HomeMy WebLinkAbout5.06 Resolution Authorizing an Intergovernmental Agreement between IDOT and the Village5/12/2017 BoardDocs® Pro
IN
Agenda Item Details
Meeting
May 16, 2017 - REGULAR MEETING OF THE MOUNT PROSPECT VILLAGE BOARD - 7:00 p.m.
Category
5. CONSENT AGENDA
Subject
5.6 A RESOLUTION AUTHORIZING AN INTERGOVERNMENTAL AGREEMENT BETWEEN THE
ILLINOIS DEPARTMENT OF TRANSPORTATION AND THE VILLAGE OF MOUNT PROSPECT TO FUND
SIDEWALK RAMP IMPROVEMENTS ASSOCIATED WITH THE IL ROUTE 83 (ELMHURST ROAD)
RESURFACING PROJECT.
Access
Public
Type
Action (Consent)
Preferred Date
May 16, 2017
Absolute Date
May 16, 2017
Fiscal Impact
Yes
Dollar Amount
2,070.00
Budgeted
No
Budget Source
Street Resurfacing Construction Fund
Recommended
Authorize the Mayor to sign an intergovernmental agreement with IDOT for construction expenses
Action
related to the resurfacing of IL Route 83 and pass a resolution verifying funding for this
expenditure.
Public Content
Information
The Illinois Department of Transportation (IDOT) has scheduled resurfacing of IL Route 83, Elmhurst Road, from U.S.
Route 14, Northwest Highway, to Palatine Road. The section between Northwest Highway and Camp McDonald Road is
within the Village of Mount Prospect.
The bid opening for this project is scheduled for the summer of 2017. Construction is expected to start this summer and
be completed by the end of the year. The scope of work includes grinding off the existing asphalt, installing new asphalt
surface, intermittent curb replacement, sidewalk ramp improvements, pavement striping, and structure adjustments. The
total estimated project cost is $3,100,000.
The contract for this work will be let and administered by IDOT.
The proposed improvements will require the removal and replacement of existing American with Disabilities Act (ADA) -
required sidewalk ramps in the downtown area. The ramps at Route 83 & Busse Avenue as well as the ramps at Route 83
& Central Road are constructed of brick pavers previously installed as part of our downtown streetscape projects. The
Village is required to bear the cost of replacing these brick paver ramps.
In order for the brick work to be included in IDOT's project, the agency has prepared an intergovernmental agreement to
establish our share of the cost. The cost to include required brick sidewalk ramp work is $2,070.
In addition, the agreement requires the Village pass a funding resolution, included as Exhibit B to the agreement. This
Resolution verifies that the Village has appropriated sufficient funds to pay for our share of the cost of the improvements.
The agreement also includes Exhibit C, An Ordinance Restricting Parking along Route 83. The Village currently has a code
restricting all parking along Route 83 throughout the entire length of the Village. Consequently, no Village Board action is
necessary to satisfy this requirement.
hftps://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login 1/2
5/12/2017
Alternatives
BoardDocs® Pro
1. Authorize the Mayor to sign an intergovernmental agreement with IDOT for construction expenses related to the
resurfacing of IL Route 83 and pass a resolution verifying funding for this expenditure.
2. Action at discretion of Village Board.
Staff Recommendation
Staff recommends that the Village Board authorize the Mayor to enter into an intergovernmental agreement with
IDOT for costs associated with IL Route 83 resurfacing brick sidewalk work. Staff also recommends that the Village Board
pass a resolution verifying the availability of funds for this purpose in an amount of $2,070.
IGA.pdf (39 KB) Resolution IDOT IL 83 funding.pdf (14 KB)
Administrative Content
Executive Content
All items under Consent Agenda are considered routine by the Village Board and will be enacted by one motion. There will
be no separate discussion of those items unless a Board member or member from the audience so requests, in which the
item will be removed from the Consent Agenda and considered in its sequence on the agenda.
hftps://www.boarddocs.com/il/vomp/Board.nsf/Private?open&login 2/2
RESOLUTION NO.
A RESOLUTION AUTHORIZING AN INTERGOVERNMENTAL AGREEMENT
BETWEEN THE ILLINOIS DEPARTMENT OF TRANSPORTATION AND
THE VILLAGE OF MOUNT PROSPECT TO FUND SIDEWALK RAMP IMPROVEMENTS ASSOCIATED
WITH THE IL ROUTE 83 (ELMHURST ROAD) RESURFACING PROJECT.
WHEREAS, , the Village of Mount Prospect has entered into an Agreement with the Illinois Department of
Transportation (IDOT) to fund sidewalk ramp improvements associated with the IL Route 83 (Elmhurst
Road) Resurfacing Project; and
WHEREAS, in compliance with the aforementioned Agreement, it is necessary for the Village of Mount
Prospect to appropriate sufficient funds to pay its share of the cost of said improvement
NOW THEREFORE, BE IT RESOLVED BY THE MAYOR AND BOARD OF TRUSTEES OF THE
VILLAGE OF MOUNT PROSPECT, COOK COUNTY, ILLINOIS PURSUANT TO ITS HOME RULE
POWERS:
SECTION ONE: The Board of Trustees of the Village of Mount Prospect do hereby authorize and direct the
Mayor to execute Agreement between the Village of Mount Prospect and the Illinois Department of
Transportation for the appropriated sum of Two Thousand Seventy Dollars (2,070.00) or so much thereof
as may be necessary, from any money now or hereinafter allotted to the Village to pay its share of the cost
of this improvement as provided in the Agreement attached hereto and made a part of this Resolution as
Exhibit "A".
SECTION TWO: That upon award of the contract for this improvement, the Village of Mount Prospect will
pay to the IDOT in a lump sum from any funds allotted to the Village an amount equal to 80% of its
obligation incurred under this Agreement, and will pay to said IDOT the remainder of the obligation in a lump
sum, upon completion of the project based on final costs.
SECTION THREE: That the Village of Mount Prospect agrees to pass a supplemental resolution to provide
any necessary funds for its share of the cost of this improvement if the amount appropriated herein proves
to be insufficient, to cover said cost.
SECTION FOUR: That this Resolution shall be in full force and effect from and after its passage and
approval in the manner provided by law.
AYES:
NAYS:
ABSENT:
PASSED and APPROVED this 16th day of May, 2017
Arlene A. Juracek
Mayor
ATTEST:
Karen Agoranos
Village Clerk
FAP Route 344
IL Route 83
South of Palatine Road to US 14(Northwest Highway)
State Section: (97130192) RS -2
Cook County
Job No.: C-91-427-16
Contract No.: 62D09
JN -117-029
AGREEMENT
This Agreement entered into this day of , 2017 A.D
by and between the STATE OF ILLINOIS, acting by and through its DEPARTMENT
OF TRANSPORTATION, hereinafter called the STATE, and the VILLAGE OF
MOUNT PROSPECT of the State of Illinois, hereinafter called the VILLAGE.
WITNESSETH:
WHEREAS, the STATE in order to facilitate the free flow of traffic and ensure safety
to the motoring public, is desirous of improving approximately 3.06 miles of IL Route
83 from south of Palatine Road to US 14 (Northwest Highway), STATE Job No.: C-
91-427-16, State Contract Number 62D09, STATE Section (97B&3192)RS-2 by
resurfacing and improving Pedestrian Ramps as follows:
This is a resurfacing project in which the work to be performed includes hot —mix
asphalt surface removal, pavement patching, resurfacing with hot -mix asphalt,
concrete curb and gutter removal and replacement, handhole and drainage structure
adjustments, cleaning of drainage structures, placement of thermoplastic pavement
markings, sidewalk curb ramp improvements and by performing all other work
necessary to complete the improvement in accordance with the approved plans and
specifications; and
WHEREAS, the VILLAGE requests that the STATE include in its contract 120 sq
ft. of Detectable Warnings (Special) at the intersections of IL Rte 83 with Busse Ave.
and with Central Road; and
WHEREAS, the STATE has agreed to the VILLAGE's request; and
WHEREAS, the VILLAGE is desirous of said improvement in that same will be of
immediate benefit to the VILLAGE residents and permanent in nature;
NOW, THEREFORE, in consideration of the mutual covenants contained herein, the
parties hereto agree as follows:
1. The STATE agrees to make the surveys, obtain all necessary rights of way,
prepare plans and specifications, receive bids and award the contract, furnish
engineering inspection during construction and cause the improvement to be built
in accordance with the approved plans, specifications and contract.
2. The STATE agrees to pay for all right of way, construction and engineering cost
subject to reimbursement by the VILLAGE as hereinafter stipulated.
3. It is mutually agreed by and between the parties hereto that the estimated cost
and cost proration for this improvement is as shown on Exhibit A attached hereto
and made a part hereof.
4. The VILLAGE has passed a resolution appropriating sufficient funds to pay its
share of the cost for this improvement, a copy of which is attached hereto as
Exhibit B and made a part hereof.
The VILLAGE agrees that upon award of the contract for this improvement, the
VILLAGE will pay to the STATE, in a lump sum from any funds allotted to the
VILLAGE, an amount equal to 80% of its obligation incurred under this
AGREEMENT, and will pay to said STATE the remainder of the obligation
(including any non -participating costs on FA Projects) in a lump sum, upon
completion of the project based upon final costs.
5. The VILLAGE further agrees to pass a supplemental resolution to provide
necessary funds for its share of the cost of this improvement if the amount
appropriated in Exhibit B proves to be insufficient, to cover said cost.
6. The VILLAGE has adopted and will put into effect an appropriate ordinance, prior
to the STATE's advertising for the proposed work to be performed hereunder, or
shall continue to enforce an existing ordinance, requiring that parking be
prohibited within the limits of this improvement, a copy of which is attached
hereto as Exhibit C, and will in the future prohibit parking at such locations on or
immediately adjacent to this improvement as may be determined necessary by
the STATE from traffic capacity studies.
7. The VILLAGE agrees not to permit driveway entrance openings to be made in
the curb, as constructed, or the construction of additional entrances, private or
commercial, along Illinois Route 83 without the consent of the STATE.
8. The VILLAGE shall exercise its franchise rights to cause private utilities to be
relocated, if required, at no expense to the STATE.
9. The VILLAGE agrees to cause its utilities installed on right of way after said right
of way was acquired by the STATE or installed within the limits of a roadway
after the said roadway's jurisdiction was assumed by the STATE, to be relocated
and/or adjusted, if required, at no expense to the STATE.
10. All VILLAGE owned utilities, on STATE right of way within the limits of this
improvement, which are to be relocated/adjusted under the terms of this
Agreement, will be relocated/adjusted in accordance with the applicable portions
of the "Accommodation of Utilities of Right of Way of the Illinois State Highway
System." (92 III. Adm. Code 530).
11. The VILLAGE agrees to obtain from the STATE an approved permit for any
VILLAGE owned utility relocated/adjusted as part of this improvement, and shall
abide by all conditions set forth therein.
12. Upon final field inspection of the improvement and so long as IL Route 83 is used
as a STATE Highway, the STATE agrees to maintain or cause to be maintained
the median, the through traffic lanes, the left -turn lanes and right turn lanes, and
the curb and gutter, stabilized shoulders and ditches adjacent to those traffic
lanes and turn lanes.
13. Upon final field inspection of the improvement, the VILLAGE agrees to maintain
or cause to be maintained those portions of the improvement which are not
maintained by the STATE, including new and existing sidewalks, new curb ramp
improvements and special detectable warnings, parkways, crosswalk and
stopline markings and VILLAGE owned utilities including appurtenances thereto.
14. The VILLAGE further agrees to continue its existing maintenance responsibilities
on all side road approaches under its jurisdiction, including all left and right turn
lanes on said side road approaches, up to the through edge of pavement of IL
Route 83. Drainage facilities, if any, at the aforementioned side roads located
within the STATE right-of-way shall be the joint maintenance responsibility of the
STATE and the VILLAGE unless there is an agreement specifying different
responsibilities.
15. The VILLAGE has adopted a resolution, will send a letter, or sign the Plan
Approval page which is part of this document, prior to the STATE advertising for
the work to be performed hereunder, approving the plans and specifications as
prepared.
16. Under penalties of perjury, the VILLAGE certifies that its correct Federal Tax
Identification number is 36-6006011 and it is doing business as a
GOVERNMENTAL ENTITY, whose mailing address is:
Village of Mount Prospect
1700 West Central Road
Mount Prospect, Illinois 60056
Obligations of the STATE and the VILLAGE will cease immediately without penalty or
further payment being required if, in any fiscal year, the Illinois General Assembly or Federal
funding source fails to appropriate or otherwise make available funds for this contract.
This AGREEMENT and the covenants contained herein shall be null and void in the
event the contract covering the construction work contemplated herein is not awarded within
the three years subsequent to execution of the agreement.
This Agreement shall be binding upon and to the benefit of the parties hereto, their
successors and assigns.
Attest:
Village Clerk
(SEAL)
VILLAGE OF MOUNT PROSPECT
By:
(Signature)
By:
(Print or Type)
Title:
Date:
STATE OF ILLINOIS
DEPARTMENT OF TRANSPORTATION
go
Date:
Anthony J. Quigley, P.E.
Region One Engineer
Job No.: C-91-427-16
Agreement No.: JN -117-029
_► _"-.7•
WHEREAS, in order to facilitate the improvement of FAP Route 344, known as IL
Route 83, State Section (97B&3192)RS-2, the VILLAGE agrees to that portion of the
plans and specifications relative to the VILLAGE's financial and maintenance
obligations described herein, prior to the STATE's advertising for the aforedescribed
proposed improvement.
Approved
Title
Date
Exhibit B
FUNDING RESOLUTION
WHEREAS, the Village of Mount Prospect (VILLAGE) has entered into an AGREEMENT
with the State of Illinois (STATE) for the improvement of FAP Route 344, known as IL Route
83, State Section (97B&3192)RS-2, south of Palatine Road to US 14 (Northwest Highway); and
WHEREAS, in compliance with the aforementioned AGREEMENT, it is necessary for
the VILLAGE to appropriate sufficient funds to pay its share of the cost of said improvement.
NOW THEREFORE, BE IT RESOLVED, that there is hereby appropriated the sum of
Two Thousand Seventy Dollars ($2,070.00) or so much thereof as may be necessary, from any
money now or hereinafter allotted to the VILLAGE to pay its share of the cost of this
improvement as provided in the AGREEMENT; and
BE IT FURTHER RESOLVED, that upon award of the contract for this improvement, the
VILLAGE will pay to the STATE in a lump sum from any funds allotted to the VILLAGE an
amount equal to 80% of its obligation incurred under this AGREEMENT, and will pay to said
STATE the remainder of the obligation in a lump sum, upon completion of the project based on
final costs.
BE IT FURTHER RESOLVED, that the VILLAGE agrees to pass a supplemental
resolution to provide any necessary funds for its share of the cost of this improvement if the
amount appropriated herein proves to be insufficient, to cover said cost.
STATE OF ILLINOIS)
COUNTY OF COOK)
Village Clerk in and for the Village of Mount Prospect hereby
certify the foregoing to be a true perfect and complete copy of the resolution adopted by the
Village Board at a meeting on , 2017 A.D.
IN TESTIMONY WHEREOF, I have hereunto set my hand seal this day of
2017 A.D.
(SEAL)
Village Clerk
EXHIBIT C
ORDINANCE NO.
AN ORDINANCE RESTRICTING PARKING ALONG
IL ROUTE 83 SOUTH OF PALATINE ROAD TO US 14(NORTHWEST HIGHWAY) WITHIN THE VILLAGE
OF MOUNT PROSPECT
WHEREAS, the State of Illinois acting by and through its Department of Transportation is desirous of
improving IL Route 83 south of Palatine Road to US 14(Northwest Highway) in Cook County; and
WHEREAS, a portion of this project runs through the Village of MOUNT PROSPECT; and
WHEREAS, in order to facilitate the free flow of traffic and ensure safety to the motoring public, the
Village of MOUNT PROSPECT determines that the parking along IL Route 83 south of Palatine Road to US
14(Northwest Highway) shall be prohibited.
BE IT ORDAINED BY THE VILLAGE BOARD OF THE VILLAGE OF MOUNT PROSPECT, COUNTY
OF COOK, STATE OF ILLINOIS, as follows:
Section 1. That parking shall not be permitted along IL Route 83 south of Palatine Road to US
14(Northwest Highway) within the corporate limits of the Village of MOUNT PROSPECT included in said
improvement.
Section 2. That the Village Board of the Village of MOUNT PROSPECT will prohibit future parking at
such locations on or immediately adjacent to IL Route 83 south of Palatine Road to US 14 (Northwest
Highway) as may be determined and directed by the State of Illinois to be necessary to ensure the free flow of
traffic and safety to the motoring public.
Section 3. The Village Clerk is hereby authorized and directed to attach a copy of this Ordinance to
the agreement dated 2017 by and between the State of Illinois and the Village of Mount
Prospect.
Section 4. That this Ordinance shall be in full force and effect from and after its passage and approval
according to law.
ADOPTED BY THE VILLAGE BOARD OF THE VILLAGE OF MOUNT PROSPECT, COUNTY OF
COOK, STATE OF ILLINOIS, this day of 12017.
VOTE:
AYES
NAYES:
ABSENT:
APPROVED BY ME THIS
DAY OF 2017
VILLAGE PRESIDENT
ATTEST: