Village of Mount Prospect
Mount Prospect, Illinois
INTEROFFICE MEMORANDUM
TO: DAVID STRAHL, ACTING VILLAGE MANAGER
VS
FROM: FINANCE DIRECTOR
12-
DATE: DECEMBER 5, 2014
SUBJECT: 2015 PROPERTY AND WORKERS COMPENSATION INSURANCE PROGRAM
PURPOSE:
To present a recommendation for the property and workers compensation insurance program for the
policy year beginning January 1, 2015 and ending December 31, 2015.
DISCUSSION:
The Village's current property and workers compensation insurance policies are set to expire on
December 31, 2014. With the assistance of the Village's insurance consultant, staff sought quotes with
the existing broker and insurance companies to secure coverage for 2015. There remains just a single
competitive insurer for the excess workers compensation - Safety National while Federal Insurance
(Chubb) has been the most competitive on cost and coverage for property. The following is a brief
summary of our expiring insurance program, an analysis of the proposal received, and a summary of
the insurance package being recommended by staff and its consultant.
Expiring Program
Attachment I provides a listing of the current schedule of insurance in force, showing the type of
coverage, the carrier, policy limits, and the broker of record.
Village buildings and vehicles were insured this past year by Federal Insurance (Chubb) Company.
Property values on which the premium was based totaled $95,296,056. A $25,000 deductible is in
place for this coverage. The annual premium was $101,750. The broker offering the coverage was
Arthur J. Gallagher and Co.
Excess workers compensation coverage was purchased from Safety National, which insured the Village
for individual claims in excess of $600,000. There is a $1 million aggregate limit for worker
compensation claims. The annual premium was $81,465. The broker again was Arthur J. Gallagher
and Co.
Proposal Received
Nugent Consulting Group assisted the Village in securing proposals from our current broker and
underwriters. Attachment II presents a summary of the 2015 insurance renewal for the upcoming policy
period. A breakdown of premium by coverage type for policy year 2013 and 2014 is also included.
The renewal quote for property coverage increased $2,865, or 2.8% from the prior year and totals
$104,615. Insurable values during the same period increased 2.9%. The renewal quote for excess
workers compensation coverage increased $6,043 or 7.4% from the prior year and totals $87,508. The
self-insured retention level did not change from the prior year and remains at $600,000. The total for all
premiums and commissions for selected coverage levels is $204,505, an increase of 4.55% from the
2014 premium.
Property and Workers' Compensation Insurance Program
December 5, 2014
Page 2
The insurance companies being recommended are very sound financially and have an excellent claims
payment history. Federal Insurance is rated A++, XV (Superior) by A.M. Best, a recognized insurance
company rating service. Safety National Casualty Corp. is rated A, IX (Excellent).
RECOMMENDATION:
It is recommended the Village purchase property and excess workers compensation insurance from
Arthur J. Gallagher and Co. with premiums and broker's fees not to exceed $204,505.
David O. Erb
Finance Director
DOE/
Attachments
I:\Insurance\Renewals\2015\2015 Renewal - Property and WC.docx
Attachment I
VILLAGE OF MOUNT PROSPECT
SCHEDULE OF INSURANCE IN FORCE
December 31, 2014
Type of Coverage
Carrier
Deductible/
Self -Insured
Retention
Specific
Excess
Limit
Aggregate
Excess
Limit
Expiration
Date
Policy
Number
Broker
Premium
Property & Inland Marine
Federal Insurance / Chubb
$25,000
$95,296,056
none
01/01/15
35826710
Arthur J. Gallagher
$101,750
Workers' Compensation
Safety National Insurance Co.
$600,000
Statutory
$1,000,000
01/01/15
SP 4047829
Arthur J Gallagher
$81,465
Self -Insured Liability Program
General Liability
N/A
$2,000,000
$0
$0
$0
Auto Liability
N/A
$2,000,000
$0
$0
$0
Employment Practices Liability
N/A
$2,000,000
$0
$0
$0
Police Professional Liability
N/A
$2,000,000
$0
$0
$0
Public Officials Liability
N/A
$2,000,000
$0
$0
$0
(Errors and Omissions)
Excess Liability
High-level Excess Liability Pool
$2,000,000
$13,000,000
$13,000,000
04/30/18
n/a
n/a
$82,282
Fiduciary Liability - Police Pension
Federal Insurance / Chubb
$25,000
$5,000,000
$5,000,000
08/01/15
8158-5499
Arthur J. Gallagher
$11,960
Fiduciary Liability - Fire Pension
Federal Insurance / Chubb
$25,000
$5,000,000
$5,000,000
08/01/15
8169-8992
Arthur J. Gallagher
$13,100
Public Employee Dishonesty
Travelers
$5,000
$500,000
none
05/01/15
105779765
Arthur J. Gallagher
$2,678
Depositors Forgery
Travelers
$1,000
$100,000
none
05/01/15
105779765
Arthur J Gallagher
Incl. in above
Public Officials Bond - President
Liberty Mutual
$0
$100,000
$100,000
05/01/15
404009933
Arthur J. Gallagher
$100
Public Officials Bond - Manager
Liberty Mutual
$0
$100,000
$100,000
05/01/15
404009934
Arthur J Gallagher
$100
Public Officials Bond - Treasurer
Liberty Mutual
$0
$250,000
$250,000
05/01/15
404009932
Arthur J. Gallagher
$250
Contingent Tax Interruption
Federal Insurance / Chubb
$25,000
$9,000,000
$9,000,000
01/01/15
35826710
Arthur J. Gallagher
Incl. in Prop
Employee & Retiree Health Ins.
Intergovernmental Personal
$30,000/
Benefit Cooperative
$75,000
none
none
06/30/15
n/a
n/a
Varied
Third Party Administrators
Workers' Comp Claims Administration
ASC
Liability Claims Administration
Gallagher Bassett
I:\Insurance\Schedule of Coverage0ecember 31, 2014 xlsx
Attachment II
VILLAGE OF MOUNT PROSPECT
2015 INSURANCE RENEWAL
Percent Increase of Renewal 4.55%
Property Values
$ 92,717,046 $
Expiring
Renewal
Coverage Type / Values
2013
2014
2015
Property & Inland Marine
$ 99,466
$ 101,750
$ 104,615
Excess Workers Compensation
65,720
81,465
87,508
Gallagher Fee
12,382
12,382
12,382
Total
$ 177,568
$ 195,597
$ 204,505
Percent Increase of Renewal 4.55%
Property Values
$ 92,717,046 $
95,296,056
$ 98,062,237
Property Deductible
25,000
25,000
25,000
Auto Physical Damage Deductible
100,000
100,000
100,000
WC Self-insured Retention - General Employees
600,000
600,000
600,000
WC Self-insured Retention - Police/Fire
600,000
600,000
600,000
ji ±Loon[ Prospcc-t
Village of Mount Prospect
Mount Prospect, Illinois
INTEROFFICE MEMORANDUM
v r
TO: DAVID STRAHL, ACTING VILLAGE MANAGER l
FROM; FINANCE DIRECTOR
DATE: DECEMBER 9, 2014
SUBJECT: GENERAL AND AUTO LIABILITY THIRD -PARTY CLAIMS
ADMINISTRATION
PURPOSE:
To present a recommendation for renewal of the annual service agreement for third -
party liability claims administration for the period January 1, 2015 - December 31, 2015.
BACKGROUND:
To assist in the administration of general and auto liability claims the Village has
contracted out the service to a third -party administrator. The Village's current
agreement for claims administration expires on December 31, 2014. A new agreement
is needed at this time for the current provider to continue to service the Village.
DISCUSSION:
Gallagher Bassett (GB) is the current service provider for general and auto liability
claims administration. The agreement for 2015 contains no changes to the terms and
conditions from the prior year. Below is a summary of fees for the prior year and 2015.
Service..................._2014
Rates._....._
2014RatesClmaims..Administrati.on
.....................................................................1......0.8.2....._
......................................1�......._......1..25..
............_..._.........................._......_..............................................
SIMMS Bankinq Fee
:��..
410
......
434
M i n i m u.m...An..�.....������� .�m........ ........m.................
nual Fee
8..............................,.....
....................�.....
.m..... ......
w........w®..................�.m.�m.000 8m 000
.....................__.....................Tota.L...Fee.................................._�
........ ..........._W.......... $�.9._4.92...........................................................
$9....,55.9....
The claims administration fee increased 4.0% ($43) from the prior year's program. The
SIMMS Banking fee is an annual flat fee assessed for maintaining the escrow and
processing and making payment on claims. This service relieves the Village from
having to process payments internally. The SIMMS fee increased 5.9% ($24) from the
prior year's program.
General and Auto Liability Third -Party Claims Administration
December 9, 2014
Page 2
The Village is subject to an $8,000 minimum annual fee. Time and expense charges
are invoiced against the annual fee until the balance is exhausted. When the entire
annual fee is depleted, the Village will begin making payments for charges incurred in
managing the open claims. Our liability ends when all the claims for a particular period
are closed.
Our experience with GB continues to be very positive. Communication between the
Finance Department, Corporation Counsel and third -party claims administrator
continues to be strong. Based on our satisfaction with the service provided and modest
increase to the minimum annual fee I recommend we continue the relationship with GB.
RECOMMENDATION:
It is recommended we approve the agreement for GB to provide general and auto
liability claims administration services during 2015 according to the proposed funding
and fee schedule.
David O. Erb
Finance Director
DOE/
Attachment
I:\Insurance\GAB-GBS\Renewal - 2015.docx
Village of Mount Prospect - #007474
1 LAG1/1/2015 - 1/1/2016 '�1�� � �i,
PRICING OPTI : TIME & EXPENSE HANDLING
This program is quoted at a total minimum of $9,559 (including administration and banking fees).
WiltiUf�MWWN'WW mm wuww.wuuu .wu... w.W .... um..M 0n m 'm'uromoN uuuuiWwi�I�W4W4llY0N01�hWNVW,b1 NOWVWWWV�NOMONV@U4W4w�'k49tiNNtlom,A�'roWV4WW
New Business Cost & Terms Revision date: 6/27/2013) Page 1
Prospect
TO:
FROM:
DATE:
SUBJ:
Background
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
ACTING VILLAGE MANAGER DAVID STRAHL
DIRECTOR OF PUBLIC WORKS
DECEMBER 11, 2014
BID RESULTS FOR ISABELLA AREA SEWER IMPROVEMENTS
($8,863,088)
The 2011 Comprehensive Flood Study Report identified several sewer improvement projects for
areas subjected to severe, recurrent, and geographically concentrated flooding.
The first phase of these improvements (Phase 1 Improvements) involved storm sewer
improvements on SeeGwun Avenue, NaWaTa Avenue, Lawrence Lane, Hatlen Avenue, Hatlen
Court, Busse Road, Michael Street, Verde Drive, Bonita Avenue, and Audrey Lane. The Phase
1 Improvements also included ditch regrading and culvert replacement work in the Golfview
Estates residential subdivision. This work was facilitated by $2.5 million in short-term debt
issued in 2012. All of this work was designed and constructed in 2013.
The second, and final, phase of public sector work identified by the 2011 Comprehensive Flood
Study is the construction of a relief sewer system in the Isabella Street residential area. The
proposed scope of work for this project includes the installation of approximately 6,600 linear
feet of relief sewer ranging in size from 15" to 84" (and appurtenances) to provide a 25 -year
recurrence interval level of protection for approximately 800 single-family homes. Funding for
this work has been facilitated by $10 million in general obligation bond debt.
Bid Results
Plans and bid documents for this project were prepared by Burns & McDonnell consulting
engineers of Downers Grove, Illinois. Bids were let on October 17, 2014. A public notice was
placed in a local newspaper. Thirteen (13) sewer construction firms picked up bid documents
and eight (8) attended a mandatory pre-bid meeting on November 3, 2014. Bids were opened
and read aloud on November 24, 2014. Six (6) bids were received:
Bidder Bid Amount
A Lamp Concrete Contractors
$8,057,352.09
Martam Construction, Inc.
$9,057,012.40
Glenbrook Excavating & Concrete, Inc.
$9,290,734.73
John Ned Construction Company
$10,158,791.00
Bolder Contractors, Inc.
$11,111,193.27
Berger Excavating Contractors, Inc.
$12,563,144.73
Page 2 of 4
Bid Results for Isabella Area Sewer Improvements ($8,863,088)
December 11, 2014
The engineer's estimate of probable construction cost for this project is $10,052,725.
Discussion
All bids were properly signed, accompanied by appropriate bid bonds, and responsive to the bid
documents. All six (6) bidders attended the mandatory pre-bid meeting.
The apparent low -bidder is A Lamp Concrete Contractors of Schaumburg, Illinois (ALamp).
ALamp has performed work for the Village in the past. In 2009, ALamp was the general
contractor for the $2.7 million street resurfacing program. The paving work was subcontracted
to Arrow Road of Mount Prospect. However, ALamp was responsible for sub -base preparation,
concrete flatwork, structure adjustments, small -diameter storm sewer work, and overall project
management. ALamp's performance was acceptable. Work was completed on time and below
the project award amount.
Review of ALamp's bid submittal revealed several concerns about their ability to complete the
project. Among these concerns were disparaging references about project close-out,
housekeeping, and crew turnover; a lack of experience installing 84" diameter (or larger) pipe;
inordinately low bid prices for trench backfill, junction chamber reconstruction work, by-pass
pumping, and overall project cost; as well as unbalanced prices for mobilization and traffic
control.
On December 4, 2014, staff and design engineer Burns & McDonnell met with ALamp
representatives to discuss these concerns. These matters were disposed as follows:
Project Close-out, Housekeeping, and Crew Turnover. ALamp acknowledged these
issues and proposed they would avoid potential problems by permanently assigning their
best underground construction crew to this project. They also identified the project
foreman they planned to assign to this project and provided specific work references for
his crews. All references were acceptable with respect to timeliness, project close-out,
and housekeeping.
Lack of Experience Installing 84" Diameter (or larger) Pipe. ALamp provided acceptable
references for the installation of 60" diameter pipe and 48" diameter pipe. However,
approximately 30% of the work in this project involves the installation of larger pipe.
Notably, the work involves installing 1,000 feet of 72" diameter sewers and 2,000 feet of
84" diameter sewers. ALamp acknowledged this deficiency but advised that they
presently own and can adeptly operate the trench boxes, large backhoes, and other
equipment necessary to safely install the large pipe.
Inordinately Low Bid Price for Trench Backfill. ALamp's bid price for trench backfill is
approximately half the cost of other bidders. ALamp explained that they own a concrete
recycling facility and have the capability to manufacture their own trench backfill. They
Page 3 of 4
Bid Results for Isabella Area Sewer Improvements ($8,863,088)
December 11, 2014
further opined that this resource differentiates them from the other bidders and facilitates
lower costs for trench backfill.
Inordinately Low Bid Price for Junction Chamber Work. The project involves structural
concrete construction work on sewer junction chambers. ALamp's prices for this work
seem low considering the scope of work involved. Particularly, staff was concerned that
ALamp might not have properly assessed the trench shoring requirements and might not
fully appreciate the difficulties performing partial concrete demolition work on active
sewer structures. ALamp responded that they plan to subcontract this work to a
structural concrete contractor with relevant experience in these niche tasks. The
subcontractor is known to Burns & McDonnell as competent in this work. In addition,
staff reminded ALamp that shoring designs must be signed and sealed by a structural
engineer; they are also subject to Village review.
Inordinately Low Bid Price for Sewer By -Pass Pumping. An important component of the
project is facilitation of by-pass pumping that will enable construction on live combination
sewers. ALamp's bid price for this work is substantially lower than the costs of other
bidders and the engineer's estimate. ALamp acknowledged that the by-pass pumping
plan must accommodate both low and peak flows without surcharging. They further
explained that they own a variety of resources and were confident that they could
provide a by-pass pumping plan that will satisfy Village requirements.
Overall Project Cost is Exceptionally Low. ALamp's bid is approximately $1 million lower
than the second -lowest bidder and almost $2 million lower than the engineer's estimate
and median bid. ALamp stated that they can construct the improvements at the bid price
and within the contract time without additional compensation. They also opined that
vertical integration of key project components including trucking, traffic control, and
trench backfill along with advantageous supplier relationships allow them to be cost
competitive on this project.
Mobilization and Traffic Control Prices are Unbalanced. ALamp's bid prices for
mobilization and traffic control constitute approximately 25% of the project cost. This
allocation of costs is unusual and could be construed as a means to be compensated at
a rate that exceeds value added. Staff advised ALamp that these pay items would be
paid pursuant to Illinois Department of Transportation (IDOT) standard procedures. As a
consequence, much of the money attributed to these pay items will not be eligible for
payout until the end of the project. ALamp acknowledged understanding of the Village's
position on this matter.
As a result of this meeting, staff is satisfied that aforementioned concerns can be effectively
managed. It is also the opinion of staff that ALamp can construct the improvements at the price
quoted and within the time frame specified in the bid documents.
Page 4 of 4
Bid Results for Isabella Area Sewer Improvements ($8,863,088)
December 11, 2014
Staff also recommends that the award for this project include a 10% contingency to
accommodate quantity variances and unforeseen conditions commonly associated with
underground work. The total recommended project award is $8,863,088 ($8,057,352.09 base
bid + $805,735.91 contingency).
Recommendation
I recommend that the Village Board accept the lowest cost bid for the Isabella Area Sewer
Improvements as submitted by Al -amp Concrete Contractors, Inc., of Schaumburg, Illinois in an
amount not to exceed $8,863,088. Sufficient funds for this propo d expenditure exist in the
current budget.
can P. Dorsey
Cc: Director of Finance David Erb
Deputy Director of Public Works Jason Leib
Water/Sewer Superintendent Matt Overeem
Streets/Buildings Superintendent Paul Bures
Village Engineer Jeff Wulbecker
Administrative Superintendent Kristina Jakupovic
Traffic Engineer Matt Lawrie
Project Engineer Joel Michalik
File
TO:
FROM:
DATE:
SUBJ:
Background
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
ACTING VILLAGE MANAGER DAVID STRAHL
DIRECTOR OF PUBLIC WORKS
DECEMBER 11, 2014
CONSTRUCTION ENGINEERING FOR ISABELLA AREA SEWER
IMPROVEMENTS ($672,799)
Staff asked Burns & McDonnell consulting engineers of Downers Grove, Illinois for a proposal to
provide specified construction engineering services for the Isabella Area Sewer Improvements
Project. The scope of work requested stipulated full-time supervision of multiple construction
crews for the contract term, project administration, material testing, and pre/post construction
videography of the project area.
Proposal
Burns & McDonnell has submitted a cost proposal to provide the requested professional
services at a cost not to exceed $672,799.
Discussion
Staff has reviewed Burns & McDonnell's proposal and determined that they have allotted
adequate, qualified resources necessary to monitor all phases of work and administer the
construction contract. In addition, their cost proposal includes appropriate allocations for
requisite sub -contracted technical assistance including laboratory materials testing services and
construction site videography.
Burns & McDonnell has successfully performed a variety of civil engineering projects for the
Village over the course of 20 years.
Of particular relevance to this project is their experience with the 2011 Comprehensive Flood
Study. Burns & McDonnell authored that study and developed its recommendations; including
all of the Phase 1 and Phase 2 projects. They were also the design engineers for the Isabella
Area Sewer Improvements project.
Because of this experience, Burns & McDonnell is intimately familiar with the Village's sewer
systems, drainage patterns, and, most importantly, the flooding problems endured by Mount
Prospect residents.
Page 2 of 2
Construction Engineering for Isabella Area Sewer Improvements ($672,799)
December 11, 2014
The Burns & McDonnell fee is approximately 8% of the low bid cost for construction and
approximately 7% of the median bid price. Typically, we expect construction engineering fees
to be 8%-10% of construction costs. As such, Burns & McDonnell's fee appears reasonable.
Burns & McDonnell staff, including the project manager Randy Patchett, and senior civil
engineer Steve Crede have established relationships with residents that will be impacted by
these proposed improvements.
Consequently, it is our opinion that Burns & McDonnell is uniquely, arguably exclusively, well
qualified to provide construction engineering services for these improvements.
Recommendation
I recommend that the Village Board accept the proposal from Burns &i McDonnell consulting
engineers of Downers Grove, Illinois, to provide specified construction gineering services for
the Isabella Area Sewer Improvements for a fee not to exceed $672,79
n P. Dorsey
Cc: Director of Finance David Erb
Deputy Director of Public Works Jason Leib
Village Engineer Jeff Wulbecker
Water/Sewer Superintendent Matt Overeem
Streets/Buildings Superintendent Paul Bures
Administrative Superintendent Kristina Jakupovic
Project Engineer Joel Michalik
Traffic Engineer Matt Lawrie
File
Mount
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
TO: ACTING VILLAGE MANAGER DAVID STRAHL
FROM: VEHICLE/EQUIPMENT MAINTENANCE SUPERINTENDENT
DATE: DECEMBER 4, 2014
SUBJECT: ACCEPT NJPA BID FOR THE PURCHASE OF ONE (1) NEW 70'
REARMOUNT AERIAL TRUCK WITH FLATBED BODY ($182,500.00)
Background
In the current budget, there are sufficient funds available to replace unit 4541. 4541 is a 1997
International 4900 with a flatbed body and 55' Aerial Lift of Connecticut (ALC) used by the
Public Works Department's Forestry Division. This truck is primarily utilized for maintaining
the Village's parkway tree population (tree trimming, tree removals, cabling, inspections, etc.).
Our current aerial unit is well liked by many operators/mechanics, but unfortunately they went
out of business several years ago. In preparation of selecting the appropriate unit, we inspected
several aerial trucks from various Villages and local tree companies over the past year. The
Forestry Division also wanted to make sure the aerial selected would have the over -center
capability, higher working height, and greater side reach compared to our current unit. The
additional 15 feet of working height and greater side reach is necessary as age and crowns of our
tree population have grown larger in the seventeen years since this truck was purchased.
Replacement Policy
This vehicle has been evaluated utilizing our detailed comprehensive replacement policy. This
policy uses a point -based criterion, which rates the following four (4) major factors to a baseline
when considering a unit for replacement: Age, mileage, repair & maintenance (R&M) cost, and
condition of the body/mechanical components. A point total equaling or exceeding eleven (11)
out of sixteen (16) indicates that the vehicle should be recommended for replacement.
This vehicle scored a total of fifteen (15) points indicating a high rating and should be placed on
the highest priority to be replaced. The vehicle condition evaluation form and summary report
have been attached as Exhibits A and B respectively. Additionally, I have included the life cycle
cost analysis on Exhibit C, which breaks out our total ownership cost.
Other Factors
If the service life is extended the following repairs should be performed:
➢ Refurbish/paint rear body and rusted sheet metal $3,500.00
➢ Replace brakes, springs and king pins $5,200.00
➢ Aerial bull gear, cables and upper boom $20,000.00
Total estimated cost: $28,700.00
Accept NJPA Bid for the Purchase of one (1) New 70' Reaimount Aerial Truck with Flatbed Body ($182,500.00)
December 3, 2014
Page 2 of 2
Discussion
There is no local or State purchasing program for this vehicle. However, Public Works is part of
a national joint purchase cooperative, the National Joint Powers Alliance (NJPA), through which
the Village can procure this vehicle from Altec Industries. The Altec model we recommend
purchasing is a LR7-60E74RM, which includes an International 4300 chassis. The International
truck chassis closely matches the rest of Public Works heavy duty truck fleet.
Bid Recommendation
I am recommending the Village Board accept the NJPA bid Contract Award #031014 and
authorize the purchase of one (1) new 70' Rearmount Aerial Truck with Flatbed Body, from
Altec Industries, of Birmingham, Alabama at a cost not to exceed $182,500.00. The NJPA
Contract is publicly bid and satisfies the public bidding requirements of the Village of Mount
Prospect Purchasing Policy.
Funds for this proposed purchase are funded through the Vehicle Replacement Fund and are
available in the 2014 budget.
The vehicle being replaced will be sold through the GovDeals.com Internet auction.
?mes R. Breitzman
Vehicle/Equipment Superintendent
I concur.
Sean P.
of Public Works
JB
Attachments
C: Deputy Director of Public Works Jason Leib
H:\Administration\BIDS\RESULTS\4541-NJPA BID Purchase, 12-2014.docx
Unit # 4541
Year: 1997
Hours: 13,165
EXHIBIT A
Village of Mount Prospect
Vehicle/Equipment Condition Evaluation Form
Assigned Dept. /Div. Public Works/Forestry
Make: International Model: 4900 Mileage: 58,200
Date of Evaluation: 12/2/14 Performed By: Jim Breitzman
System
Diagnosis
Estimated Repair Cost
Engine
Fair
Possible rebuild in future
Transmission
Fair
Possible rebuild in future
Differential
Good
Exhaust System
Good
Cooling System
Good
Brakes
Fair -Shoes, Drums
$1,200.00
Tires
Good
Steering
Fair -King Pins
$1,000.00
Suspension
Fair -Springs
$3,000.00
HVAC
Good
Electrical
Good
Body/Frame
Fair-Refurbish/Paint
$3,500.00
Interior
Good
Other- ALC Aerial
Total Estimated Repair Cost
Fair -Bull Gear, Drive Cables,
Fiberglass Upper Boom
$20,000.00
$28,700.00
Diagnosis Code
Code Description
Good
Systems are functioning well and no major repairs are expected.
Fair
Some major repairs are needed, but unit can remain in service a little longer
in current condition.
[P-0or
Major repairs are required as soon as possible to ensure unit safety and
reliability.
1 *3 0111 i
Village of Mount Prospect
Vehicle/Equipment Evaluation Summary Report
Unit # 4541 Assigned Dept. /Div. Public Works/Forestry
Year: 1997 Make: International Model: 4900 Mileage: 58,200
Date of Evaluation: 12/2/14 Performed By: Jim Breitzman
Ratings:
Unit age: 17 Base Policy Age: 15
Mileage/Hrs: 58,200/13,165 Base Policy Mileage/Hrs: 50,000/9,000
Maintenance Cost:
Repair and Maintenance Cost: $ 68,836 _ Purchase Price: $ 97,005
Repair and Maintenance Percentage of Purchase Price: 71 %
Condition Evaluation: (attach Vehicle Condition Evaluation Form)
Estimated Repair Cost: $ 28,700 - Current Book Value: $ 12,000
Repair Cost Percentage of Current Book Value: 239 %
Total Ownership Cost Per Mile:
(Lifetime Fuel + R&M + Purchase Price) $ 202,641
Less Salvage Value $ 12,000
Net Lifetime Costs $ 190,641
Divided by Mileage Hours 58,200
Operating Cost Per Mile/Hour $ 3.28
Points: 3
Points: 4
Points: 4
Points: 4
otal Points: 15
Comments and other considerations:
This vehicle has operated 13,165 hours during its lifetime which equals 394,950 engine miles.
Superintendent's recommendation:
This vehicle has well exceeded its life expectancy and major repairs will be needed if service life
is extended any longer based on condition.
Total Point Evaluation: A point total equaling or exceeding eleven (11) indicates that the vehicle should be
recommended for replacement. The point total is used to rank its replacement priority. The larger the number the
higher the replacement priority will be.
EXHIBIT C
Village of Mount Prospect
December 2014 Vehicle/Equipment Life Cycle Cost Analysis
Vehicle/Equipment Number - 4541 (1997 International 4900, 55' Aerial)
--O—Total Ownership Costs
Life Cycle Costs —A— Total R&M
—0 Total Fuel
■ - Market Value
$200,000.00 �,,� $202,641.00
$150,000.00
N
Year
Total Ownership Cost - Salvage Value / Mileage = Cost Per Mile to Operate
$202,641.00 $12,000.00 58,200 $3.28
Mount Prospect Public Works Department
INTEROFFICE MEMORANDUM
TO: ACTING VILLAGE MANAGER DAVID STRAHL
FROM: VEHICLEXQUIPMENT MAINTENANCE SUPERINTENDENT
DATE: DECEMBER 9, 2014
SUBJECT: RFP RESULTS FOR ALTERNATIVE FUEL STUDY ($39,135.00)
BACKGROUND
In October 2014, Public Works requested proposals for an alternative fuel study of the Village's
municipal fleet in an effort to examine the potential for fuel expenditure reductions and
environmental improvements utilizing alternative fuels. The following scope of work was
requested in the RFP:
• Assessment of the Village's fleet, define the feasibility and advantages of conversion to
an alternate fuel without sacrificing safety and service. A complete list of vehicles will be
provided upon contract approval.
• Alternative fuel sources should include compressed natural gas, liquid petroleum gas, all
electric and hybrid.
• Feasibility of constructing an alternative fueling station in the Village and the estimated
cost to construct. Include the time needed to fuel a single vehicle for various fuels.
• Provide information of any grant, rebate or incentive programs offered by the State or
Federal government.
• Provide cost analysis to retrofit vehicles for alternative fuels.
• Identify any necessary alterations and associated costs needed to the Public Works
vehicle maintenance area to accommodate the repair and maintenance of alternative
fueled vehicles.
• Estimate the regular maintenance costs of a fleet utilizing alternative fuels.
• Define impacts of converting to alternative fuels on drivers/mechanics daily routines and
changes associated with alternative fuel vehicles.
o Fueling (charging) logistics based on Village's vehicle use
o Impacts on driver's /Village's daily processes
o Repair and maintenance, including training
• Define safety considerations for use of alternative fuels
• Define matrix of investment requirements for Village Fleet needs:
o Vehicle change alternatives (fuel type, convert or buy new)
o Fueling infrastructure options
o Operation and maintenance facilities
o Vehicle repair and maintenance
Page 2 of 3
RFP Results for Alternative Fuel Study ($39,135.00)
December 9, 2014
o Site candidates
o Utility infrastructure
• Model Return on Investments (RO" for 111'�Icycic cost matrix of vehicles. and
infrastructures for Village Fleet
• Compile data, analyses and recommendation into Final Study Report
• All recommendations should include data indicating the expected return on investment.
Staff requires assistance from a qualified and experienced fleet consultant to determine the
advantages of alternative fuel sources for the purpose of reducing the overall life cycle cost of
our fleet. Ultimately, the selected consultant will create a final report denoting opportunities for
alternative fuel implementation and recommendation as the most advantageous course of action
for the Village. This report will be presented to the Village Board in the spring 2015.
REQUEST FOR PROPOSALS
Chapter 4 of the village's purchasing policy and procedures manual states:
F. Requests for Professional Services
Some contracts, by their nature, are not adapted to award by competitive bidding. These
contracts generally result from a request for proposal (RFP). A request for proposal is
utilized when professional services are being sought such as engineering, legal, audit, or
consulting services.
Pursuant to this policy, staff requested proposals for an alternative fuel study from eight (8)
qualified consultants. We received five (5) responses from Mercury Associates of Rockville,
MD, Chatham Consulting, Inc. of Chatham, NJ, Energetics of Columbia, MD, Green Ways 2Go
of Park Ridge, IL, and MCB Fleet Management of St. Simmons, GA.
These consultants submitted documentation that indicated their ability to perform the necessary
services. All of the consultants also included references for past work and qualifications of
personnel who will be analyzing our fleet and suggesting any opportunities for alternative fuel
implementation.
All five (5) firms were evaluated and selected top two (2) interviewed utilizing the following
weighted criteria:
Criteria
Response to proposal request
Points
10
Education and experience of key personnel
25
Project understanding, implementation plan, and methods
25
Experience on similar projects
25
Total cost of proposed study
15
Total
100
Page 3 of 3
RFP Results for Alternative Fuel Study ($39,135.00)
December 9, 2014
With a maximum best score of 100 points possible, the proposals and interviews were rated
yielding the following results:
Discussion
Staff established that Mercury Associates, Inc. was the most qualified firm that can perform the
necessary services within budget limits.
It is noteworthy that Mercury Associates has experience working with local Illinois government
fleets, which includes the Cities of Springfield, Lake Forest, Highland Park, Kane County and
the Village of Buffalo Grove.
Their cost proposal for the specified work is a not to exceed amount of $39,135.00. This amount
includes all professional services and out-of-pocket expenses and is based on 235 hours of work.
It is the opinion of staff that the work hours allotted are reasonable, including the rate of $150-
$200/hour is competitive.
RECOMMENDATION
I recommend that the Village Board accept the proposal for the Alternative Fuel Study from
Mercury Associates, Inc. of Rockville, MD in an amount not to exceed $39,135.
'ames R. Breitzman
Vehicle/Equipment Superintendent
JB
C: Deputy Director of Public Works Jason Leib
H:\Administration\ALT FUEL STUDY PROPOSALS\RFP Results for Alt Fuel Study, 12-2014.docx