HomeMy WebLinkAbout06/02/2015 Prospect Meadows Drainage ProjectMount Prospect Public Works Department L $/ INTEROFFICE MEMORANDUM TO: ACTING VILLAGE MANAGER DAVID STRAHL FROM: VILLAGE ENGINEER DATE: MAY 28, 2015 SUBJECT: PROSPECT MEADOWS DRAINAGE PROJECT (CONTRACT AWARD NOT TO EXCEED $334,120.00) Background The Prospect Meadows Subdivision is bounded by Forest Avenue to the west, Kensington Road to the south, Elmhurst Avenue to the east and Rand Road to the north. The subdivision does not have storm sewers and relies on ditches for storm water drainage. Inconsistencies in the flow lines of several of the ditches has created local summits that reduce the capacity of the ditches and low areas that collect and hold water long after the rain has ended. The Prospect Meadows Drainage Project reestablishes a consistent flow line along Bob -O -Link Road, and sections of Prospect Manor Avenue to both improve the drainage of the ditches. Bid Results A Notice to Bidders was published in a local newspaper as required and invitations were sent to contractors familiar with this program. At 1:00 P.M. on May 26, 2015 sealed bids were publicly opened and read aloud. Eight (8) contractors submitted bids for this project. The bids ranged from a low of $303,745.00 by Canyon Contracting, Inc. to a high of $617,440.00 by Kovilic Construction Co., Inc. The Engineer's estimate for the project was $362,050.00. Each of the bidders submitted a bid bond in the amount of 10% of the total bid as required in the bid proposal packet. All bids were checked for their accuracy. No errors were found. All bidders correctly signed their bids and bid bonds. Below is a summary of the bids: Bidders Total Bid Canyon Contracting, Inc. $303,745.00 Patnick Construction, Inc. $347,745.00 Vian Construction Co., Inc. $456,735.00 Copenhaver Construction $467,035.00 Maneval Construction Co., Inc. $509,410.00 Berger Excavating Contractors, Inc. $515,450.00 Al -amp Concrete Contractors, Inc. $520,875.00 Kovilic Construction Co., Inc. $617,440.00 Engineer's Estimate $362,050.00 Page 2 of 2 Prospect Meadows Drainage Project ($334.120.00) May 28, 2015 Discussion The low bidder, Canyon Contracting, Inc., has not completed any prior work for the Village but references contacted for work done within other municipalities said their work had been satisfactory. Canyon Contracting is also a subcontractor for the Levee 37 project and received favorable recommendations from the U.S. Army Corps of Engineers and the general contractor. Staff recommends including a 10% contingency in the project award to allow for quantity variances and unanticipated underground conflicts. For this project, a 10% contingency added to the lowest bid would result in a total contract award of $334,120.00. (Base Bid: $303,745.00 + Contingency: $30,375.00 = Total Recommended Award: $334,120.00) Recommendation I recommend the low bidder, Canyon Contracting, Inc. of Spring Grove, IL, be awarded the contract for the Prospect Meadows Drainage Project in the amount not to exceed $334,120.00. Please include this item on the June 2nd Village Board Meetina Aaenda. I concur with the above reco mendation. _� Director of ubl orks Sean P. Dorsey cc: Village Clerk Lisa Angell H:\Engineering\Drainage\Prospect Meadows Drainage Project -Ph 1\Board Recommendation.doc