linear feet of 8 -inch water main and water services in the Eagle Heights North Subdivision. The project included the replacement of all existing curb and gutter, sidewalks and driveway aprons as well as the replacement of some storm and sanitary sewer and the milling and resurfacing of approximately 2.5 miles of City streets. The project required coordination with the City, contractor, various utility companies and local residents and businesses. Pairk StiI'I''1'1"ta,t'I'I'oin & Water Mall'in J Cilly of Elgliin Elgin, Illinois Resilden't III® The complete replacement of approximately 3,200 linear feet of 8- and 6 -inch diameter water main and water services on Riverside Drive, College Street and Gifford Street. The project included the replacement of all existing curb and gutter, sidewalks and driveway aprons, concrete patching, installation of new storm sewer and milling and resurfacing of Park Street, College Street, Franklin Boulevard, Addison Street and Gifford Street. The project included coordination with the City, contractor, various utility companies, local residents and businesses, schools and museums. BURNS &MSDON N ELL' 10 o� BS, Civil Engineering Matt Dunlop Resident Engineer, 05 years of IV experience Matt Dunlop has experience in both design and construction of water - related projects. His educational background provided him with the knowledge needed for the design of a variety of project types including collection, treatment and transmission and distribution. Matt has construction experience with projects involving the installation of water BA, Engineering Physics main, storm sewer, sanitary sewer and force main systems. During his construction experience, he has successfully resolved conflicts that I�t io in s were discovered in the field. Matt also holds the interpersonal skills Engineer -in -Training required to communicate and coordinate effectively with the contractor, IDOT Documentation residents and the Owner. He has the IDOT Documentation Certification Certification of Contract necessary to work as an inspector for IDOT projects. Quantities OSHA 10 -HR Construction West Piressuire Zane Coininectiivilty - H11gh1and Woods Transmil'st'lan MM[n I CilIty of Elgiihn Elgi"n, lifinol"s Field engineer for the installation of 5,700 linear ft. of 24 -inch diameter ductile it water transmission main along Coombs Road and U.S. Route 20. This project was the second of two phases to increase water flow and water quality for the southwest area of the City's West Pressure Zone. Both phases were required to fill gaps in the City's water transmission mains that resulted from developments that did not move forward. The project included utilizing jack and bore installation for crossings of Coombs Road and U.S. Route 20. The project also included replacement of existing driveway culverts, driveway aprons, and bike path pavement. Permits had to be obtained from the IEPA, IDNR, IHPA, and Kane County. Responsibilities included inspection and documentation of the contractor's work. The project required coordination with the City, various utility companies, and local residents and businesses. 2017 Water Mailhn Re�p!acement I 011ty of Elgilh Elgin, 11finol"s I Project engineer for a water main replacement project including approximately 2,400 linear ft. of new 8 -inch water main and pavement patching. This project required coordination with the City, local businesses, and various utility companies. Responsibilities included permitting support, preparation of the design plans, specifications, bid documents, and cost estimate. BURNS `MSDON N ELL' Matt Dunlop Resident Engineer 2015 Wate�r Mailhn Improvements J V1111age of Mount Pros�pect Mount Prospect Is ,, Iffin o" Project engineer for a water main replacement project including approximately 1,350 linear ft. of new water main ranging in size from 24 -inch as well as a connection to an existing elevated tank. This project required coordination with the Village, local businesses, and various utility companies. Responsibilities included permitting support, preparation of the design plans, specifications, bid documents, and cost estimate. West Pressure Zane Comnect'11411ty - �Bowes �Road Transmil'ssil'an Maiihn J 01ty of Elgiihn Elgin, Illinoi's Field engineer for the installation of 5,600 linear ft. of 20 -inch diameter ductile it water transmission main along Nesler Road. This project was the first of two phases to increase water flow and water quality for the southwest area of the City's West Pressure Zone. Both phases were required to fill gaps in the City's water transmission mains that resulted from developments that did not move forward. The project included utilizing jack and bore installation for crossings of Nesler Road, Canadian National Railroad, and Fitchie Creek. The project also included replacement of existing driveway culverts, driveway aprons, and bike path pavement. Permits had to be obtained from the IEPA, IDNR, IHPA, Kane County, Plato Township, and Canadian National Railroad. Responsibilities included inspection and documentation of the contractor's work. Isabe1h DraImage Improvements J V1111age of Mount Pros�pect Mount Prospect, Illinois / 2015 Field engineer for the separation of approximately 15,000 ft. of combined sewer in the Isabella Street area via the installation of a relief sewer ranging in size from 12- to 96 -inch. In addition, the project also included catch basins, manholes, lowering water main, reconstructing MWRD junction chambers, and site restoration. While utilizing normal open cut method, the new relief sewer was installed across two state highways. The existing combined main on Isabella Street was removed and replaced while maintaining the flow with bypass pumping. Responsibilities included providing inspection and documentation of the contractor's work. BURNS &MSDON N ELL' ID Village of Mount Prospect lMount lProspect, II1- Burns & McDonnell completed the Water System Master Plan for the Village of Mount Prospect in ® As a result of water modeling performed as part of that study, Burns & McDonnell identified multiple areas in the Village where there were water quality and water service issues. These areas were then worked into the Village's S -year capital improvement program. The latest project to come out of this effort is the Maple & Evergreen Water Main Improvements. The project consisted of the design and construction of approximately 2,500 linear feet of new water main ranging in size from 4- to 24 -inches in diameter. In addition, the project included a new connection to the elevated tank on Evergreen Avenue. The tank had previously been filled with an existing 6 -inch water main. The elevated tank now has a 24 -inch service connection. The connection to the elevated tank includes a 24 -inch butterfly valve in a valve vault, a 20 -foot deep 7 -foot diameter vault, 24 -inch flanged piping and a pressure transmitter in a vault. The project also included the removal and replacement of portions of the curb and gutter, sidewalk and driveway aprons as well as pavement patching on multiple streets. Coordination with the local residents and businesses, the Illinois Department of Transportation (IDOT), the Northwest Suburban Municipal Joint Action Water Agency (NSMJAWA) and the Village was required. Project scope and deliverables included the final plans, specifications, cost estimates, permitting, utility conflict resolution, soil testing and analysis, Clean Construction Demolition Debris certification and bidding assistance. Burns & McDonnell provided the construction services. .pURNS MONNELU Mh &M 4D Project Statistics Client Name I Village of Mount Prospect Construction Cost I $1m5M E Project Reference Sean Dorsey, Director of Public Works 1700 W. Central Road Mount Prospect, Illinois 60056 847-870-5640 SDorsey@mountprospect.org Project Team Client Manager: Randy Patchett Project Manager/Lead Engineer: Joe Darlington Construction Manager: Steve Crede Village of Mount Prospect lMount lProspect, IIL Burns & McDonnell provided design and construction services to the Village of Mount Prospect for the Isabella Combined Relief Sewer. In July 2011, the Village was devastated by a 500 - year storm event that resulted in wide spread flooding throughout the Village as well as significant property damage. Burns & McDonnell was hired to conduct a comprehensive study encompassing the entire Village to assess local flooding and combined sewer problems. This project addresses one portion of the Village's flooding issues. This is a combined relief sewer improvements project requiring over 17,000 linear feet of sewer ranging in size from 12- to 84 -inches in diameter. These improvements will improve the capacity of the system from less than a 2 -year level of service to a 25 -year level of service. In addition to sewer improvements, approximately 15,000 linear feet of asphalt roadway, curb and gutter, driveway aprons and sidewalk was removed and replaced. Due to the size and depth of the new sewer, there were numerous locations where the existing water main had to be relocated which required an IEPA permit. Project limits intersected with Illinois Route 83 and US Route 12, requiring coordination with the Illinois Department of Transportation (IDOT) and highway Project Statistics Client Name I Village of Mount Prospect Construction Cost I $1m5M Project Team Project Manager: Randy Patchett Resident Engineer: Steve Crede Lead Design Engineer: Joe Darlington Construction Inspector: Matt Dunlop Claus Dunkelberg: QA/QC Services Provided Design Phase Services Construction Phase Services Design & Post Construction Sewer Modeling Permitting Survey Bidding Services Public Relations Material Testing CCDD Coordination permits. In both cases, permits were obtained to open cut ® 83 and Rte. 45 which required significant staged traffic control. BURNS MISDONNELL: 4D In addition, significant coordination with IDOT was required as Rte. 45 was milled and resurfaced at the same time as the construction of the Isabella Project and IDOT also performed a miscellaneous pavement patching project on Rte. 83 at the same time as the Isabella Project. The coordination allowed all three projects to proceed seamlessly. The sewer system conveys combined runoff through two Metropolitan Water Reclamation District of Greater Chicago (MWRDGC) junction chambers. The dry weather flow discharges in the first junction chamber at the intersection of Isabella Street and US Route 45 into an MWRD interceptor. During wet weather flows, there is a weir wall in the first junction chamber that when it overflows, discharges to a collecting structure for MWRDGC Drop Shaft No. 3, requiring a Watershed Management Ordinance permit. Construction was performed in an area that was mixed residential and commercial/business. The project had impacts to existing restaurants, a bank, automotive maintenance businesses, a home improvement store, and a business condo complex. Coordination with residents and commercial property owners was a top priority throughout the design phase and continued throughout the construction phase. Burns & McDonnell met on- site during design with each resident that reported impacts with the flooding in 11® Multiple public meetings were held during the design of the project to keep residents informed. During construction, Burns & McDonnell assisted the Village with maintaining a project website and submitting monthly newsletters to all property owners in the Isabella Drainage Basin. In addition, there was a weekly email blast that was sent to anyone in the Village that signed up for this update. Project design scope and deliverables included the final plans, specifications, cost estimates, permitting, utility conflict resolution, soil testing and analysis, Clean Construction Demolition Debris certification (CCDD) and bidding assistance. Burns & McDonnell provided construction management services to the Village for this project. Construction phase services included full-time resident engineering consisting of acting as the liaison between the Village and the contractor, coordination with residents and production schedules, observing work for compliance with the contract documents, review of materials testing reports and shop drawings, maintaining a daily field book that documents number of crews, equipment and individuals on-site and daily quantities of work completed. Services also included review, recommendation and processing of pay requests and change orders. BURNS N �**, WDONNELL' ,, "I" 4D DRAINAGE IMPROVEMENTS imm HAITLEN, LAWRENCE & LOUNQUIS W: Village of Mount Prospect � Mount Prospect, 11- 1 Burns cDonnell provided design and construction services to the Village of Mount Prospect for the 2013 Drainage Improvements project, located in the Hatlen Avenue, Lonnquist Avenue and Lawrence Lane neighborhoods. In 2011, Burns & McDonnell conducted a comprehensive study encompassing the entire Village to assess local flooding and combined sewer problems®T i ject addressed one portion of the Village's flooding issues. This project consisted of the design and construction of approximately 5,700 linear feet of storm sewer ranging in size from 12- to 54 -inches and in three separate neighborhoods. Existing storm sewers were either removed or abandoned and replaced with new sewers capable of conveying the 25 -year rainfall event. Several street inlets were removed and replaced to help reduce surface flooding. A 300 - foot, 12 -inch sanitary sewer was also replaced due to poor existing condition. In addition to sewer improvements, approximately 4,700 linear feet of asphalt roadway, curb and gutter, driveway aprons and sidewalk were removed and replaced. Sewer improvements were also located in multiple resident sideyards where easements were necessary. Coordination with local residents was a top priority for the duration of this project. Project design scope and deliverables included the final plans, specifications, cost estimates, permitting, utility conflict resolution, Clean Construction Demolition Debris (CCDD) certification and bidding assistance. Burns & McDonnell also provided construction management services through final .pURNS MISDONNELU Mh 4D Project Statistics Client Name I Village of Mount Prospect Project Reference Sean Dorsey, Director of Public Works 1700 W. Central Road Mount Prospect, Illinois 60056 847-870-5640 SDorsey@)mountprospect.org Project Team Project Manager: Randy Patchett Construction Manager: Steve Crede Lead Design Engineer: Joe Darlington Survey Services Design Services Permitting Bidding Services Construction Phase Services Material Testing UZI, City of Chiicago, IL Burns & McDonnell has a Master Consulting Agreement (MCA) with the City of Chicago's Department of Water Management (CDWM) to provide construction engineering services. As a part of the MCA, Burns & McDonnell was contracted to provide a resident engineer and a construction inspector to oversee the replacement of existing water main by City of Chicago in-house crews. On a yearly basis, CDWM uses in-house crews to replace existing water main throughout the City. As a part of this program, the City has broken the entire water main system into grids and focuses on replacing the mains in specific grids annually. The City uses State Revolving Funds to cover the costs of this program. Burns & McDonnell was responsible coordinating with the City foreman, administration of the City crews, technical aspects of construction and quality of ® Our resident engineer was responsible for the oversight of 2-4 City crews at any point in Project Statistics Client Name I City of Chicago Construction Cost I $1M Project Team Construction Manager: Steve Crede Construction Inspection time. As the resident engineer for this program, and grade for water main installation, coordination Burns & McDonnell was responsible for reviewing with residents, business owners, schools and the plans and specifications, ordering of all water hospitals for shut downs, sending daily and main materials, obtaining all required permits, semi-monthly reports to the City, maintaining all coordination with utilities and local police and fire project documentation, providing Conforming to departments, reviewing traffic control, providing line Construction Drawings and project closeout. BURNS ,,MMONNELL' M//ffA'ffff1 MUSIGH/1 W0001m; MZ1191AINVAI �Mmff C �i -t y o f IE I g ii in I g ii in, I �L Burns & McDonnell provided design services to the City of Elgin fort 2014 Neighborhood Street Rehabilitation, Combined Sewer Separation and Water Main. The design services an in January 2013®T is total project encompassed 25 streets within the City of Elgin's Lord Street Basin. Due to the size of the overall project, the City chose to break the actual construction into phases that could be more easily managed. The 8th phase of construction was the 2018 Neighborhood Street Rehabilitation - Woodard/Standish. The project consisted of the design and construction of approximately 3,000 linear feet of 8- and 12 - inch water main with 22 gate valves in vaults 10 fire hydrants to replace existing 4- and 6 -inch water main to improve water quality and water flow as well as provide better coverage for it protection. The project also included 2,300 linear feet of new storm sewer ranging in size from 12- to 24 -inches in diameter. The proposed storm sewer was to remove all wet weather flows from the existing combined sewer to alleviate issues with basements flooding during large storm events. In addition to the new storm sewer, Burns & McDonnell had all of the existing combined sewer televised during the design of the overall rjc® A portion of the existing combined sewer along Locust Street and West Chicago Street was found to be in need of repair. Based on the condition of the sewer pipe, it was determined that 2,100 linear feet could be repaired using cured -in-place pipe (C I P }® The project also included the removal and replacement of the curb and gutter, sidewalk and driveway aprons as well as the reconstruction of 0.75 miles of roadway on Standish Street, Holly Street, .pURNS WDONNELU Mh 4D Project Statistics Client Name I City of Elgin Construction Cost 1 $4,000,000 Project Team Project Manager: Randy Patchett Design Lead: Joe Darlington Construction Manager: Steve Crede Project Engineer: Caleb Apker mul "IMUZON, R1111MIMP 'V!0111'6 Design Services Construction Phase Services Permitting Material Testing Survey Services CCDD Coordination Gertrude Street and Jewett Street. Coordination with the local residents and businesses, St. Laurence Catholic Church and School, PACE and the City was required. Project scope and deliverables included the final plans, specifications, cost estimates, permitting, utility conflict resolution, soil testing and analysis, Clean Construction Demolition Debris certification and bidding assistance. Construction is set to being in March 2018 and is scheduled to be completed in October 2018. Burns & McDonnell is providing the construction engineering services. I BURNS,*�*,,,MSDON N ELL' City of Elgin Elgin, II1- Burns & McDonnell provided design and construction phase services to the City of Elgin for the Standish/Elm Neighborhood Street Rehabilitation, Combined Sewer Separation and Water Main. Design services began in January 2013. This total project encompassed 25 streets within the City of Elgin's Lord Street Sewer Basin. Due to the size of the overall project, the City chose to break the project design and construction into phases that could be more easily managed. Part of the fifth phase of construction was the 2017 Water Main Replacement. The project consisted of the design and construction of approximately 3,500 linear feet of new water main ranging in size from 8- to 12 -inches in diameter to replace existing 6 -inch -diameter water main. The project also included new valves, fire hydrants and new services to private property and connections to existing water main. The proposed water main in this project being done for two purposes: 1) to improve water quality and service in the subdivision; and 2) to eliminate conflicts between the existing water main and the future storm sewer as a part of future combined sewer separation phases. Project scope and deliverables included the final plans, specifications, cost estimates, permitting, utility conflict resolution, soil testing and analysis, Clean Construction Demolition Debris certification and bidding assistance. Burns & McDonnell provided construction engineering services. m-hURNS �**,,,MSDONNELU Project Statistics Client Name I City of Elgin Construction Cost 1 $800,000 Project Team Project Manager: Randy Patchett Design Lead: Joe Darlington Design Engineer: Caleb Apker Construction Manager: Steve Crede City of Elgin lElgin, II1- Burns & McDonnell provided design and construction phase services to the City of Elgin for the 2014 Neighborhood Street Rehabilitation, Combined Sewer Separation and Water Main. The design services began in January 2013. This total project encompassed 25 streets within the City of Elgin's Lord Street Basin. Due to the size of the overall project, the City chose to break the actual construction into phases that could be more easily ® The third phase of construction was the 2015 Water Main Replacement project. The project consisted of the design and construction of approximately 3,000 linear feet of new water main ranging in size from 6- to 12 -inches in diameter with approximately 150 linear feet of casing pipe ranging in size from 10- to 18 -inches. The proposed water main in this project was being installed for two To improve water quality and service in the subdivision To eliminate conflicts between the existing water main and the future storm sewer as a part of future combI ned sewer separation phases This contract had to have all of the new water main installed, tested, chlorinated and services connected no later than May 29, 2015. This was to verify that all of this water main work would be completed in advance of the 2015 Neighborhood Street Rehabilitation - Elm Street, which was scheduled for construction in 2015. In addition to the tight deadline for completion, this work also had to be closely coordinated with St. Edwards High School as school will still be in session while much of this work is being performed and vehicular and pedestrian traffic must be maintained. m-hURNS DONNELU Project Statistics Client Name I City of Elgin Construction Cost I $1M Project Team Project Manager: Randy Patchett Design Lead: Joe Darlington Construction Manager: Steve Crede The project also included the removal and replacement of portions of the curb and gutter, sidewalk and driveway aprons as well as pavement patching on multiple streets. Coordination with the local residents, schools, PACE and the City was required. Project scope and deliverables included the final plans, specifications, cost estimates, permitting, utility conflict resolution, soil testing and analysis, Clean Construction Demolition Debris certification and bidding assistance. Burns & McDonnell provided the construction engineering services. I BURNS,*�*,,,MSDON N ELL' C ii -t y o f IE I g ii in I g ii in, I IL The City of Elgin's West Zone Connectivity project provided capacity, looping redundancy, water quality and general operational improvements throughout the City's West Pressure Zone. Two connections were made as part of the project: the Bowes Road Transmission Main (south) and the Highland Woods Transmission Main (north). The Bowes Road Transmission Main was the most critical component to provide needed improvements to allow housing developments in the area to continue. The Bowes Road Transmission Main project consisted of approximately 5,900 feet of 20 -inch diameter water transmission main. Approximately 330 feet of 36 -inch diameter steel casing pipe installed by je was required for crossings of the Canadian National Railroad and Fitchie Creek. The Highland Woods Transmission Main consisted of approximately 5,800 feet of 24 -inch diameter water transmission main. Approximately 345 feet of 42 - inch diameter steel casing pipe installed by jack -and - bore was required for crossings of Coombs Road and US Route 20. Burns & McDonnell first completed topographic survey of the entire project area, prepared construction bid documents including plans and specifications, and developed several engineer's opinions of probable costs for the City. Burns & McDonnell also provided assistance in obtaining the following permits: Elgin Township Approval; Illinois Department of Natural Resources (IDNR) - EcoCAT Review; Illinois Department of Transportation (IDOT) - Utility Crossing Permit - Illinois Environmental Protection Agency (IEPA) - Water Main Construction Permit- Kane County - Utility Permit; Kane-Dupage Soil & Water Conservation District - Soil Erosion & Sediment Control Plan; and Plato Township Approval. .pURNS M51111130NNELU Mh 4D Project Statistics Client Name I City of Elgin Construction Cost 1 $4,000,000 Project Reference Eric Weiss, Sr. Engineer - Utilities 150 Dexter Court Elgin, IL 60120 847-931-6159 weiss—e@cityofelgin.org Project Team Project Manager: Randy Patchett Staff Engineer: Joe Darlington Construction Manager: Steve Crede Topographic Survey Design Services Permitting Property Appraisal Easement Acquisition Bid Phase Services Resident Engineering The project required obtaining a license agreement from Canadian National Railroad. Permanent and temporary easement agreements from several affected property owners were acquired. Bid phase services were provided. Burns & McDonnell provided resident engineering services during construction, which included Clean Construction Demolition Debris (CCDD) certification, full-time construction inspection, and processing contractor's request for information (RFIs), pay requests and change order requests. Construction of the Bowes Road Transmission Main was completed in 2016. Construction of the Highland Woods Transmission Main was completed in 2017. I BURNS,*�*,,,MSDON N ELL' , li-M TOT sBURNS Village of Mt. Prospect MDNNLL Water Main Replacement Design and Inspection Activity Name Qriginal Start Finish,'2020 Duration Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec , Design Consultant Contract Award 0 04 -Feb -20 Notice to Proceed 0 10 -Feb -20 O Kick-off Meeting 1 12 -Feb -20 12 -Feb -20 Prepare and Submit Preliminary Plans to Village 23 13 -Feb -20 16 -Mar -20 Site Visit/Structure Inspections 4 13 -Feb -20 18 -Feb -20 11 Prepare and Submit Preliminary Construction Cost Estimate 7 06 -Mar -20 16 -Mar -20 Prepare and Submit IEPA and MWRDGC Permit Applications 1 16 -Mar -20 16 -Mar -20 Prepare and Submit Final Construction Cost Estimate P 24 17 -Mar -20 17 -Apr -20 Q P Prepare and Submit Final Plans to Village --------------- 24 17 -Mar -20 17 -Apr -20 Q ---- --------------------- IEPA Permit Review and Approval 60 17 -Mar -20 15 -May -20 Bidding and Bid Opening 11 24 -Apr -20 08 -May -20 0 Bid Evaluations and Construction Contract Document Assembly 10 11 -May -20 22 -May -20 0 _ Contract Award ---------------,-------- 0----------,I 0 19 -May -20 -----------------------,I -------------------- Construction NTP 0 26 -May -20 O Construction 86 02 -Jun -20 01 -Oct -20 Substantial Completion 0 01 -Oct -20 Punch List 21 02 -Oct -20 30 -Oct -20 ---------------------, D Final Completion 0 30 -Oct -20 O MOW swig M, Post -project Review & As -built Drawings 20 02 -Nov -20 30 -Nov -20 0 Project Complete 0 30 -Nov ---20 O Page 1 of 1 Date Revision Checked Approved 09 -Jan -20 Proposed Schedule 01/09/2020 SP BURNS MMONNELL° BURNS M�DONNELL.. CREATE AMAZING. 1431 Opus Place, Suite 400 Downers Grove, 11L 60515 lb u ir n s rn c d.. c o rn