8.3 Motion to accept proposal for pedestrian crossing signal design and construction engineering
services in an amount not to exceed $79,430.
Public
Action
]an 15, 2019
]an 15, 2019
Yes
79,430.00
Yes
Accept the proposal from Sam Schwartz Engineering to provide design and construction
engineering services for the 2019 Pedestrian Signal Project for a not to exceed amount of $79,430.
A key component of the Village"s Strategic Plan is to create a complete pedestrian infrastructure network that promotes multi-
modal transportation options. This project looks to enhance safety and efficiency for pedestrians crossing at traffic -signalized
intersections under the jurisdiction of the Illinois Department of Transportation (IDOT) and Cook County Department of
Transportation and Highways (CCDOTH). The project scope includes work at four intersections and is described below:
rpm11111
Three (3) intersections in the downtown business district including Northwest Highway @ Main Street, Northwest Highway
Emerson Street, and Main Street @ Prospect Avenue, are part of an interconnected traffic signal system under the jurisdictio
of the Illinois Department of Transportation (IDOT). This system is also interconnected with the Union Pacific railroad gates a
the Main Street (IL Route 83) and Emerson Street crossings. These intersections currently have pedestrian crossing signal
However, a single push button at each corner limits the efficiency of the traffic signal timing by putting a call to multipl
crossings. The objective is to install two separate push buttons at each corner such that a call is for a single crossing. Desig
will include evaluating post locations and sidewalk ramps to assure they comply with ADA standards. An important componen
of the project will be to coordinate efforts with IDOT as they will be resurfacing Northwest Highway through Mount Prospect i
2019. In addition, design work will also require coordination with the Union Pacific Railroad and the Illinois Commerc
Commission.
rem
This stand-alone intersection is under the jurisdiction of Cook County Department of Transportation and Highways (CCDOTH). I
currently has pedestrian crossing signals on the east leg of the intersection. The Village installed sidewalk this year alon
Dempster Street west of Linneman Road. The objective is to install pedestrian crossing signals on the north leg of th
intersection. Design will include a marked crosswalk that may necessitate relocating the stop line and loop detectors. It will als
include evaluating post locations and sidewalk ramps to assure they comply with ADA standards. Funds for construction wi
come from the Community Development Block Grant (CDBG) Program requiring a separate contract from the downtown work.
https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login 1/16/2019
BoardDocs® Pro Page 2 of 3
Staff is seeking at this time to enter into a contract with a consulting firm for design and construction engineering to facilitatit
construction of the pedestrian signal improvements at these four (4) intersections. Work must be performed under twit,
separate contracts requiring two (2) sets of construction plans and potentially separate construction schedules depending on
when permits are obtained from IDOT and CCDOTH.
As permitted by the Village Purchase Policy, staff solicited Technical and Cost Proposals from four (4) engineering consulting
firms to provide design and construction engineering services for the pedestrian signal project. Three (3) firms responded
sending in Technical and Cost Proposals while one (1) firm declined due to scheduling conflicts. Each firm was asked to submit
as part of their proposal the following information:
1. Resumes of key personal and related experience on similar type projects
2. Summary of the firm"s approach to the project
3. Project schedule
4. Staff hour estimate and cost proposal for major phases of work
Tasks that are identified to be performed include:
MGM=o
• Perform field survey
• Incorporate pedestrian signals into traffic signal timing plans
• Prepare two sets of construction plans, specifications, and cost estimates
• Comply with ADA design requirements
• Provide bidding assistance
• Provide construction layout
• Provide construction inspection and supervision for two separate contracts
• Attend construction meetings
• Prepare pay estimates, punch -list, and as -built drawings
The consulting firms" Technical and Cost Proposals were reviewed on the basis of their understanding of our goals and thei
methodology of the design process. They were rated (with a maximum score of 100 points) according to these specifi
III
categories: project team, relevant experience, project approach, project schedule, work effort, and proposal content. Cos
proposals were requested from all of the firms to perform the tasks as identified in the Request for Technical and Cos
Proposals. All three (3) firms were then invited to be interviewed by Village staff. The rankings are:
Sam Schwartz Engineering has put together a very strong project team with experience in design for numerous municipal
transportation projects. They recently completed the Mount Prospect Downtown Transportation Study and have unique
knowledge of the relationship between vehicles, trains, pedestrians and bicyclists in our downtown. The downtown study
produced an improved traffic signal timing program, an evaluation of the train impact on traffic flow, an evaluation of the
potential impact on future downtown redevelopment, and strategies of short-term and long-term improvements. Patrick
Engineering, a subconsultant for Sam Schwartz Engineering, is currently the lead consultant on the Rand/83/Kensington
Intersection Phase I Study and will provide construction engineering services on this pedestrian signal project. Together, the
firms have a very experienced professional engineering staff with a thorough understanding of the project coordination,
communication and documentation needs to successfully accomplish the project within the proposed schedule. It is staff's
opinion that Sam Schwartz Engineering will provide the best product at an appropriate number of hours dedicated to design anl#
construction engineering.
Alternatives
1. Accept recommended proposal for design and construction engineering services.
2. Action at discretion of Village Board.
Staff Recommendation
https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login 1/16/2019
Sam Schwartz Engineering
Hampton, Lenzini, and Renwick, Inc. (HLR)
V3 Companies
Sam Schwartz Engineering has put together a very strong project team with experience in design for numerous municipal
transportation projects. They recently completed the Mount Prospect Downtown Transportation Study and have unique
knowledge of the relationship between vehicles, trains, pedestrians and bicyclists in our downtown. The downtown study
produced an improved traffic signal timing program, an evaluation of the train impact on traffic flow, an evaluation of the
potential impact on future downtown redevelopment, and strategies of short-term and long-term improvements. Patrick
Engineering, a subconsultant for Sam Schwartz Engineering, is currently the lead consultant on the Rand/83/Kensington
Intersection Phase I Study and will provide construction engineering services on this pedestrian signal project. Together, the
firms have a very experienced professional engineering staff with a thorough understanding of the project coordination,
communication and documentation needs to successfully accomplish the project within the proposed schedule. It is staff's
opinion that Sam Schwartz Engineering will provide the best product at an appropriate number of hours dedicated to design anl#
construction engineering.
Alternatives
1. Accept recommended proposal for design and construction engineering services.
2. Action at discretion of Village Board.
Staff Recommendation
https://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login 1/16/2019
BoardDocs® Pro Page 3 of 3
Staff recommends that the Village Board accept the proposal from Sam Schwartz Engineering to provide design and
construction engineering services for the 2019 Pedestrian Signal Project for a not to exceed amount of $79,430.
P. �p d f (4 7 7 K B) cost proposaLpff (1,856 KB)
locati&n map (003).pdf (321. KB) [Z 1: SSE
-u-iical proposaLpff (611-57 KB)
SSE tec[
Administrative Content
Executive Content
Motion & Voting
Accept the proposal from Sam Schwartz Engineering to provide design and construction engineering services for the 201t
Pedestrian Signal Project for a not to exceed amount of $79,430.
Motion by Richard Rogers, second by William Grossi.
Final Resolution: Motion Carries
Yea: William Grossi, Eleni Hatzis, Paul Hoefert, Richard Rogers, Colleen Saccotell: