HomeMy WebLinkAbout6. Village Manager's Report 04/08/2015Mount Prospect Public Works Department
LL $/ INTEROFFICE MEMORANDUM
TO: ACTING VILLAGE MANAGER DAVID STRAHL
FROM: VILLAGE ENGINEER
DATE: MARCH 30, 2015
SUBJECT: NORTHWEST HIGHWAY STREETSCAPE PROJECT
CONSTRUCTION ENGINEERING SERVICES AGREEMENT ($136,541)
BACKGROUND
The Village is seeking to have streetscape improvements made to Northwest Highway
from Maple Street to Louis Street, George Street to Albert Street and Forest Avenue to
Fairview Avenue.
The project was approved for Illinois Transportation Enhancement Program (ITEP)
funding for an 80/20 split of the construction costs. The Village is responsible for the
Engineering costs. The Design Engineering is complete and the bids were opened by
IDOT on January 30, 2015. IDOT is preparing to award the contract to Path
Construction Co. in the amount of $1,268,950. The Village is responsible for the Phase
III Construction Engineering cost which is estimated to be $136,541.
DISCUSSION
With the approaching start of construction the Village must enter into a CONSTRUCTION
ENGINEERING SERVICES AGREEMENT with a consulting engineer. Prior to awarding the Phase
I, Project Preliminary Engineering Services and Phase II, Design Engineering Services
contracts the Village requested a statement of qualifications from six consulting
engineering firms. After reviewing and evaluating the qualifications, the Village selected
to negotiate an agreement with the first ranked consultant, Hancock Engineering Co. and
the Village board approved the contract on June 18, 2013. Their Phase I and Phase II
work has been satisfactory and because of their specific knowledge about this project, it
is my recommendation that the Phase III Construction Engineering contract be awarded
to Hancock Engineering Co., in the amount not to exceed $136,541.
The proposed Construction Engineering cost of $136,541 represents 10.7% of the bid
construction cost of $1,268,950. This is in line with what we would expect and is very
similar to the Kensington Road Improvement Project which had a 10.6% ratio. Also,
based on the estimated 1,228 hours necessary to complete the Phase III Engineering
work, the average cost per hour of $103.17 is also reasonable.
Page 2
Northwest Highway Streetscape Project
March 30, 2015
RECOMMENDATION
It is my recommendation that the proposal submitted by Hancock Engineering Company
of Westchester, Illinois for Phase III Engineering services be accepted with a not to exceed
amount of $136,541. There are sufficient funds in the 2015 Budget for this contract.
e lbecker
1 concur with the above recommendation.
,
Jacrii H. Leib, Deputy Director of Public Works
H:\Engineering\Agencies\ITEP\NW Hwy Streetscape\Phase III\Consultant Rec Mm
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
TO: ACTING VILLAGE MANAGER DAVID STRAHL
FROM: SUPERINTENDENT OF STREETS & BUILDINGS
DATE: MARCH 31, 2015
SUBJECT: 2015-2016 BRICK PAVER SEALING CONTRACT
(NOT TO EXCEED $75,000)
BACKGROUND
This contract is for sealing of brick pavers installed throughout the Village. The sealing of brick
pavers is necessary to keep the brick color from fading and to seal out moisture, dirt, oil and
paint that might otherwise get imbedded into the brick. Sealing also extends the life expectancy
of the brick walk and facilitates cleaning. The life expectancy for the sealant is five (5) to seven
(7) years and currently all brick walks are scheduled to be sealed on a six year cycle. The
proposed agreement is for a two (2) year term concluding at the end of 2016. Bidders were
asked to submit pricing for 2015 and 2016.
BID RESULTS
Sealed bids were opened at 1:00 P.M. on March 16, 2015 for the proposed 2015-2016 brick
paver sealing program. Bid prices were based on estimated quantities of 50,000 square feet.
Seven invitational bids were mailed, and a bid notice was placed in the local paper. Eight
contractors attended the mandatory pre-bid meeting.
One bid was received with result as follows:
Bidders
1 2015
2016
Midwest Brickpaving, Inc.
1 $57,000.00
$57,000.00
DISCUSSION
The only bid received was from Midwest Brickpaving, Inc. Midwest Brickpaving has held the
brick sealing contract the past two years, in addition Midwest Brickpaving, Inc. has previously
completed repair and installation projects for the Village. All work has been satisfactorily
completed on time and within budget. Submitted references were checked and responded with
positive recommendations and stated they would rehire Midwest Brickpaving for any future
projects.
Page 2 of 2
2015-2016 Brick Paver Sealing Contract (Not to Exceed $75,000)
March 31, 2015
The price submitted by Midwest Brickpaving is 4.6% higher than the 2013 awarded bid price
(see table below). The 4.6% increase is reflective of the CPI the last two years. In addition, the
2015 bid price of $57,000 is approximately $20,000 lower than the second lowest bid received
in 2013 (see table below). Taking these factors into consideration the Ione bid received from
Midwest Brickpaving represents a very competitive bid price.
Bidders
2015 Bid Results
2013 Bid Results
Midwest Brickpaving, Inc.
$57,000.00
$54,500.00
LPS Pavement Company
No Bid
$77,500.00
Lester's Material Service, Inc.
No Bid
$126,500.00
Co enhaver Construction
No Bid
$127,500.00
The Village budget limit for this project is $75,000. This year's bid unit pricing is less than
anticipated. Therefore, I recommend that we take advantage of the lower than anticipated unit
prices and add additional work up to the budgeted amount of $75,000
RECOMMENDATION
I recommend award of a two (2) year contract to Midwest Brick Paving, Inc. Year one (1) will be
in an amount not to exceed $75,000. Year two (2) will be in an amount not to exceed the
appropriated budget in 2016.
Paul Bures
Superintendent of Streets & Buildings
I concur:
/J on H. Leib
eputy Director of Public Works
c: Director of Public Works Sean P. Dorsey
Deputy Director of Public Works Jason Leib
file
Prospect
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
TO: ACTING VILLAGE MANAGER DAVID STRAHL
FROM: SUPERINTENDENT OF STREETS & BUILDINGS
DATE: MARCH 31, 2015
SUBJECT: ACCEPT BID FOR 2015 CONCRETE RESTORATION CONTRACT
(NOT TO EXCEED $61,200)
BACKGROUND
This contract provides for concrete restoration following emergency repairs on Village -
owned and privately -owned water and sewer lines installed in the Village rights of way.
Concrete restoration of driveways, curbs, and sidewalks is necessary throughout the
year following emergency repair excavations. This contract provides for monthly
services, thus reducing the time our residents are waiting for restoration.
This contract is for a one (1) year agreement.
BID RESULTS
Sealed bids were publicly opened at 1:00 P.M. on March 16, 2015 for a proposed
concrete restoration contract. Bid prices were based on estimated quantities. Eight (8)
invitational bids were mailed, and a bid notice was placed in the local paper. Four (4)
companies attended the mandatory pre-bid meeting.
Three (3) bids were received, and the results are as follows:
Bidder
Bid Price
A Lamp Concrete Contractors Inc.
$61,200.00
Strada Construction Co.
$63,075.00
Globe Construction
$76,055.00
Page 2 of 2
Accept Bid for 2015 Concrete Restoration Contract (Not to Exceed $61,200)
March 25, 2015
DISCUSSION
The apparent low bidder A Lamp Concrete Contractors, Inc. has previously worked for
the Village. A Lamp Concrete Contractors, Inc. has performed street resurfacing,
concrete restoration and is currently completing the Isabella drainage improvements.
All previous work completed by A Lamp was satisfactory. Supplied references were
contacted and said that A Lamp Concrete Contractors, Inc. completed their contracts
performing satisfactorily and that they would hire then, again.
RECOMMENDATION
I recommend the Village Board award a one (1) year contract to the lowest qualified
bidder, A Lamp Concrete Contractors, Inc. in an amount not to exceed $61,200.
Sufficient funds exist in the current budget.
Paul Bures
Superintendent of Streets & Buildings
I concur:
Jason H. Leib
Deputy Director of Public Works
PB/pb
c: Director of Public Works Sean P. Dorsey
Deputy Director of Public Works Jason Leib
File
Village of Mount Prospect oust prosp(
Community Development Department
MEMORANDUM
TO: DAVID J. STRAHL, ACTING VILLAGE MANAGER vg/04
FROM: NELLIE S. BECKNER, SENIOR PLANNER
DATE: MARCH 30, 2015
SUBJECT: DOWNTOWN WAYFINDING SIGNAGE PROGRAM — PHASE I: DESIGN
PROCESS
BACKGROUND
The Downtown Implementation Plan includes a recommendation to implement a wayfinding signage
program. Wayfinding, such as directional signs, information kiosks, and gateway signage is discussed
and would be scaled to direct both vehicular and pedestrian traffic to downtown services, shops,
parking and transit. The plan proposes sign locations throughout the downtown and denotes Prospect
Avenue as a potential special district that could be highlighted through the wayfinding signage program.
REQUEST FOR PROPOSALS
On February 27, 2015 the Community Development Department posted a Request for Proposals (RFP)
to address the Phase I Design Process of the Wayfinding Signage Program implementation. The
Community Development Department has budgeted $50,000 for this phase, which includes:
• An assessment/analysis of pedestrian and auto -oriented wayfinding needs.
• A unified design for all sign types [pole -mounted directional wayfinding, information kiosks, and
gateway signs], the final deliverable resulting in bid -ready drawings for accurate cost
estimation.
• Location and wording for each proposed sign.
The deadline for the RFP was March 13, 2015. The department received 6 proposals:
Consultant....._���_..........�. C__.
. ost
Media Objectives (Chicago, IL) $ 37,842
Studio Graphiqueµµ(Cleveland, OH $ 4 _.�...........__.
_ ( ) 1,000
...The Lakota_Group (Chicago, IL) $ 42,420
Corbin Design . ��....�.��.........
(Traverse City, MI) $ 49,910
Teska Associates ) (Evanston, IL _$.�...5..�.....�_..
1,590
Merje (West Chester PA _ .......57�,5�.�
$ 400
PROJECT TIMELINE
The design process is interactive and will last approximately 12 weeks:
• A steering committee will be established by staff, with representatives from the Downtown
Merchants Association, local developers and business owners.
\\,f1\vh I kWplan\n ,,m 12015\wayfinding signs - comullut scicclioo3-30-15 docs
Wayfinding Signage Program — Design Process
March 30, 2015
Page 2
• The consultant will meet with the steering committee to identify points -of -interest and to discuss
design options.
• The consultant will conduct on-site analysis related to existing signage and traffic patterns, and
then draft a report of their analysis and recommendations for steering committee review.
• Two preliminary sign designs with proposed locations will be drafted by the consultant and
presented to the steering committee and board/public for review and further refinement.
• A draft design document including cost estimates for one sign design will be prepared by the
consultant. This document will be detailed and may be used for accurate bidding to kick-off
Phase II — Fabrication and Installation of the wayfinding signage program.
CONCLUSION
Media Objectives addressed all of the department's requested elements for the design portion of the
wayfinding signage program in the RFP at the lowest cost. Staff recommends retaining Media
Objectives to complete the Design Phase of the downtown Wayfinding Signage Program. Sufficient
funds are available in account 022.40.90.00.0.710.636.028 on page 313 of the Budget.
Please forward this memorandum and attachments to the Village Board for their review at their April 8,
2015 meeting. Staff will be present to answer any questions related to this matter.
I concur with the above recommendation.
William J. Cooney, Jr.,ICP
Director of Community evelopment
UflWh t hedStpl:m4nemus120 t5twnyfinding Mg.. - emlln.I selection 3-30-15 do-