HomeMy WebLinkAbout04/16/2019 Bid Result Design and Construction Engineering Services - Maple Street Parking Deck5/1/2019 BoardDocs® Pro
Agenda Item Details
Meeting Apr 16, 2019 - REGULAR MEETING OF THE MOUNT PROSPECT VILLAGE BOARD - 7:00 p.m.
Category 8. VILLAGE MANAGER'S REPORT
Subject 8.2 Motion to accept proposal for design and construction engineering services for Maple
Street Parking Deck in an amount not to exceed $248,500.
Access Public
Type Action
Preferred Date Apr 16, 2019
Absolute Date Apr 16, 2019
Fiscal Impact Yes
Dollar Amount 248,500.00
Budgeted Yes
Budget Source Tax Increment Financing District Fund
Recommended Action Accept the proposal for design and construction engineering services to construct the Maple
Street Parking Deck as submitted by Walker Consultants of Hoffman Estates, Illinois in an
amount not to exceed $248,500.
Public Content
Plans for the Maple Street Lofts redevelopment project include design and construction of a 268 -space, multi-
level parking garage. This facility will be designed and constructed in conjunction with the redevelopment project, but
will be owned and operated by the Village. The Village is responsible for costs associated with designing and
constructing the deck.
The parking spaces provided by this new deck are intended to replace the Maple Street surface parking lot. A portion
of the land presently occupied by the Maple Street Parking Lot will be redeveloped with a mixed-use building with
rental apartments and commercial space, as well as a portion of rowhomes with related improvements such as
underground stormwater detention. Attachment A depicts the location of the proposed Maple Street Parking Deck as it
relates to the project's site plan. Attachment B presents a potential layout concept.
Request for Proposals (RFP).
To design this deck, staff requires technical assistance from a qualified parking facility design and construction
consultant. Accordingly, staff prepared a detailed request for proposals (RFP) necessary to solicit these services. A
copy of this RFP is enclosed as Attachment C. Parking facility consultants were asked to submit a technical proposal
detailing the firm's background, key personnel, and approach to the project. In addition, each firm was also asked to
submit a separate cost proposal indicating work effort anticipated and a not -to -exceed fee. The required scope of
work included topography and field data collection; preparation of plans and bid documents; and construction
management/inspection (Phase 2 and Phase 3 engineering).
Two (2) technical proposals and two (2) cost proposals were received. Each proposal was evaluated based on the
background of the firm, related project experience, proposed services and scope of work, schedule, work effort, and
https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login# 1/3
5/1/2019
proposal content. Table 1 below summarizes this analysis:
Table 1: Technical Proposal Analysis
BoardDocs® Pro
Category
Max Points
Walker Consultants
Desman Design
Management
Background
20
20
20
Experience
20
20
20
Scope
25
23
19
Schedule
15
14
13
Work Effort
10
9
7
Content
10
10
7
Totals:
100
96
86
Each firm was also asked to submit a cost proposal as well. Table 2 below summarizes staff's analysis of costs:
Table 2: Cost Proposal Analysis
Firm Hours Total Cost Cost / Hour
Walker Consultants 1,508 $248,500 $165
Desman 1,083 $276,300 $255
The highest rated, and lowest -cost proposals, were submitted by Walker Consultants of Hoffman Estates, Illinois
(Walker). Walker is a global consulting firm that specializes in the design and construction of parking facilities. The
firm was started in 1965 and presently has over 300 employees in 18 domestic and one (1) international office. The
firm has designed and constructed parking facilities in all 50 states and 20 foreign countries. The firm maintains a
regional office in Hoffman Estates, Illinois.
Staff conducted interviews with representatives from Walker and Desman Design Management. Although both firms
fielded exceptional project teams, it is the opinion of staff that Walker submitted a more qualitative proposal and
assembled a uniquely qualified project team that will better serve the Village's needs. Notably, Walker designed and
constructed comparable decks in Libertyville and Palatine. Reference checks with both of these communities yielded
positive endorsements and complimentary comments about the firm's performance.
In addition, Walker has had several projects, including recent developments in Glen Ellyn and Elgin, that incorporate
the shared use of an adjacent building foundation. This component differentiates the project and requires a high level
of communication, planning, and coordination with third -party contractors and designers.
Most importantly, Walker has ample experience working in public/private partnerships as advocates for government
agencies. Consequently, staff is confident the firm will represent the interests of the Village well while working to
deliver a cost-effective, aesthetically pleasing parking facility.
It is staff's opinion that Walker understands the proposed project, has prepared a thorough proposal based on
extensive and unique experience, and is best qualified to perform the work. Staff has also concluded that Walker has
allocated sufficient work effort (1,508 hours) and their average hourly rate ($165) is competitive.
Alternatives
1. Accept proposal for Maple Street Parking Deck design and construction engineering services submitted by Walker
Consultants of Hoffman Estates, Illinois.
2. Action at discretion of Village Board.
Staff Recommendation
Staff recommends that the Village Board accept the proposal for design and construction engineering services to
construct the Maple Street Parking Deck as submitted by Walker Consultants of Hoffman Estates, Illinois in an amount
not to exceed $248,500.
https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login# 2/3
5/1/2019
BoardDocs® Pro
Attachment B
_ Maple Street Deck Layout Concept.pdf (171 KB)
Attachment C
_ Maple Street Parking Deck Design RFP.pdf (376 KB)
Attachment E _
Walker Consultants Cost Proposal.pdf (4,503 KB)
Attachment D
_ Walker Consultants Technical Proposal.pdf (14,907 KB)
MSL Parking Deck Location - Exhibit A.png (2,348 KB)
Administrative Content
I've replaced Attachment A as it had the old OLD old MSL site plan as the background image. - NB
Executive Content
Motion & Voting
Accept the proposal for design and construction engineering services to construct the Maple Street Parking Deck as
submitted by Walker Consultants of Hoffman Estates, Illinois in an amount not to exceed $248,500.
Motion by Michael Zadel, second by Richard Rogers.
Final Resolution: Motion Carries
Yea: William Grossi, Eleni Hatzis, Paul Hoefert, Richard Rogers, Colleen Saccotelli, Michael Zadel