HomeMy WebLinkAbout8.1 Authorization for the Village Manager to amend the Construction Management Contract for new Fire HQ4/10/2019 BoardDocs® Pro Agenda Item Details Meeting Apr 03, 2019 - REGULAR MEETING OF THE MOUNT PROSPECT VILLAGE BOARD - 7:00 p.m. - REVISED Category 8. VILLAGE MANAGER'S REPORT Subject 8.1 Authorization for the Village Manager to amend the Construction Management contract with Nicholas and Associates to include a guaranteed maximum price of $7,958,000 for the new Fire Headquarters to be located at 111 E. Rand Road Access Public Type Action Preferred Date Apr 03, 2019 Absolute Date Apr 03, 2019 Fiscal Impact Yes Dollar Amount 7,958,000.00 Budgeted Yes Budget Source Fire Headquarters Capital Account Recommended Action Authorization for the Village Manager to amend the Construction Management contract with Nicholas and Associates to include a guaranteed maximum price of $7,958,000 for the new Fire Headquarters to be located at 111 E. Rand Road Public Content Information On May 15, 2018, the Village Board authorized the purchase of 111 E. Rand Road for the adaptive reuse as the new Fire Headquarters and Station 13. Then on July 17, 2018, Williams Architects and Nicholas and Associates were hired to design and construct the project. The first authorized construction budget by the Village Board was $7,478,000, with an overall project budget of $10,378,000. As the design team worked through layout options with staff, a building addition to the Apparatus bay was approved by the Board on September 11, 2018 at a cost of $300,000, raising the approved construction budget to $7,778,000. However, due to land acquisition costs being lower than budgeted, this $300,000 construction cost increase had a zero impact to the overall project budget, which remained at $10,378,000 including land acquisition, FFE (fixtures, furnishings, and equipment)/by owner costs, and design and other soft costs. Moving through schematic design and into design development drawings provided for a projected construction budget that grew to $8,211,117. The final update to the construction budget at 80% Construction Document completion included an anticipated construction budget of $8,311,193 which pushed the overall project budget to $10,911,193, or about $533,000 over budget. The savings from the architectural fee and other soft cost savings of $200,000 reduced the anticipated budget shortfall to $333,000, with an overall anticipated construction budget of $10,711,193. This increased amount can be attributed to a number of additional scope items now included in the project budget, including: • The addition of a seventh bay within the same apparatus footprint, • Additional site work not anticipated due to utility connections on site, • Additional radiant slab heating, https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login# 1/3 4/10/2019 BoardDocs® Pro • Additional interior details such as full height tile walls in the bathrooms and some glass replacement not anticipated in initial budgeting. The Village in conjunction with the Fire HQ construction manager, Nicholas and Associates, advertised 22 bid packageson February 22, 2019 in order get a final cost of the new Fire HQ. Those bids were accepted and opened at the Village Hall on March 15, 2019. A total of 86 companies responded to the request for bids, which results in an average of 3.9 bidders per package. Staff is encouraged with the results of the bid opening, as the bids came in below the estimated budget. The final guaranteed maximum price (GMP) as offered by Nicholas and Associates for the Fire Headquarters is $7,958,000, which includes a project contingency of $508,500. This provides for an overall project budget of $10,357,890. This GMP is under the initial project budget by approximately $20,000. This GMP includes all of the additional scopes of work mentioned previously, and outlined below: • Decorative fencing instead of vinyl coated chain link fencing • Stainless steel counters in the kitchen • Epoxy coating in apparatus bay to match the coating at Public Works and the new Police HQ • A full building lightning protection system • 100% acoustical panel coverage on the apparatus bay ceiling • Full height ceramic tile in bathrooms • Monument signs at both entrances • Additional under slab radiant heat in apparatus bay • Replacement of the existing sanitary and storm pumps in the lower level of the building It is clear that the efforts of the Construction Manager, Architects, and Village Staff to control the overall costs of this project have paid off. The Fire Headquarters will reflect all the needs and requests of the Fire Staff and the needs for the long term maintenance of the building by Public Works, all within the original overall project budget parameters. As previously noted, the new project budget is more than $20,000 under the original as proposed in early 2018, prior to the start of design. As a reminder, the contingencies outlined in the overall project GMP are fully refundable to the Village in case they are not used. Therefore, the potential exists to be even further under budget at the end of the construction process. Alternatives 1. Motion to authorize the Village Manager to amend the Construction Management contract with Nicholas and Associates to include a guaranteed maximum price of $7,958,000 for the new Fire Headquarters to be located at 111 E. Rand Road. 2. Action at discretion of Village Board. Staff Recommendation As the project includes additional services and is still under the original project total budget, staff recommends approval of a motion to authorize the Village Manager to amend the Construction Management contract with Nicholas and Associates to include a guaranteed maximum price of $7,958,000 for the new Fire Headquarters to be located at 111 E. Rand Road. Administrative Content Executive Content Motion & Voting Authorization for the Village Manager to amend the Construction Management contract with Nicholas and Associates to include a guaranteed maximum price of $7,958,000 for the new Fire Headquarters to be located at 111 E. Rand https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login# 2/3 4/10/2019 Road BoardDocs® Pro Motion by Michael Zadel, second by Richard Rogers. Final Resolution: Motion Carries Yea: William Grossi, Eleni Hatzis, Paul Hoefert, Richard Rogers, Colleen Saccotelli, Michael Zadel https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login# 3/3 Village of Mount Prospect Community Development Department MEMORANDUM TO: MICHAEL CASSADY, VILLAGE MANAGER CC: NELLIE BECKNER, ASSISTANT VILLAGE MANAGER FROM: MARK RYSAVY, DD BUILDING & INSPECTION SERVICES DATE: MARCH 26, 2019 SUBJECT: FIRE HEADQUARTERS GUARANTEED MAXIMUM PRICE Prospect On May 15, 2018 the Village Board authorized the purchase of 111 E. Rand Road for the adaptive reuse as the new Fire Headquarters and Station 13. Then on July 17, 2018, Williams Architects and Nicholas and Associates were hired to design and construct the project. The first authorized construction budget by the Village Board was $7,478,000 with an overall project budget of $10,378,000. As the design team worked through layout options with the staff, a building addition to the Apparatus bay was approved by the Board on September 11, 2018 at a cost of $300,000 raising the approved construction budget to $7,778,000. However, due to land acquisition costs being lower than budgeted, this $300,000 construction cost increase had a zero impact to the overall project budget, which remained at $10,378,000 including land acquisition, FFE/by owner costs, and design and other soft costs. Moving through schematic design and into design development drawings provided for a projected construction budget that grew to $8,211,117. The final update to the construction budget at 80% Construction Document completion included an anticipated construction budget of $8,311,193 which pushed the overall project budget $10,911,193 or about $533,000 over budget. The savings from the architectural fee and other soft cost savings of $200,000 reduced the anticipated budget shortfall to $333,000 with an overall anticipated construction budget of $10,711,193. This increased amount can be attributed to a number of additional scope items now included in the project budget including the addition of a seventh bay within the same apparatus footprint, some additional site work not anticipated due to utility connections on site, additional radiant slab heating, some interior details like full height tile walls in the bathrooms, and some glass replacement not anticipated in initial budgeting. Anticipating positive bid results staff proceeded with the project bidding, and on February 22, 2019 the Village, in conjunction with the Fire HQ construction manager, Nicholas and Associates, advertised 22 bid packages in order get a final cost of the new Fire HQ. Those bids were accepted at the Village Hall on March 15, 2019 and were opened over the afternoon. The bid packages were as follows: 001 Demolition and Abatement 002 Earthwork 003 Site Utilities 004 Fencing and Gates Page 2 005 Concrete 006 Asphalt Paving 007 Masonry 008 Steel 009 Roofing 010 Aluminum and Glazing 011 Overhead Doors 012 Doors, Frames, and Hardware 013 General Trades 014 Framing and Drywall 015 Flooring and Tile 016 Acoustical Ceilings 017 Paints and Coatings 018 Elevator 019 Fire Suppression 020 Plumbing 021 HVAC 022 Electrical 86 companies responded overall to the request for bids, which gave us an average of 3.9 bidders per package. When compiling all the bids for each package, staff is encouraged with the results as the bids came in below the estimated budget. The final guaranteed maximum price (GMP) as offered by Nicholas and Associates for the Police Headquarters is $7,958,000 which includes a project contingency of $508,500. This provides for an overall project budget of $10,357,890. This GMP includes all of the additional scopes of work mentioned previously, but outlined below: Decorative fencing instead of vinyl coated chain link fencing Stainless steel counters in the kitchen Epoxy coating in apparatus bay to match the coating at public works and the new Police HQ • A full building lightning protection system • 100% acoustical panel coverage on the apparatus bay ceiling Full height ceramic tile in bathrooms Monument signs at both entrances Additional under slab radiant heat in apparatus bay Replacement of the existing sanitary and storm pumps in the lower level of the building A detailed construction budget breakdown is provided as an attachment to this memo, but a summary of the project costs from initial budget presentation to the final GMP and budget is below: Page 3 It is clear that the efforts of the Construction Manager, Architects, and Village Staff to control the overall costs of this project have paid off. The Fire Headquarters will reflect all the needs and requests of the Fire Staff and the needs for the long term maintenance of the building by Public Works, all within the original overall project budget parameters. In fact, the new project budget is more than $20,000 under the original as proposed in early 2018 prior to the design even beginning. As a reminder the contingencies outlined in the overall project GMP are fully refundable to the Village in case they are not used. So the potential exists to be even further under budget at the end of the construction process. At the Village Board meeting on April 4, 2019 staff will be requesting for the Board to authorize the Village Manager to modify the contract for Construction Management services with Nicholas and Associates to include the GMP of $7,958,000. 111 E. Rand Road - New Fire HQ Original Budget- Amended GMP Costs Construction Cost $7,277,000.00 $7,149,500.00 add'I costs for app bay $300,000.00 $300,000.00 project contingency $201,000.00 $508,500.00 FFE/ By Owner Costs $350,000.00 $350,000.00 Design Fees & Soft Costs $750,000.00 Architect Base $498,000.00 Architect Interior $16,500.00 Architect Reimb. $10,000.00 Furniture Design $18,200.00 site borings $7,190.00 Total Cost Without Land $8,878,000.00 $8,857,890.00 Land Acquisition $1,500,000 $1,500,000.00 Total Project Cost $10,378,000.00 $10,357,890.00 It is clear that the efforts of the Construction Manager, Architects, and Village Staff to control the overall costs of this project have paid off. The Fire Headquarters will reflect all the needs and requests of the Fire Staff and the needs for the long term maintenance of the building by Public Works, all within the original overall project budget parameters. In fact, the new project budget is more than $20,000 under the original as proposed in early 2018 prior to the design even beginning. As a reminder the contingencies outlined in the overall project GMP are fully refundable to the Village in case they are not used. So the potential exists to be even further under budget at the end of the construction process. At the Village Board meeting on April 4, 2019 staff will be requesting for the Board to authorize the Village Manager to modify the contract for Construction Management services with Nicholas and Associates to include the GMP of $7,958,000. ..- . • ..- - Station No. 13JA • Attachment BP # Description (30,600 SF) $/SF TOTAL Allowance Included 001 Demolition & Abatement 7.00 $214,125 $15,000 002 Earthwork 13.21 $404,100 $100,000 003 Site Utilities 4.68 $143,153 $15,000 004 Fencing & Gates 4.83 $147,850 $5,000 005 Concrete 18.45 $564,700 $20,000 006 Asphalt Paving 1.91 $58,493 $15,000 007 Masonry 14.11 $431,900 $20,000 008 Steel 7.97 $243,800 $10,500 009 Roofing 11.00 $336,670 $20,000 010 Aluminum & Glazing 5.11 $156,500 $20,000 011 Overhead Doors 1.63 $49,900 $3,000 012 Doors, Frames & Hardware 3.64 $111,270 $15,000 013 General Trades 15.03 $459,800 $60,000 014 Framing & Drywall 12.47 $381,625 $20,000 015 Flooring & Tile 13.74 $420,349 $15,000 016 Acoustical Ceilings 4.72 $144,528 $10,000 017 Paints & Coatings 5.62 $172,000 $10,000 018 Elevator 3.10 $95,000 $5,000 019 Fire Suppression 3.29 $100,756 $10,000 020 Plumbing 18.62 $569,900 $40,000 021 HVAC 24.97 $763,965 $40,000 022 Electrical 37.71 $1,154,040 $40,000 Landscaping Allowance 2.45 $75,000 Lockers & Benches 2.61 $80,000 Window Treatments 0.33 $10,000 Flagpoles 0.23 $7,142 Signage & Plaques Allowance 2.12 $65,000 Pre-emptive Control on Main Street Allowance 1.63 $50,000 Total Hard Costs Contingency / Allowances Insurance Bond Premium General Conditions Construction Fee $7,411,566 Included in Bid Packages Included in Fee 1.82 $55,587 8.77 $268,500 7.27 $222,347 Total Construction Costs 260.07 $7,958,000 $508,500