HomeMy WebLinkAbout8.2 Project Update: New Fire HeadquartersBoardDocs® Pro Agenda Item Details Meeting Dec 11, 2018 - VILLAGE BOARD SPECIAL MEETING - 7:00 P.M. Category 8. VILLAGE MANAGER'S REPORT allbject 8.2 Project Upd M10-404,1quarters - 111 E. Rand Road Access Public Type Information Public Content Page I of 2 Information On October 2, 2018 the Village Board provided general direction for the Fire Headquarter design to move forward into thit design development phase. As such, staff has continued meeting weekly with the architects and construction manager t* further develop the entire building design and the budget. The drawings are currently ready to enter into construction documents and have been provided for review to the staff, along with Nicholas and Associates so they could complete an updated bu•- D- • e Design Update At this point, all interior wall locations and spatial designs have been completed and set. Each space has been analyzed as tit, where furniture will be provided by the Village versus where built in millwork will be designed by the Architects. The expanded apparatus bay has been incorporated into the floor plans based on previous direction from the Village Board. Initial meetings between staff, the design team, the construction team and the mechanical, electrical, plumbing, and fire protection engineers have taken place and major system design concepts have been set. The types of systems, gas or electric, have been selected, but specific designs have not begun. General interior finish types have been decided upon as well, however, no actual material selections have taken place. An initial interior design meeting has taken place where general color pallets have been narrowed, but no specific products have been selected. We also know that the majority of the Administrative staff's furniture will bit reused as it is only 6 years old and in great condition. On the exterior of the building materials have been set for some time as they will simply match the existing brick and metal window framing. The site has been designed to allow for fire trucks to be able to enter and leave the site on both major roadways with the use of the south drive aisle. Both entrances will be modified to account for the turning radius of the fire trucks. A simple landscape plan will be developed to compliment the existing vegetation that is to remain. Budget Update Other than the expansion of the apparatus bay, there have been very few changes to the project scope since the initial construction budget was set in early 2018. Initial project assumptions did not include the reuse of any major mechanical, electrical, or plumbing systems. The roof was planned to be replaced as well. So the only reuse of the building was thit structure and the exterior shell. These initial assumptions still hold true, however as the design has progressed, thit construction budget has increased. The initial budget plus the expansion of the apparatus bay was presented to the Board at $7,744,945 including a $483,000 contingency. The most recent budget presented to the staff by Nicholas and Associates this week came in at $8,226,690 with a $350,000 contingency. This is an increase of $481,745 overall. Similar to the Police Headquarters project cost saving measures have been discussed and include the following efforts: fence material modifications, reduction of sound control panels in the apparatus bay, reduction of ceramic tile for decorative purposes, electric system adjustments, elimination of one monument sign, reduction of the radiant heating system in the slab inside and outside the building, reuse of some heaters form 799 Biermann Court, and a change from a natural gas to electric building generator. These efforts are expected to net a savings of about $400,000 and not effect the comfort or function of the building. https://www.boarddocs.com/il/vomp/Board.nsf/Public 12/19/2018 BoardDocs® Pro Page 2 of 2 That leaves the budget about $81,000 or less than 1% over budget. The team from Nicholas and Associates has assured staff this amount may be made up during negotiations with subcontractors. This amount will work itself out as the project moves into construction documents and more specific details can be applied by contractors to the budget. It is the recommendation of staff to allow Williams Architects to move forward with construction documents for the Fire Headquarters. Alternatives 1. Action at discretion of Village Boarl Staff Recommendation Staff recommends the Village Board authorize Williams Architects to move forward with construction documents for the Fire Headquarters. -ire update memo 1.2-.7-201.8.pff (94 KB) 1: VOMP Statio�n 1.3 BUdget 12.4.18.pdf (1.1.0 KB) ........... . .. . . Administrative Content Executive Content https://www.boarddocs.com/il/vomp/Board.nsf/Public 12/19/2018 Village of Mount Prospect Community Development Department MEMORANDUM TO: MICHAEL CASSADY, VILLAGE MANAGER CC: NELLIE BECKNER, ASSISTANT VILLAGE MANAGER FROM: MARK RYSAVY, DD BUILDING & INSPECTION SERVICES DATE: DECEMBER 7, 2018 SUBJECT: FIRE HEADQUARTERS STATUS UPDATE Mount Prospect The following is a brief overview of the status of the Fire Headquarters design process and what will be presented at the Village Board meeting on Tuesday December 1 lth. On October 2, 2018 the Village Board provided general direction for the Fire Headquarter design to move forward into the design development phase. As such, staff has continued meeting weekly with the architects and construction manager to further develop the entire building design and the budget. The drawings are currently ready to enter into construction documents and have been provided for review to the staff, along with Nicholas and Associates so they could complete an updated budget. Design Update At this point, all interior wall locations and spatial designs have been completed and set. Each space has been analyzed as to where furniture will be provided by the Village versus where built in millwork will be designed by the Architects. The expanded apparatus bay has been incorporated into the floor plans based on previous direction from the Village Board. Initial meetings between staff, the design team, the construction team and the mechanical, electrical, plumbing, and fire protection engineers have taken place and major system design concepts have been set. The types of systems, gas or electric, have been selected, but specific designs have not begun. General interior finish types have been decided upon as well, however no actual material selections have taken place. An initial interior design meeting has taken place where general color pallets have been narrowed, but no specific products have been selected. The furniture design has also begun. Staff has met with the furniture designer from STV Construction twice times and have visited showrooms of all types for furniture. The layouts of each office and desk space have been discussed and will be completed in drawing format in mid-December. Final material selections for furniture will be completed in early 2019 to be bid in middle to late 2019 as this installation work will not begin until 2020 prior to move in. The bonus to the Fire project is that the existing furniture in the administration offices is only 6 years old. As such most of it will be reused. The floor plans have been massaged to account for current furniture layouts. On the exterior of the building materials have been set for some time as they will simply match the existing brick and metal window framing. The site has been designed to allow for fire trucks to be able to enter and leave the site on both major roadways with the use of the south drive aisle. Both entrances Page 2 will be modified to account for the turning radius of the fire trucks. A simple landscape plan will be developed to compliment the existing vegetation that is to remain. Budget Update Other than the expansion of the apparatus bay, there have been very few changes to the project scope since the initial construction budget was set in early 2018. Initial project assumptions didn't include the reuse of any major mechanical, electrical, or plumbing systems. The roof was planned to be replaced as well. So the only reuse of the building was the structure and the exterior shell. These initial assumptions still hold true. The project budget was on target after the schematic design phase. To offset the additional cost of the expanded apparatus bay, the Village Board previously approved the use of cost saving from the building purchase on the extra construction. The budget after preliminary design was $7,744,945 with a $483,000 contingency. Now that Design Development is completed, the budget has grown to $8,226,690 with a $350,000 contingency, which is an increase of $481,745. This is a reflection of the design team and Village staff packing as much responsible value into the project as possible. Now that the team sees the costs, several cost cutting measures have been proposed including: fence material modifications, reduction of sound control panels in the apparatus bay, reduction of ceramic tile for decorative purposes, electric system adjustments, elimination of one monument sign, reduction of the radiant heating system in the slab inside and outside the building, reuse of some heaters form 799 Biermann Court, and a change from a natural gas to electric building generator. These efforts are expected to net a savings of about $400,000 and not effect the comfort or function of the building. These modifications will leave the project at about $81,000 over budget, which Nicholas and Associates is confident can be overcome to be back on budget overall. Much of this flux in costs is a reflection of budgeting by contractors being safe because not all the information is available at the design development level of drawings. Once construction documents are completed there will be a significant amount of detail on each product and system that will be used in the building. That is the point when the project will be ready for public bid. Upcoming Schedule The design development phase has concluded and staff is looking for approval from the Board to move forward with construction documents. Assuming construction documents move forward as planned, they should be completed by February 19, 2019 to be handed off to Nicholas and Associates for the public bidding process. No official bid date has been set yet, but all public bids are expected to be due in early March 2019 with Board approval of a guaranteed maximum price before the end of March, and construction to begin in April 2019. The schedule for construction is between 10 and 12 months, so no advanced construction packages are expected to be released at this point. Village Of Mount Prospect WILLIAMS 1AAFire Station No. 13 ARCHITECTS N I C N® L A 5 Schematic Design Budget VOMP Fire Station No. 13 Construction Estimates ......................................................................................................................................................................................................................... ITEM DISCRIPTION DEMOLITION ABATEMENT (Allowance) CONCRETE WORK (Building foundations & SOG) MASONRY STEEL ROUGH CARPENTRY ROOFING & SHEET METAL JOINT SEALANTS DOORS, FRAMES & HARDWARE INSTALLATION - DOORS, FRAMES & HARDWARE OVERHEAD DOORS GLASS, GLAZING, & ALUMINUM SYSTEMS METAL STUDS & DRYWALL PORCELAIN / CERAMIC TILE ACOUSTICAL CEILING SYSTEMS CARPET TILE & WOM RUBBER FLOORING LVT (RESILIENT) VCB EPDXY FLOORING SEALED CONCRETE FLOORS PAINTING & WALL COVERING TECTUM CEILING PANELS INTERIOR SIGNAGE (Allowance) DIMENSIONAL SIGNAGE / PLAQUES (Allowance) TOILET PARTITIONS TOILET ACCESSORIES FIRE PROTECTION SPECIALTIES LOCKERS & BENCHES SOLID SURFACE WALL PROTECTION FITNESS ROOM MIRRORS WINDOW TREATMENTS MANUFACTURED CASEWORK (F&I) KITCHEN CABINETRY (material Only) FLAG POLES ELEVATOR FIRE PROTECTION PLUMBING HVAC ELECTRICAL EARTHWORK SITE CONRETE WORK FENCING (Interior & Exterior) ASPHALT PAVING LANDSCAPING (Allowance) SITE UTILITIES ROOF SCREENING TRASH ENCLOSURE GENERATOR ENCLOSURE MONUMENT SIGN(S) PRE-EMPTIVE CONTROL - Main St. ALT Apparatus Bay Extension CONTINGENCY INSURANCE BOND PREMIUM GENERAL CONDITIONS CONSTRUCTION FEE 12/6/2018 100% Schematic Design 100% Design Development 60% Construction Documents ....................................................................................................................................................................................................................................................................................................................................................................................................................... TOTAL $190,000 $45,000 $225,000 $395,000 $100,000 $12,000 $255,000 $15,000 $185,000 $40,000 $42,400 $45,000 $355,000 $150,000 $50,000 $55,000 $40,000 $65,000 $0 Alternate $50,000 $150,500 $80,000 $7,500 $0 $7,500 $10,000 $12,500 $100,000 $30,000 $49,000 $0 $10,000 $37,500 $0 $0 $115,000 $100,000 $445,000 $935,000 $930,000 $311,000 $260,000 $105,000 $132,000 $75,000 $50,000 $50,000 $20,000 $15,000 $50,000 $50,000 $268,000 TOTAL HARD $6,719,900 $503,993 Included in Fee $50,399 $268,500 $201,597 $175,000 $45,000 $225,000 $515,000 $170,000 $15,000 $332,500 $15,000 $149,995 $41,500 $52,300 $95,550 $411,000 $226,000 $50,100 $53,000 $35,000 $41,000 $37,000 Alternate $53,000 $165,500 $102,800 $5,500 $42,000 $7,000 $12,500 $13,500 $125,000 $32,500 $49,000 Included in Glass/Glazing # $12,000 $110,800 $30,000 $3,000 $115,000 $110,000 $448,500 $920,650 $1,200,000 $315,000 $260,000 $110,000 $135,000 $75,000 $60,000 $0 $20,000 $0 $50,000 $50,000 $7,318,195 $350,000 Included in Fee $54,886 $268,500 $219,546 Village Of Mount Prospect WILLIAMS 1AAFire Station No. 13 ARCHITECTS N I C H 0 L A 5 Schematic Design Budget 12/6/2018 2 TOTAL CONSTRUCTION COSTS $7,744,389 $8,211,127 NO. ALTERNATES TOTAL 01 Alternate No. 1: Provide 6'-0" high vinyl -coated DEDUCT Chain Link Fence (refer to Section 323113 - Chain Link Fences) in lieu of fence specified. 02 Alternate No. 2: Remove portion of existing west DEDUCT parking lot and restore to landscape area (refer to civil and landscape documents bound separately). 03 Alternate No. 3: Provide double -broadcast quartz ADD $172,000 epoxy floor finish (refer to Section 096724 - Double Broadcast Epoxy Quartz Flooring) in Apparatus Bay zone. 04 Alternate No. 4: Install existing captured exhaust ADD / system in Apparatus Bay 156. Contractor to DEDUCT disassemble existing system and reinstall at subject site. Refer to Mechanical drawings. 05 Alternate No. 5: Provide stainless steel countertops in ADD Kitchen 138 (refer to Section 123560 - Stainless Steel Kitchen Cabinets). 06 Alternate No. 6: Provide stainless steel upper and ADD lower cabinets in Kitchen 138 (refer to Section 123560 -Stainless Steel Kitchen Cabinetry). 07 Alternate No. 7: Provide Chemical Resistant ADD $167,000 Epoxy/Urethane flooring in Apparatus Zone. Refer to Section 097500 - Chemical Resistant Epoxy/Urethane Flooring System. 08 Alternate No. 8: Provide complete Lightning ADD Protection System. Refer to Section 264113 - LightningProtection for Structures. 09 Alternate No. 9: Provide Heavy Duty Asphalt in lieu of DEDUCT Concrete Pavement where indicated (refer to civil documents bound separately). 10 Alternate No. 10: Provide 50% Tectum panel cover in DEDUCT ;d44,000 the apparatus bay in lieu of 100% Coverage 12/6/2018 2