HomeMy WebLinkAbout12/16/2014 Isabella Area Sewer ImprovementsProspect
TO:
FROM:
DATE:
SUBJ:
Background
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
ACTING VILLAGE MANAGER DAVID STRAHL
DIRECTOR OF PUBLIC WORKS
DECEMBER 11, 2014
BID RESULTS FOR ISABELLA AREA SEWER IMPROVEMENTS
($8,863,088)
The 2011 Comprehensive Flood Study Report identified several sewer improvement projects for
areas subjected to severe, recurrent, and geographically concentrated flooding.
The first phase of these improvements (Phase 1 Improvements) involved storm sewer
improvements on SeeGwun Avenue, NaWaTa Avenue, Lawrence Lane, Hatlen Avenue, Hatlen
Court, Busse Road, Michael Street, Verde Drive, Bonita Avenue, and Audrey Lane. The Phase
1 Improvements also included ditch regrading and culvert replacement work in the Golfview
Estates residential subdivision. This work was facilitated by $2.5 million in short-term debt
issued in 2012. All of this work was designed and constructed in 2013.
The second, and final, phase of public sector work identified by the 2011 Comprehensive Flood
Study is the construction of a relief sewer system in the Isabella Street residential area. The
proposed scope of work for this project includes the installation of approximately 6,600 linear
feet of relief sewer ranging in size from 15" to 84" (and appurtenances) to provide a 25 -year
recurrence interval level of protection for approximately 800 single-family homes. Funding for
this work has been facilitated by $10 million in general obligation bond debt.
Bid Results
Plans and bid documents for this project were prepared by Burns & McDonnell consulting
engineers of Downers Grove, Illinois. Bids were let on October 17, 2014. A public notice was
placed in a local newspaper. Thirteen (13) sewer construction firms picked up bid documents
and eight (8) attended a mandatory pre-bid meeting on November 3, 2014. Bids were opened
and read aloud on November 24, 2014. Six (6) bids were received:
Bidder Bid Amount
A Lamp Concrete Contractors
$8,057,352.09
Martam Construction, Inc.
$9,057,012.40
Glenbrook Excavating & Concrete, Inc.
$9,290,734.73
John Ned Construction Company
$10,158,791.00
Bolder Contractors, Inc.
$11,111,193.27
Berger Excavating Contractors, Inc.
$12,563,144.73
Page 2 of 4
Bid Results for Isabella Area Sewer Improvements ($8,863,088)
December 11, 2014
The engineer's estimate of probable construction cost for this project is $10,052,725.
Discussion
All bids were properly signed, accompanied by appropriate bid bonds, and responsive to the bid
documents. All six (6) bidders attended the mandatory pre-bid meeting.
The apparent low -bidder is A Lamp Concrete Contractors of Schaumburg, Illinois (ALamp).
ALamp has performed work for the Village in the past. In 2009, ALamp was the general
contractor for the $2.7 million street resurfacing program. The paving work was subcontracted
to Arrow Road of Mount Prospect. However, ALamp was responsible for sub -base preparation,
concrete flatwork, structure adjustments, small -diameter storm sewer work, and overall project
management. ALamp's performance was acceptable. Work was completed on time and below
the project award amount.
Review of ALamp's bid submittal revealed several concerns about their ability to complete the
project. Among these concerns were disparaging references about project close-out,
housekeeping, and crew turnover; a lack of experience installing 84" diameter (or larger) pipe;
inordinately low bid prices for trench backfill, junction chamber reconstruction work, by-pass
pumping, and overall project cost; as well as unbalanced prices for mobilization and traffic
control.
On December 4, 2014, staff and design engineer Burns & McDonnell met with ALamp
representatives to discuss these concerns. These matters were disposed as follows:
Project Close-out, Housekeeping, and Crew Turnover. ALamp acknowledged these
issues and proposed they would avoid potential problems by permanently assigning their
best underground construction crew to this project. They also identified the project
foreman they planned to assign to this project and provided specific work references for
his crews. All references were acceptable with respect to timeliness, project close-out,
and housekeeping.
Lack of Experience Installing 84" Diameter (or larger) Pipe. ALamp provided acceptable
references for the installation of 60" diameter pipe and 48" diameter pipe. However,
approximately 30% of the work in this project involves the installation of larger pipe.
Notably, the work involves installing 1,000 feet of 72" diameter sewers and 2,000 feet of
84" diameter sewers. ALamp acknowledged this deficiency but advised that they
presently own and can adeptly operate the trench boxes, large backhoes, and other
equipment necessary to safely install the large pipe.
Inordinately Low Bid Price for Trench Backfill. ALamp's bid price for trench backfill is
approximately half the cost of other bidders. ALamp explained that they own a concrete
recycling facility and have the capability to manufacture their own trench backfill. They
Page 3 of 4
Bid Results for Isabella Area Sewer Improvements ($8,863,088)
December 11, 2014
further opined that this resource differentiates them from the other bidders and facilitates
lower costs for trench backfill.
Inordinately Low Bid Price for Junction Chamber Work. The project involves structural
concrete construction work on sewer junction chambers. ALamp's prices for this work
seem low considering the scope of work involved. Particularly, staff was concerned that
ALamp might not have properly assessed the trench shoring requirements and might not
fully appreciate the difficulties performing partial concrete demolition work on active
sewer structures. ALamp responded that they plan to subcontract this work to a
structural concrete contractor with relevant experience in these niche tasks. The
subcontractor is known to Burns & McDonnell as competent in this work. In addition,
staff reminded ALamp that shoring designs must be signed and sealed by a structural
engineer; they are also subject to Village review.
Inordinately Low Bid Price for Sewer By -Pass Pumping. An important component of the
project is facilitation of by-pass pumping that will enable construction on live combination
sewers. ALamp's bid price for this work is substantially lower than the costs of other
bidders and the engineer's estimate. ALamp acknowledged that the by-pass pumping
plan must accommodate both low and peak flows without surcharging. They further
explained that they own a variety of resources and were confident that they could
provide a by-pass pumping plan that will satisfy Village requirements.
Overall Project Cost is Exceptionally Low. ALamp's bid is approximately $1 million lower
than the second -lowest bidder and almost $2 million lower than the engineer's estimate
and median bid. ALamp stated that they can construct the improvements at the bid price
and within the contract time without additional compensation. They also opined that
vertical integration of key project components including trucking, traffic control, and
trench backfill along with advantageous supplier relationships allow them to be cost
competitive on this project.
Mobilization and Traffic Control Prices are Unbalanced. ALamp's bid prices for
mobilization and traffic control constitute approximately 25% of the project cost. This
allocation of costs is unusual and could be construed as a means to be compensated at
a rate that exceeds value added. Staff advised ALamp that these pay items would be
paid pursuant to Illinois Department of Transportation (IDOT) standard procedures. As a
consequence, much of the money attributed to these pay items will not be eligible for
payout until the end of the project. ALamp acknowledged understanding of the Village's
position on this matter.
As a result of this meeting, staff is satisfied that aforementioned concerns can be effectively
managed. It is also the opinion of staff that ALamp can construct the improvements at the price
quoted and within the time frame specified in the bid documents.
Page 4 of 4
Bid Results for Isabella Area Sewer Improvements ($8,863,088)
December 11, 2014
Staff also recommends that the award for this project include a 10% contingency to
accommodate quantity variances and unforeseen conditions commonly associated with
underground work. The total recommended project award is $8,863,088 ($8,057,352.09 base
bid + $805,735.91 contingency).
Recommendation
I recommend that the Village Board accept the lowest cost bid for the Isabella Area Sewer
Improvements as submitted by Al -amp Concrete Contractors, Inc., of Schaumburg, Illinois in an
amount not to exceed $8,863,088. Sufficient funds for this propo d expenditure exist in the
current budget.
can P. Dorsey
Cc: Director of Finance David Erb
Deputy Director of Public Works Jason Leib
Water/Sewer Superintendent Matt Overeem
Streets/Buildings Superintendent Paul Bures
Village Engineer Jeff Wulbecker
Administrative Superintendent Kristina Jakupovic
Traffic Engineer Matt Lawrie
Project Engineer Joel Michalik
File